SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(P&H) 52

IN THE HIGH COURT OF PUNJAB AND HARYANA
Arun Palli, Vikram Aggarwal, JJ.
Parsvnath Developers Limited - Appellant
Versus
Brig. Devendra Singh Yadav & Ors. – Respondents
FAO (CARB) No. 28 of 2022
Decided On : 20-01-2025

Advocates Appeared:
Mr. Puneet Bali Senior, Advocate, Ms. Bhagyashri setia Adv., Mr. Rajat Joneja Adv., Mr. Tarun Khaira Adv., Mr. Siddharth Yadav Senior, Advocate, Mr. Manav Bajaj Adv., Mr. Narender Adv.

Venue of arbitration does not equate to its jurisdictional seat; petitions under the Arbitration Act must be filed where arbitration took place, as established in prior Supreme Court rulings.

Headnote:(A) Code of Civil Procedure, 1908 - Order VII Rule 10; Arbitration and Conciliation Act, 1996 - Sections 2(1)(e)(i), 34, 37 - Maintainability of appeal - Court dismissed appeal for lack of jurisdiction, ruling that venue of arbitration does not define its seat, relying on BGS SGS Soma JV v. NHPC Limited (2020) 4 SCC 234; Jurisdiction to entertain Section 34 petition lies only with the court at Delhi where arbitration proceedings were conducted. (Paras 1, 17, 20)

(B) Finality of Orders - The appeal was dismissed solely on the issue of maintainability without delving into the merits, highlighting that procedural aspects of jurisdiction supersede substantive claims. (Paras 2, 20)

Facts of the case:
The appellant challenged the District Judge's ruling that returned its Section 34 petition for lack of jurisdiction, asserting it should be heard in Rewari based on the collaboration agreement's terms.

Findings of Court:
The High Court upheld conclusions regarding the non-maintainability of the appeal per Supreme Court precedence, affirming procedural jurisdiction which limits appeal options.

Issues: The main issues included the appropriateness of filing Section 34 appeals at Rewari rather than Delhi and whether the collaboration agreement specified jurisdiction.

Ratio Decidendi: The court emphasized that the venue where arbitration occurs does not necessarily define the seat of arbitration, maintaining that jurisdiction must align with where proceedings are conducted, reinforcing earlier Supreme Court judgments.

Result: Appeal dismissed.

Table of Content
1. maintainability of the petition under section 34 (Para 1 , 2)
2. factual basis of the arbitration agreement (Para 3 , 4 , 5)
3. jurisdiction issues in arbitration (Para 6 , 7)
4. court's approach to legal arguments (Para 8 , 13 , 14)
5. arguments from both parties on jurisdiction (Para 9 , 10)
6. supreme court precedents on appeal maintainability (Para 11 , 15 , 16 , 17 , 18 , 20)

JUDGMENT :

Vikram Aggarwal, J.

The appellant (M/s Parsvnath Developers Limited) assails the order dated 06.08.2022 passed by the Court of learned District Judge Rewari, vide which the application preferred by the respondents under Order VII Rule 10 read with Section 151 of the Code of Civil Procedure, 1908 (for short the “CPC”) read with Section 2 (1)(e)(i) of the Arbitration and Conciliation Act, 1996 (for short the “1996 Act”) seeking return of the objection petition preferred by the present appellant under Section 34 of the 1996 Act was allowed and the petition preferred under Section 34 was ordered to be returned for being presented in the competent Court.

2. The appeal raises an interesting, often debated but short question, for which extremely lengthy arguments were addressed by both sides. The question to be decided is as to whether the petition preferred by the appellant under Section 34 of the 1996 Act challenging the Award dated 21.09.2020 passed by the Arbitral Tribunal would be maintainable at Rewari or the same would have to be filed at Delhi, where the arbitration proceedings were conducted. The issue of “venue” and “seat” has once again been raised by the parties which this Court shall proceed to discuss and answer.

3. A collaboration agreement (Annexure A-2) was executed on 27.10.2005 between the respondents, who were owners in possession of land measuring approximately 54 acres, situated in Village Dharuhera, District Rewari and the appellant (M/s Parsvnath Developers Limited) being a developer. It was agreed that the land in question would be developed by the developer into a residential colony on mutually agreed terms. Various terms and conditions were agreed upon between the parties.

4. It appears that as is the case in many such other similar agreements, certain issues cropped up between the parties leading to the filing of a petition under Section 9 of the 1996 Act (Annexure A-3) by the respondents. The said petition was opposed by way of reply (Annexure A-4). Ultimately, the petition was allowed vide order dated 04.11.2015 (Annexure A-5) holding as under:

    “25. This, however, will not mean that the court will not take any interim measure. To my mind, the purpose can be served by issuing following directions:-

    (i) The respondent, in order to secure damages, if any, to be awarded by the arbitrator, shall not sell 10% of the residential plots falling to its share;

    (ii) If the respondent wants to transfer/alienate the project to a third party after leaving aside 10% of the residential plots in terms of condition No.1 above, in that eventuality, there shall be a condition in agreement to be executed with that third party that it shall be bound to complete the development work and to discharge other obligations under the collaboration agreement. Such a condition shall, however, be not necessary while selling individual plots in retail. In other words, the condition will be necessary when the entire project or a major part of the project is to be alienated en-block.

    26. The petition stands disposed of in terms of the above directions which shall hold good for a period of 90 days from today within which arbital proceedings have to commence or till any further directions are issued by the arbital tribunal whichever is later. Needless to say that in case the arbital proceedings are not commenced within 90 days, the directions will cease to operate.”

It would be significant to mention here that till this stage, no issue of jurisdiction of the Courts had cropped up between the parties.

5. It is apparent that the project ran into rough

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top