IN THE HIGH COURT OF PUNJAB AND HARYANA
Arun Palli, Vikram Aggarwal, JJ.
Parsvnath Developers Limited - Appellant
Versus
Brig. Devendra Singh Yadav & Ors. – Respondents
FAO (CARB) No. 28 of 2022
Decided On : 20-01-2025
| Table of Content |
|---|
| 1. maintainability of the petition under section 34 (Para 1 , 2) |
| 2. factual basis of the arbitration agreement (Para 3 , 4 , 5) |
| 3. jurisdiction issues in arbitration (Para 6 , 7) |
| 4. court's approach to legal arguments (Para 8 , 13 , 14) |
| 5. arguments from both parties on jurisdiction (Para 9 , 10) |
| 6. supreme court precedents on appeal maintainability (Para 11 , 15 , 16 , 17 , 18 , 20) |
JUDGMENT :
Vikram Aggarwal, J.
The appellant (M/s Parsvnath Developers Limited) assails the order dated 06.08.2022 passed by the Court of learned District Judge Rewari, vide which the application preferred by the respondents under Order VII Rule 10 read with Section 151 of the Code of Civil Procedure, 1908 (for short the “CPC”) read with Section 2 (1)(e)(i) of the Arbitration and Conciliation Act, 1996 (for short the “1996 Act”) seeking return of the objection petition preferred by the present appellant under Section 34 of the 1996 Act was allowed and the petition preferred under Section 34 was ordered to be returned for being presented in the competent Court.
2. The appeal raises an interesting, often debated but short question, for which extremely lengthy arguments were addressed by both sides. The question to be decided is as to whether the petition preferred by the appellant under Section 34 of the 1996 Act challenging the Award dated 21.09.2020 passed by the Arbitral Tribunal would be maintainable at Rewari or the same would have to be filed at Delhi, where the arbitration proceedings were conducted. The issue of “venue” and “seat” has once again been raised by the parties which this Court shall proceed to discuss and answer.
3. A collaboration agreement (Annexure A-2) was executed on 27.10.2005 between the respondents, who were owners in possession of land measuring approximately 54 acres, situated in Village Dharuhera, District Rewari and the appellant (M/s Parsvnath Developers Limited) being a developer. It was agreed that the land in question would be developed by the developer into a residential colony on mutually agreed terms. Various terms and conditions were agreed upon between the parties.
4. It appears that as is the case in many such other similar agreements, certain issues cropped up between the parties leading to the filing of a petition under Section 9 of the 1996 Act (Annexure A-3) by the respondents. The said petition was opposed by way of reply (Annexure A-4). Ultimately, the petition was allowed vide order dated 04.11.2015 (Annexure A-5) holding as under:
(i) The respondent, in order to secure damages, if any, to be awarded by the arbitrator, shall not sell 10% of the residential plots falling to its share;
(ii) If the respondent wants to transfer/alienate the project to a third party after leaving aside 10% of the residential plots in terms of condition No.1 above, in that eventuality, there shall be a condition in agreement to be executed with that third party that it shall be bound to complete the development work and to discharge other obligations under the collaboration agreement. Such a condition shall, however, be not necessary while selling individual plots in retail. In other words, the condition will be necessary when the entire project or a major part of the project is to be alienated en-block.
26. The petition stands disposed of in terms of the above directions which shall hold good for a period of 90 days from today within which arbital proceedings have to commence or till any further directions are issued by the arbital tribunal whichever is later. Needless to say that in case the arbital proceedings are not commenced within 90 days, the directions will cease to operate.”
It would be significant to mention here that till this stage, no issue of jurisdiction of the Courts had cropped up between the parties.
5. It is apparent that the project ran into rough
BGS SGS Soma JV V/s NHPC Limited (2020) 4 SCC 234
Indus Mobile Distribution Pvt. Ltd. V/s Datawind Innovations Pvt. Ltd.
Swastik Gases Private Limited V/s Indian Oil Corporation Limited
Hemsukh Prajapati V/s Jai Prakash Associates Limited
State of Maharashtra V/s Atlanta Limited
SBP & Co. V/s Patel Engineering Ltd. and another
Bharat Aluminum Company V/s Kaiser Aluminum Technical Services Inc.
Union Bank of India V/s Hardy Exploration and Production (India)
Mankastu Impex Private Limited V/s Airvisual Limited
Hindustan Construction Company Limited and another V/s Union of India and others
Venue of arbitration does not equate to its jurisdictional seat; petitions under the Arbitration Act must be filed where arbitration took place, as established in prior Supreme Court rulings.
Power to refer parties to arbitration where there is an arbitration agreement - Application of any of the parties to the suit, withdraw such suit or application from the court before which it is pend....
The jurisdiction for appeals regarding arbitration awards under the Arbitration and Conciliation Act lies with the Commercial Appellate Court as prescribed by the Commercial Courts Act, 2015, superse....
The designated seat of arbitration establishes exclusive jurisdiction for related applications, affirming that the Commercial Court in Ranchi has jurisdiction over Section 34 applications.
The court established that challenges to an arbitrator's jurisdiction under Section 16 can only be raised after a final award, not as an interim appeal.
Granting or refusing to grant any measure and set aside an arbitral award - No final adjudication of Section 9 application nor does impugned order finally decide same - Decision in application under ....
The main legal point established in the judgment is that the appealability of orders pertaining to the Arbitration and Conciliation Act must be determined as per the drill under Section 50 alone, and....
A memorandum of settlement does not attain finality and is not executable as an award under the Arbitration Act; therefore, an appeal against a refusal to execute such an award is not maintainable un....
The main legal point established in the judgment is that appeals would only lie from the orders mentioned in Section 37 of the arbitration and Conciliation act, 1996, and from no others. Additionally....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.