PUNJAB AND HARYANA HIGH COURT AT CHANDIGARH
JASGURPREET SINGH PURI, J.
Jalandhar Improvement Trust And Others - Appellant
Vs.
Shourya Towers Private Limited - Respondent
CR-6014-2025 (O&M)
Decided On : 06-11-2025
| Table of Content |
|---|
| 1. civil revision petition filed (Para 1 , 2 , 3 , 4) |
| 2. proceedings of the arbitral tribunal (Para 5 , 6 , 7 , 8 , 9 , 10) |
| 3. impugned orders by arbitrator (Para 11 , 12) |
| 4. arguments by petitioners' senior counsel (Para 13 , 14 , 15 , 16) |
| 5. respondents' arguments against petitioners (Para 17 , 18 , 19 , 20 , 21 , 22 , 23 , 24) |
| 6. court's analysis and observations (Para 30 , 31 , 32 , 33 , 44 , 45) |
| 7. dismissal of revision petition (Para 48) |
JUDGMENT :
Jasgurpreet Singh Puri, J.
The present is a Civil Revision Petition filed under Article 227 of the Constitution of India seeking quashing of the order dated 09.04.2025 (Annexure P-11) passed by learned Sole Arbitrator whereby the right to file the statement of defence as well as the counter claim of the petitioner has been struck off by invoking the provisions of Section 25 (b) of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as 'the Arbitration Act'). Further prayer has been made for setting aside of the impugned order dated 12.08.2025 (Annexure P-18) passed by learned Sole Arbitrator whereby the application filed by the petitioner for recalling of the aforesaid order dated 09.04.2025 has been rejected.
Factual Matrix
2. Brief facts of the present case are that there was an Agreement between petitioner No.1 i.e. Jalandhar Improvement Trust and the respondent-Contractor pertaining to construction of towers and thereafter, a dispute arose between the parties. Since there was a valid arbitration clause in the aforesaid Agreement and the mechanism for appointment of an Arbitrator had failed, the respondent-Contractor filed an application before this Court for appointment of an Arbitrator under the provisions of Section 11 (6) of the Arbitration Act which was allowed by a Co-ordinate Bench of this Court vide order dated 30.08.2024 (Annexure P-3) and a former Judge of this Court was appointed as a Sole Arbitrator by way of the aforesaid order.
3. Learned Sole Arbitrator initiated the proceedings vide Annexure P-4 on 27.09.2024 and on that date, it was directed that the Power of Attorneys on behalf of the parties be filed by the next date of hearing and the counsel for the claimant (who is the respondent in the present petition) appeared and one Inderpal Singh, Trust Engineer along with Mandeep, Assistant, Trust Engineer also appeared and stated before the learned Arbitrator that Executive Officer of Trust will represent all the respondents in the matter. In the aforesaid first sitting of the learned Arbitrator, the procedure to be followed during the course of arbitration proceedings was also recorded in consultation with both the parties and in this way, a procedure was formulated which is also attached vide Annexure-I of Annexure P-4 in the present petition. The aforesaid order (Annexure P-4) is reproduced as under:-
'Annexure P-4
BEFORE THE ARBITRAL TRIBUNAL COMPRISING OF SOLE ARBITRATOR MR. JUSTICE RAJIV SHARMA (RETD.)
Arbitration Case No. 269 of 2020
In the matter of Arbitration:
BETWEEN
Shourya Towers Pvt. Ltd. Registered Office at B-111. Sector 5, Noida, UP through its authorized representative Sh. Mohit Garg. ..Claimant
AND
1. Jalandhar Improvement Trust, Jalandhar.
2. Chairman, Jalandhar Improvement Trust.
3. Punjab Local Body Government, Government of Punjab,Plot No.3, Dakshin Marg, Sector 35-A, Chandigarh
4. Director, Punjab Local Body Government, Government of Punjab, Plot No.3, Dakshin Marg, Sector 35-A, Chandigarh ...Respondents
Present: Mr. Himanshu Gupta, Advocate with Mr. Ankur Jain, Director, Shourya Towers Pvt. Ltd. for the claimant.
Mr. Inderpal Singh, Trust Engineer, Mr. Mandeep, Assistant, Trust Engineer for the respondents
Chandigarh.
Dated: 27th September, 2024
ORDER
1. Power of Attorneys on behalf of the parties be filed by the next date of hearing. Mr. Inderpal Singh, Trust Engineer submits that Executive Officer of Trust will represent all the respondents in the matter.
2. The parties in consultation with the Arbitral Tribunal have agreed to th
Srei Infrastructure Finance Limited Vs. Tuff Drilling Private Limited
M/s SBP & Company Vs. Patel Engineering Ltd. & Another
M/s Deep Industries Limited Vs. Oil and Natural Gas Corporation Limited
Failure to file a statement of defense within the statutory period under the Arbitration Act results in forfeiture of that right, emphasizing the necessity for timely compliance in arbitral proceedin....
The main legal point established in the judgment is the arbitrator's duty to inform the claimant of their failure to communicate their claim and to provide an opportunity to show sufficient cause, an....
The Arbitrator has jurisdiction to consider recall of a termination order if sufficient cause is shown for non-filing of claims, reinforcing judicial support for arbitral processes. The defaulting pa....
Once arbitration has commenced in the arbitral tribunal, parties have to wait until the award is pronounced unless, of course, a right of appeal is available to them under Section 37 of the Act even ....
Judicial review under Article 227 can intervene in arbitration matters to ensure justice, particularly regarding the acceptance of amendments and additional documents.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.