HIGH COURT OF SIKKIM
Bhaskar Raj Pradhan, J.
The District Collector & Ors. - Appellants
Versus
Raj Balam Prasad - Respondent
C.R.P. No. 02 of 2023
Decided On : 10-10-2023
| Table of Content |
|---|
| 1. title and possession of land (Para 1) |
| 2. jurisdictional objections and pleadings (Para 2) |
| 3. trial court's procedural ruling (Para 3 , 5) |
| 4. limitation issues raised by defendants (Para 4 , 6) |
| 5. criteria for plaint rejection under cpc (Para 7 , 8 , 9) |
| 6. revenue order no.1 and scope (Para 10) |
| 7. validation of trial court's ruling. (Para 11) |
| 8. duty of courts in adjudicating on plaints. (Para 12) |
| 9. cause of action and jurisdiction (Para 13 , 14) |
| 10. final judgment and dismissal of petition (Para 15) |
JUDGMENT
Bhaskar Raj Pradhan, J. - The respondent, Raj Balam Prasad (plaintiff) filed Title Suit No. 11 of 2021 against the revisionist nos. 1 to 3 (defendants). It was the respondent's case that plot no.42 with an area of 0.0200 hectares (suit land) was provided to his father by late Zigmee Wangyal Lassopa in the year 1985 and after the demise of his father the suit land came to his possession with the consent of Jolly Wangyal Lassopa, son of late Zigmee Wangyal Lassopa. The respondent constructed two storied RCC structured in the suit land with the consent of Jolly Wangyal Lassopa who is the title holder of the suit land. The two storied RCC structure is in the respondent's possession and occupation but there is no change in ownership and title of the suit land as it is a Bhutia/Lepcha land. When the respondent constructed the two storied RCC structure no one including the Government objected to it and the Power Department in fact provided electricity supply. During 2008 the Town Planner blamed the respondent that he had constructed the two storied RCC structure on the suit land by encroaching State Government drain from west side of the suit land. The respondent requested the Town Planner to employ an Amin to verify the status of the suit land but it was not considered. During 2016 the Town Planner again raised the same allegation. The Town Planner also objected on the ground that the RCC structure was built without any approved blue print plan. The respondent made applications for regularization of the encroached portion, if any, but to no avail. On 10.09.2021 the revisionist no.2 (defendant no.2) i.e. the Principal Chief Town Planner issued a demolition notice to demolish the structure within 15 days of the issuance of the demolition notice. In such circumstances, the respondent approached the Court of the learned Civil Judge seeking the following substantial reliefs:
'(a) A decree with declaration and confirmation that the plaintiff has not encroached any portion of Government land as alleged by the defendants while having his RCC structure on plot no.42.
(b) A decree with the declaration that the demolition order dated 10.09.2021 providing 15 days time to the plaintiff is unjust, illegal and causing harassment to the plaintiff and hence to be rejected.' (Sic)
2. During the trial the revisionists filed a petition under Order 7 Rule 11(d), sections 9 and 151 of the Code of Civil Procedure, 1908 (CPC) for rejection of the plaint. The petition was filed on the following grounds:-
(i) The jurisdiction of the Civil Court is barred by the Sikkim Allotment of House Sites and Construction of Building (Regulation and Control) Act, 1985 (the Act of 1985).
(ii) Section 9 of the CPC bars the filing of the plaint.
(iii) The plaint is also barred by Revenue Order No.1.
3. The petition under Order 7 Rule 11 (d) of the CPC was heard by the learned Civil Judge and rejected. During the hearing, as reflected in the impugned order, no plea of limitation was raised by the revisionists and therefore, not considered.
4. The learned Additional Advocate General for the revisionists submitted that the suit is barred by Article 58 of the LIMITATION ACT , 1963 as the right to sue first accrued in favour of the respondent, as per paragraph 5 of the plaint, in the year 2008 itself. The learned Additional Advocate General also relied upon the demolition notice dated 10.09.2021 which records the issuance of another demolition notice on 11.03.2011. It is
The court affirmed that a Civil suit is maintainable when a demolition notice is contested, emphasizing that limitations apply only where expressly provided, allowing full examination of possession c....
The main legal point established in the judgment is that at the stage of considering an application under Order VII Rule 11 of the CPC, the trial Court need not conduct a roving inquiry into the fact....
The main legal point established in the judgment is that the right to sue first accrues when the fact first comes to the knowledge of the plaintiff, and if a suit is filed beyond the limitation perio....
The main legal point established in the judgment is the importance of considering documents filed along with the plaint for deciding the application under Order 7 Rule 11 CPC. The judgment emphasized....
A suit for declaration of title and recovery of possession is maintainable in a civil court, even if the property in question is alleged to be an endowment property.
The trial court must evaluate plaints for clear causes of action, dismissing those that are vexatious and lack legal foundation.
The demolition of protected structures without due process (notice) is illegal and entitles the occupier to reconstruct the premises at their own cost, maintaining the obligations under prior agreeme....
A plaint should not be rejected unless it manifestly discloses no cause of action or is vexatious; here, the court found it did disclose a cause of action based on registered title.
A plaint must be deemed to disclose a cause of action if the statements therein, taken as true, allow for a claim to proceed, regardless of subsequent merits, as defined under CPC.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.