SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2024 Supreme(Sikk) 35

THE HIGH COURT OF SIKKIM: GANGTOK
BISWANATH SOMADDER, CJ., BHASKAR RAJ PRADHAN, J.
Karma Tshering Bhutia, S/o Shri Tempo Rapgay Bhutia – Appellant
Versus
State of Sikkim, Through the Chief Secretary, Government of Sikkim and Ors. – Respondents
W.A. No. 07 of 2023
Decided On : 08-10-2024 

Advocates Appeared:
For the Appellant :Mr. Yash Raj Singh Deora, Advocate and Mr. Girmey Bhutia, Advocate.
For the Respondents:Mr. Zangpo Sherpa, Additional Advocate General with Mr. Sujan Sunwar, Assistant Government Advocate, Ms. Pubalee Bujarbaruah, Senior Advocate with Mr. Ganesh Man Chettri and Mr. Benhail Alfieri Wanswett, Advocates.

Compensation in land acquisition must adhere to statutory requirements, including formal awards under section 11 of the Land Acquisition Act, or provisions of the updated Act of 2013 apply.

Headnote:(A) Land Acquisition Act, 1894 - Sections 4, 6, 9, 11, 17(3A), 24; Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 - The court found the learned Single Judge erred in holding the statement of compensation dated 31.05.2013 as an award without considering the relevant provisions, thereby necessitating review. (Paras 2, 12, 26)

(B) Acquisition of land under urgency provisions - The proper application of the urgency clause requires compliance with statutory obligations including notice and the tendering of compensation. The absence of a formal award under section 11 does not negate the need for adherence to procedural provisions in land acquisition. (Paras 23, 24)

Facts of the case:
The appellant sought release of compensation for land acquired under the Land Acquisition Act of 1894, which involved the computation of compensation under challenging procedural circumstances due to the state’s actions in acquiring the land.

Findings of Court:
The Court highlighted that the statement of compensation dated 31.05.2013 was not an award as per the statutory requirements, and directed the state to proceed under section 24 of the Act of 2013 for determining compensation.

Issues: Whether the statement of compensation computed dated 31.05.2013 constitutes an award under the Act of 1894; whether procedural requirements of land acquisition were adequately met.

Ratio Decidendi: The court concluded that the absence of a formal award under section 11 of the Act of 1894 indicates that all provisions of the Act of 2013, relating to compensation, must be applied in the absence of compliance with procedural requirements.

Result: The impugned judgment was set aside, granting relief to the appellant.

Table of Content
1. compensation claims and proceedings (Para 1 , 3 , 4 , 5 , 6 , 8)
2. misinterpretation of compensation as an award (Para 2 , 13 , 19)
3. procedure for land acquisition under act of 1894 (Para 9 , 10 , 11 , 12 , 14)
4. legal requirements for awards under sections 11 and 17 (Para 15 , 16 , 17 , 18)
5. supreme court interpretation on compensation and awards (Para 20 , 24 , 25 , 26)
6. final decision to allow writ petition no. 32 of 2018 (Para 27)

JUDGMENT :

Bhaskar Raj Pradhan, J.

The impugned judgment passed by the learned Single Judge dated 10.07.2023, disposing two connected writ petitions, was primarily on the opinion that the statement of compensation computed on 31.05.2013 was not an award and the State respondents had failed to explain the law under which compensation was computed and prepared.

2. The impugned judgment holding that the statement of compensation computed on 31.05.2013 was in fact the award, is based on the premise that there was no provision in the LAND ACQUISITION ACT , 1894 (for short, Act of 1894) under which such statements of compensation which had all the trappings of an award could be computed. This was incorrect. The relevant provision was not examined as it was not placed by the parties. We are, therefore, constrained to interfere with the impugned judgment for reasons stated below.

3. Writ Petition (C) no. 32 of 2018 preferred by Karma Tshering Bhutia (the appellant herein) was dismissed and Writ Petition (C) 43 of 2022 preferred by College of Agriculture Engineering and Post Harvest Technology (for short, CAEPHT) (the respondent no.4 herein), was allowed.

4. The appellant had prayed for release of compensation amount as per the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (for short, Act of 2013); payment of interest at 10% per annum on balance compensation amount unpaid until final payment; and for rehabilitation and resettlement of the appellant and his family members who were displaced.

5. CAEPHT in their writ petition had prayed for quashing of memo no. 1748/LR & DMD/GOS/ACQ/317- 318 dated 12.08.2017; memo no.1748/LR & DMD/ACQ/GOS/418 dated 20.09.2017; and memo no. 1748/LR & DMD/2018/681 dated “Nil” 2018. These memos were issued by the respondent no.3 forwarding rectified details of compensation to CAEPHT.

6. Both the writ petitions arose from an acquisition proceeding under the Act of 1894.

7. Heard the learned counsel for the appellant, the learned senior counsel for the CAEPHT and the learned Additional Advocate General for the State respondents.

8. The admitted facts reflect:

DateEvents

22.08.2008

29.11.2008

10.06.2009

CAEPHT requested the State for additional land in Ranipool.
12.09.2012 CAEPHT sought administrative clarification regarding purchase of land and the correct procedure to be followed for purchase of land from willing local persons.
05.09.2012 Karma Tshering Bhutia offered his land for sale to CAEPHT.
18.05.2013Preliminary notification under Section 4 was issued notifying the land of Karma Tshering Bhutia being needed for public purpose invoking urgency clause under Section 17 of the Act of 1894.
31.05.2013Statement of compensation for land and other standing properties as assessed by respondent no.2 was forwarded to the respondent no.4 requesting for release of 80% advance payment for making payment to land owners.
03.08.2013The declaration under Section 6 of the Act of 1894 was published.
01.11.2013The respondent no.3 conveyed to respondent no.2 the government’s approval under Section 7 of the Act of 1894 for the construction of the Central Agricultural University by respondent no.4 requesting respondent no.2 to proceed as per Act of 1894.
25.11.2013Public notice under Section 9 of the Act of 1894 published calling upon interested persons to appear personally or by agent before the respondent no.2 on or before 12.12.2013 and state in writing the nature of their respective interest in the land and the amount in particular

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top