Important Points
Subject
Employment Law - Contractual Employment
Act Referred
SOCIETIES REGISTRATION ACT : .
Headnote
Abolishment - Employment Contract - Societies Registration Act - Rajendra v. State of Rajasthan and others. AIR 1999 SC 923, N. C. Singh v. Union of India, AIR 1980 SC 1255, K. Rajendran v. State of Tamil Nadu, AIR 1982 SC 1107, Mathuresh chand v. U. P. Public Service Tribunal. 1999 (81) FLR 322 - The court held that the decision to abolish the post was based on administrative and financial grounds, and the Court cannot interfere with such matters. The financial crisis in the country was considered, and the Court recommended the petitioner's parent department to re-employ the petitioner considering the abolishment of his post in the Centre.
Fact of the Case:
The petitioner was appointed as Deputy Director (Public Relations) in the North Central Zone Cultural Centre, Allahabad, and his post was later abolished. The petitioner alleged that he was assured of absorption in the Centre, but the Centre decided to abolish his post due to administrative and financial reasons.
Finding of the Court:
The Court found that the decision to abolish the post was based on administrative and financial grounds, and the Court cannot interfere with such matters. The Court recommended the petitioner's parent department to re-employ the petitioner considering the abolishment of his post in the Centre.
Issues: The issues revolved around the alleged assurance of absorption in the Centre, the decision to abolish the petitioner's post, and the legality of the contractual appointment.
Ratio Decidendi: The Court held that the decision to abolish the post was based on administrative and financial grounds, and the Court cannot interfere with such matters. The financial crisis in the country was considered, and the Court recommended the petitioner's parent department to re-employ the petitioner considering the abolishment of his post in the Centre.
Final Decision: The writ petition was dismissed, and the Court recommended the petitioner's parent department to re-employ the petitioner considering the abolishment of his post in the Centre.
A.KUMAR, Prabodh Gaur, S.P.SINGH, Tauja Somvanshi, TEJ PRAKASH, U.N.Sharma, VINEET SARAN
( 1 ) THIS writ petition has been filed against the impugned orders dated 13. 1. 1998 Annexures-25 and 26 to the petition. By the order dated 13. 1. 1998 Annexure-25 to the petition the post of deputy Director (Public Relations) in the North Central Zone Cultural Centre, Allahabad was abolished. By the second order of the same date (Annexure-26 to the petition) the petitioner was given contractual appointment for two years from 1. 12. 1993 terminable at any point of time without any prior notice. It was also provided therein that on the expiry of the contract period, it will be in the sole discretion of the Executive Board of the North Central Zone Cultural Centre, allahabad, to determine whether the contract should be renewed or not.
( 2 ) HEARD learned counsel for the parties.
( 3 ) THE North Central Zone Cultural Centre. Allahabad (hereinafter referred to as the Centre)was set up with a view to promote and preserve the cultural heritable of India. It is registered as a society under the Societies Registration Act. Its governing body consists of several persons mentioned fn paragraph 2 of the pelition. The finance of the centre is provided by the Central government and participating State Government. The Director is an I. A. S. Officer.
( 4 ) IT is alleged that the petitioner was a confirmed/regular employee working as Administrative officer in the U. P. Panchayat Raj Vitta Evam Vikas Nigam Ltd. (hereinafter referred to as the nigam) a Government of U. P. undertaking and he was sent on deputation by the Nigam to the centre. True copy of the letter appointing him on deputation is Annexure-2 to the writ petition. The petitioner took charge on 2. 12. 1991 vide Anncxure-3. It is alleged in paragraph 17 of the writ petition that while working In the Centre the petitioner retained his lien in the Nigam. In paragraph 18 it is alleged that the petitioner was appointed as Deputy Director (Public Relations)by the order dated 19. 1,1993 In the Centre vide Annexure-4. He was given pay scale of Rs. 3,000-4,500. It is alleged in paragraph 21 that on the assurance given by the respondent No. 1 that he would be absorbed in the Centre he resigned from the Nigam. True copy of the petitioners application dated 13. 7. 1993 is Annexure-5 to the petition. True copy of the resignation letter is Annexure-6 to the writ petition. The resignation was accepted by the Nigam w. e. f. 1. 12. 1993 vide Annexure-8. In paragraph 28 it is alleged that the Executive Board of the centre by the resolution dated 4. 3. 1994 resolved that the post of Deputy Director (Public relations and Publications) be re-designated as Deputy Director [public Relations) and the petitioner be appointed on the pay scale of Rs. 3,000-4,500 for three years from 1. 12. 1992. It was resolved by the Executive Board that the petitioner be treated as an officer on contract employment. By the order dated 3. 6. 1996 the petitioner was allowed to continue to work in continuation of his previous service till such time as the next meeting of the Executive board/governing Body. The petitioner made a representation for absorption. True copy of the representation dated 24. 1. 1997 is Annexure-10 to the petition. By the order dated 26. 4. 1997 vide annexure-11 to the petition the petitioners contractual appointment was extended till 30. 4. 1997. It was mentioned therein that if the petitioner failed to extend his contract tilt 30. 4. 1997 the letter dated 24. 1. 1997 will be considered as notice of termination of employment as per contract. The petitioner submitted a representation on 29. 4. 1997 against this order vide Annexure-12. In reply the office memo dated 3. 5. 1997 was sent to him vide Annexure-13. The petitioner signed the contract referred to in the office memo as stated in paragraph 50 of the writ petition. He then moved an application dated 10. 10. 1997 for reconsidering the decision vide Annexure-14. In paragraph 54 of the petition it is alleged that the petitioner was n