SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2008 Supreme(All) 1522

[2008(6) ADJ 660 (DB)]
ALLAHABAD HIGH COURT
BEFORE : ANJANI KUMAR AND SUDHIR AGARWAL, JJ.
ASHOK KUMAR AND OTHERS .......Petitioners
Versus
STATE OF U.P. AND OTHERS ........Respondents
(Writ Petition Nos. 21073, 22678, 22674, 22373, 22371, 22370, 22369, 22368, 22367, 22365, 22263, 22262, 22260, 21989, 21988, 21987, 21986, 21985, 21984, 18542 of 2008, decided on 18th July, 2008)

Headnote:Electricity Act, 2003—Sections 126, 127, 131(4), 14, 2(39), 2(31) and 135—U.P. Government Electrical Undertakings (Dues Recovery) Act, 1958—Sections 3, 2(c) and 2(b)—U.P. Electricity Reforms Act, 1999—Sections 23(1) and (2)—U.P. Electricity Supply Code, 2005—Clause 6.8—Electricity (Supply) Act, 1948—Section 5—Unauthorised use of electricity—Assessment—Issue of provisional/final assessment notices under Section 126 of Act of 2003 and demand notice under Section 3 of Act of 1958—Validity of—Petitioner, an oil Expeller obtained electric connection with contracted load of 21 Horse Power at his premises—Procedure prescribed in Para 6.8 of Code of 2005, while issuing provisional assessment notice, has not been followed at all—Before issuing a demand notice under Section 3 of 1958 Act, no final order of assessment, as contemplated under Para 6.8(c)(i) and (ii) of Code of 2005 has passed by assessing officer—There was no averments in affidavit the M.R.I. report and its findings were made available to consumers at the time of Inspection, or alongwith provisional assessment notice after discussing and substantiating alleged irregularity, as required in Para 6.8(a)(iv) and (v) of Code of 2005—Therefore, it cannot be said that a valid and proper assessment notice was issued to petitioners—Which could have been replied by them effectively—Hence, non-compliance of Para 6.8 of Code of 2005—Held, impugned provisional/final assessment notices, issued under Section 126 of Act of 2003, as well as demand notice issued under Section 3 of Act of 1958 quashed and set aside—However, respondents at liberty to take appropriate steps and to pass a fresh order. [Paras 12, 42, 45, 49, 77, 78 and 79]

       

JUDGMENT

Hon’ble Sudhir Agarwal, J.—Pleadings are complete. As requested and agreed by learned Counsel for the parties, the matter has been heard finally at the admission stage under the Rules of the Court. Further, in all these petitions, common questions of law and facts are involved, therefore, they have been heard together and are being decided by this common judgment. Besides oral submissions, the parties have also filed written arguments.

2. Aggrieved by the assessment orders under Section 126 of the Electricity Act, 2003 (hereinafter referred to as the “Act, 2003”) and demand notices under Section 3 of the U.P. Government Electrical Undertaking (Dues Recovery) Act, 1958 (hereinafter referred to as the “1958 Act”), these petitions (except Writ Petition Nos. 22263 of 2008, 22365 of 2008, 22678 of 2008, 21986 of 2008, 22367 of 2008 and 18542 of 2008) have been filed seeking a writ of certiorari quashing the aforesaid orders/notices. A writ of mandamus has also been sought commanding respondents not to realise any amount pursuant to the impugned orders. Further notification dated 27.6.2006 issued by the State Government notifying ‘assessing officer’ under Section 126 of the Act, 2003 has also been challenged on the ground that it is ultra vires and illegal. In Writ Petition Nos. 22263 of 2008, 22365 of 2008 and 22678 of 2008, only provisional assessment notice issued by the Executive Engineer concerned as well as the Government notification dated 27.6.2006 have been challenged. In Writ Petition Nos. 21986 of 2008 and 22367 of 2008, the demand notice dated 29.3.2008 under Section 3 of 1958 Act as well as the notification dated 27.6.2006 are under challenge.

3. For the purpose of brevity the facts have been taken from the leading Writ Petition No. 21073 of 2008 (Ashok Kumar and others v. State of U.P. and others).

4. The petitioner is running an Oil Expeller at his premises situated at Kheragarh, District Agra for which he obtained an electric connection with the contracted load of 21 Horse Power. The electricity is being distributed in District Agra by respondent No. 2 namely, Dakshinanchal Vidyut Vitran Nigam Limited (hereinafter referred to as the “DVVNL”). It is said that on 22.9.2007 a new meter was installed at the petitioner’s premises. While taking away old meter, it was mentioned in the meter sealing certificate dated 22.9.2007 (Annexure-1 to the writ petition) that the old meter shall be tested in the laboratory of respondent No. 2 on 4.10.2007 in the presence of the consumer or his representative. The petitioner submits that on 4.10.2007, in the test laboratory, old meter was checked and nothing wrong was found therein for the purpose of revenue assessment as is evident from page 52 of the paper book which is a test report duly signed by the Assistant Engineer (Meters), Electricity Test Laboratory, Electricity Test Division, Agra. However, on 18.3.2008 the respondent No. 3, i.e., Executive Engineer, Electricity Distribution Division-I, DVVNL, Agra issued a provisional assessment notice stating that on 15.1.2008 during an inspection the petitioner was found committing certain irregularities/theft of energy on account whereof an assessment of Rs. 3,83,622/- was imposed. The petitioner was given seven days time to submit his objection. Copy of the said notice dated 18.3.2008 is on record as Annexure-1-A to the writ petition. Thereafter on 29.3.2008 a demand notice under Section 3 of 1958 Act was issued for recovering Rs. 3,83,644/- which included the amount of provisional assessment as mentioned in the notice dated 18.3.2008 as well as the process fee of Rs. 22/- being cost of notice under Section 3 of 1958 Act. It is this act of the respondents which has compelled the petitioner to approach this Court under Section 226 of the Constitution of India.

5. In all other matters the assessment orders and demand notices are similar except of amount and in some cases date of inspection is different which is given in the form o























































































































































































































Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
Judicial Analysis

SupremeToday

SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top