SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2022 Supreme(All) 1183

IN THE HIGH COURT OF ALLAHABAD
ATTAU RAHMAN MASOODI, OM PRAKASH SHUKLA, JJ.
U.P. Expressways Industrial Development Authority Thru Chief Executive Officer – Appellant
Versus
M/s Sahakar Global Ltd. Thru Thru Authorized Signatory Stephen Lobo – Respondent
Appeal Under Section 37 Of Arbitration And Conciliation Act 1996 No. - 16 of 2022
Decided on : 02-12-2022

Advocates:
Advocate Appeared:
For the Appellant : Brijesh Kumar, Amal Rastogi, Utkarsh Srivastava
For the Respondent: Pritish Kumar

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 37 and Section 9 - Appeal against interim relief - Appellant contends that the status quo order effectively amounts to a final adjudication of the Section 9 petition; thus, the court was called to set aside the order - Bank guarantees must be honored as per their terms unless there is egregious fraud or irretrievable injustice - The court noted that the guarantees are unconditional, and the existence of disputes between the parties does not prevent invocation. (Paras 2, 4, 24, 38)

(B) Legal Principles - The invocation of unconditional bank guarantees is a matter of strict adherence to the terms without consideration of underlying disputes; only exceptionally can injunctions against such invocation be granted on grounds of egregious fraud, irretrievable injury, or special equities. (Paras 19, 27, 49)

Facts of the case:
The matter arises from a contract between the parties involving bank guarantees for performance security. The Respondent sought interim relief under Section 9 regarding the performance bank guarantees as disputes over stamp duty and force majeure reliefs emerged. (Paras 2-4)

Findings of Court:
The court found no ground supporting an injunction against invoking the performance bank guarantees and ruled that the status quo order was improperly granted. The unconditional nature of the bank guarantees demanded enforcement. (Paras 44, 50)

Issues: Whether the status quo order is tantamount to a final decision on the pending Section 9 petition and whether the court should intervene in enforcing unconditional bank guarantees despite ongoing disputes. (Paras 3, 5)

Ratio Decidendi: The court reiterated that invocations of unconditional bank guarantees should proceed in harmony with their express terms; only blatant fraud or proven irretrievable harm can warrant judicial restraint on such enforceability. (Paras 19, 32, 41)

Result: The appeal is allowed, and the impugned order is set aside.

Table of Content
1. overview of the contract between upeida and sahakar global ltd. (Para 2 , 4)
2. arguments regarding the implications of the status quo order. (Para 3 , 8)
3. discussion on the nature and invocability of bank guarantees. (Para 10 , 12)
4. court's legal scrutiny of claims made by both parties. (Para 11 , 13 , 14 , 15)
5. precedents regarding bank guarantees and conditions for injunctive relief. (Para 21 , 22 , 24)
6. clarification of fraud and its threshold in bank guarantee cases. (Para 31 , 32)
7. assessment of irretrievable injustice as a factor in bank guarantee invocation. (Para 40 , 41)
8. final decision on the appeal and the implications of an unconditional bank guarantee. (Para 49 , 50)

JUDGMENT :

Om Prakash Shukla, J.

1. Heard Mr Brijesh Kumar Saxena Learned Advocate appearing for UPEIDA and Mr. Jaideep Narain Mathur, Learned Senior Advocate along with Mr. Pritish Kumar representing M/s Sahakar Global Ltd.

2. A short but seminal question arises in the present Appeal filed under section 37 of the Arbitration & Conciliation Act, 1996 (as amended) by the Uttar Pradesh Expressways industrial Development Authority (for short UPEIDA) against an ad-interim Injunction order dated 12.09.2022 (Impugned Order) passed by the Learned Commercial Court, Lucknow under section 9 of the Arbitration & Conciliation Act, 1996 (as amended). Apparently, in the said impugned order the Learned Commercial Court has directed the parties to maintain ‘status quo” with respect to the performance Bank Guarantee, furnished by the Respondent Contractor – M/s Sahakar Global Ltd.

3. The Appellants have submitted that the said “Status Quo” order passed by the Learned Commercial Court, Lucknow as per the impugned order, not only amounts to restraining the invocation and/or encashment of Performance Bank Guarantee by them but also amounts to final adjudication of the pending section 9 petition itself as the nature of relief, which can be obtained/granted under a proceeding under section 9 of the Arbitration & Conciliation Act, 1996 can be only interim in nature as any dispute can be finally decided in an arbitration proceedings before the Learned Arbitral Tribunal. Thus, it has been urged by the appellant that since a status quo order has been passed nothing remains in the pending section 9 petition to be decided and as such this court has been called upon to set aside the impugned order as well as dismiss the pending section 9 petition.

4. The genesis of dispute in the present case can be capitulated in the following manner:

(i) UPEIDA and M/s Sahakar Global Ltd. entered into a Contract Agreement dated 13.10.2020, which provided collection of user fee at such rates from the vehicles in terms of the U.P. Toll Rules, 2020 at the 17 designated Toll Plazas, located on the Agra-Lucknow Express way.

(ii) M/s Sahakar Global Ltd. was required to pay one year contract amount of Rs.402,39,00000/- (Rupees Four Hundred Two Crores and Thirty Lakhs only) divided by number of days in a year (365 or 366 as the case may be) and multiplied by seven on weekly basis every Thursday to UPEIDA. For the subsequent second year of contract, the payable amount was to be escalated by 10% till end of the contract tenure.

(iii) The period of contract commenced on 15.10.2020 (00:00 hours) until 14.10.2022 (23:59:59 hours).

(iv) In terms of the contract, M/s Sahakar Global Ltd furnished five Bank Guarantees all valid and subsisting upto January 31, 2023 for a total sum of Rs.33,53,25,000/- (Rupees Thirty Three Crore Fifty Three lakhs and Twenty Five Thousand only) in favour of the present Appellant as performance security.

(v) As per M/s Sahakar global Ltd. a serious dispute arose between the parties in connection with the contract Agreement with regard to (a) Stamp Duty and (b) Force Majeure reliefs, which required to be adjudicated by a duly constituted Arbitral Tribunal.

(vi) As far as

          Click Here to Read the rest of this document
          1
          2
          3
          4
          5
          6
          7
          8
          9
          10
          11
          SupremeToday Portrait Ad
          supreme today icon
          logo-black

          An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

          Please visit our Training & Support
          Center or Contact Us for assistance

          qr

          Scan Me!

          India’s Legal research and Law Firm App, Download now!

          For Daily Legal Updates, Join us on :

          whatsapp-icon Back to top