IN THE HIGH COURT OF DELHI AT NEW DELHI
Jyoti Singh, J.
Central Electronics Limited – Appellant
Versus
Energy Efficiency Services Limited & Anr. – Respondents
O.M.P.(I) (COMM.) 44 of 2023
Decided On : 06-07-2023
Invocation/encashment of unconditional Bank Guarantees (BGs) cannot be restrained by the Court unless there is egregious fraud or irretrievable harm or injustice to one party. Financial status of a party to the contract cannot be taken as a defence against encashment of an unconditional BG.
Fact of the Case:
Petitioner was awarded a work contract by Respondent No. 1 for designing, engineering, supplying, constructing, erecting, testing, commissioning and Operation and Maintenance (O&M) of 120 MW Solar Power Generating Systems (SPGS) at various sub-stations in Maharashtra under the Mukhyamantri Saur Krishi Vahini Yojana (MSKVY) or Chief Minister's Agriculture Feeder Scheme of Government of Maharashtra. Disputes arose between the parties and Petitioner claimed that it has installed and commissioned Solar Power Plants at designated sites successfully during the period September, 2018 till February, 2022 and yet against the total value of bills raised being Rs.221.29 Crores, it has received Rs.86.18 Crores and thus an amount of Rs.24.43 Crores is outstanding, while Respondent No. 1 adopted a position that Petitioner installed and commissioned a total of 57 sites with 59.80 MWp capacities and out of the 57 sites, 23 were under complete shutdown when the Default Notice cum Termination Letter dated 27.06.2022 was issued to the Petitioner. Petitioner was also not performing the O&M work at most of the sites resulting in degradation of system efficiency and consequent revenue loss of approximately Rs.1.67 Crore as on 08.06.2022 for shut down sites besides other defaults and lapses. When situation did not improve, Respondent No. 1 sent a final Default Notice dated 31.01.2023 to the Petitioner under Clause 42.2 of GCC for rectifying the breaches within 14 days, failing which contract shall be deemed to be terminated under Clause 22 with necessary consequences under the provisions of contract and in law. This Default Notice triggered the filing of the present petition and vide order dated 14.02.2023, this Court directed the parties to maintain status quo till the next date of hearing. Thereafter, Respondent No. 1 filed an application being I.A. 5355/2023 dated 13.03.2023 seeking modification of the interim order to the extent that the status quo order shall not come in the way of termination of the contract, as according to the final Default Notice, Respondent No. 1 was at liberty to terminate the contract at the end of 14 days, if the Petitioner failed to rectify the alleged breaches.
Finding of the Court:
The Court held that the invocation/encashment of unconditional BGs cannot be restrained by the Court unless there is egregious fraud or irretrievable harm or injustice to one party. The Court also held that the financial status of a party to the contract cannot be taken as a defence against encashment of an unconditional BG.
Issues: Whether invocation/encashment of unconditional Bank Guarantees (BGs) can be restrained by the Court.
Ratio Decidendi: The Court held that the invocation/encashment of unconditional BGs cannot be restrained by the Court unless there is egregious fraud or irretrievable harm or injustice to one party. The Court also held that the financial status of a party to the contract cannot be taken as a defence against encashment of an unconditional BG. The Court relied on the following judgments of the Supreme Court: Dwarikesh Sugar Industries Ltd. v. Prem Heavy Engineering Works (P.) Ltd. and Another, (1997)6 SCC 450, Gujarat Maritime Board v. Larsen and Toubro Infrastructure Development Projects Limited and Another, (2016)10 SCC 46 and Himadri Chemicals Industries Ltd. v. Coal Tar Refining Co., (2007)8 SCC 110.
Final Decision: The Court dismissed the petition and vacated the ad-interim order passed by the Court on 14.02.2023.
JUDGMENT
Jyoti Singh, J.
I.A. 5356/2023 (Exemption)
Allowed, subject to all just exceptions.
Application stands disposed of.
O.M.P.(I) (COMM.) 44/2023 & I.A. 5355/2023 (for modification)
1. This is a petition under Section 9 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as the `1996 Act') seeking interim injunction restraining Respondent No. 1 from invoking/encashing Bank Guarantee (`BG') No. U7AGPGE211810041 dated 30.06.2021 for a sum of Rs.1,97,40,000/-, BG No. 161BGPR191330002 dated 08.05.2019 for a sum of Rs.1,97,40,000/-, BG No. 161BG032020 dated 11.02.2020 for a sum of Rs 1,97,40,000/- and BG No. VP9GPGE213220093 dated 18.11.2021 amounting to Rs.5,79,344/-, pursuant to a final Default Notice dated 31.01.2023 and/or in any manner whatsoever adopting coercive measures for recovery of any sum, pursuant to the said notice.
2. Brief facts that need to be captured for deciding the present petition are that Petitioner is a Government of India enterprise under the Department of Scientific and Industrial Research (`DSIR'), Ministry of Science and Technology and was established in 1974 with an objective to commercially exploit indigenous technologies developed by National Laboratories and R&D institutions in the country. Petitioner also undertakes various projects for other Government enterprises in the field of solar power generation, security and surveillance, railway signalling etc.
3. Respondent No. 1 is promoted by Ministry of Power, Government of India as a Joint Venture of four Public Sector Undertakings i.e. NTPC Limited, Power Finance Corporation Limited, REC Limited and Powergrid Corporation of India Limited.
4. Petitioner was awarded a work contract by Respondent No. 1 vide Letter of Award (`LoA') dated 11.01.2018 for designing, engineering, supplying, constructing, erecting, testing, commissioning and Operation and Maintenance (O&M) of 120 MW Solar Power Generating Systems (`SPGS') at various sub-stations in Maharashtra under the Mukhyamantri Saur Krishi Vahini Yojana (`MSKVY') or Chief Minister's Agriculture Feeder Scheme of Government of Maharashtra.
5. Under Clause 9 of the LoA, Contract Performance Guarantee (`CPG') was to be submitted by the Petitioner for successful execution of the work under the LoA, Special Conditions of Contract (`SCC') and General Conditions of Contract (`GCC'), at the rate of 10% of the contract value. CPG was to remain valid to cover the Delivery Period plus Warranty Period and three months Claim Period and was required to be furnished in the form of Demand Draft/Pay Order or BG for 10% of the contract value within 30 days of receipt of notification of award of the contract from Respondent No. 1. Details of CPGs furnished by the Petitioner for a total sum of Rs.597,99,344/- are as follows:
| Sl. | PBG No. | Amount of PBG (Rs.) | Bank Name | Date of Issue | Expiry date |
| 1 | 161BGPR191330002 | 1,97,40,000 | Syndicate/Canara Bank, SBB | 08-05-19 | 07-04-26 |
| 2 | 161BG032020 | 1,97,40,000 | Syndicate/Canara Bank, SBB | 11-02-20 | 29-07-23 |
| 3 | U7AGPGE211810041 | 1,97,40,000 | Canara Bank, SBB | 30-06-21 | 21-02-26 |
| 4 | VP9GPGE213220093 | 5,79,344 | Canara Bank, NV | 18-11-21 | 05-06-24 |
| Total | 597,99,344/- | , |
6. Subsequently, disputes arose between the parties and Petitioner claims that it has installed and commissioned Solar Power Plants at designated sites successfully during the period September, 2018 till February, 2022 and yet against the total value of bills raised being Rs.221.29 Crores, it has received Rs.86.18 Crores and thus an amount of Rs.24.43 Crores is outstanding, while Respondent No. 1 adopts a position that Petitioner installed and commissioned a total of 57 sites with 59.80 MWp capacities and out of the 57 sites, 23 were under complete shutdown when the Default Notice cum Termination Letter dated 27.06.2022 was issued to the Petitioner. Petitioner was also not performing the O&M work at most of the sites resulting in degradation of system efficiency and consequent revenue loss of approximately Rs.1.67 Crore as on 08.06.2022 for shut down sit
Development Projects Limited and Another
Dwarikesh Sugar Industries Ltd. v. Prem Heavy Engineering Works (P.) Ltd. and Another
The court clarified that injunction against unconditional bank guarantees requires proof of egregious fraud, irretrievable injustice, or special equities, none of which were sufficiently substantiate....
Unconditional bank guarantees may only be reviewed for egregious fraud or irretrievable injustice; disputes over contract performance must be resolved through arbitration.
The court emphasized the independence and unconditional nature of bank guarantees, while recognizing exceptions such as fraud, irretrievable injustice, or special equities.
Bank guarantees are independent contracts and can only be restrained in exceptional cases of fraud or irretrievable injustice.
A confirmed Bank Guarantee/irrevocable Letter of Credit cannot be interfered with unless there is established fraud or irretrievable injustice involved in case.
Bank guarantees can be invoked regardless of disputes, unless fraud or irretrievable harm is clearly established.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.