IN THE HIGH COURT OF JUDICATURE AT ALLAHABAD
Rajesh Bindal, CJ.
M/s R.B.T. Industries Ltd. and another - Applicants
Versus
Jaswant Rai and others - Respondents
Arbitration & Conciliation App. U/s 11(4) No. 1 of 2020
Decided On : 25-01-2023
Arbitration and Conciliation Act, 1996 – Section 11 – Seeking appointment – Claiming damages – Whether claim is a dead (long-barred) claim or a live claim – Held, Once claim is found to be ex facie time barred, in my considered opinion, appointment of Arbitrator for resolution of dispute would be a futile exercise and, therefore, no arbitrator need be appointed in case in hand – Accordingly dismissed.
ORDER :
1. This is an application filed under Section 11 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as “the Act”) praying for appointment of an Arbitrator for resolution of dispute between the parties.
2. The fact, in brief, are that a tender was invited for the work-supplying, fabrication, erection and fixing of 3000 nos. steel channel sleepers on bridge no. 11 on MGS-BSB Section under DRM Northern Railway, Lucknow, wherein applicants also participated. The rates of the applicants were found lowest as a result whereof the work was awarded to the applicants vide letter of acceptance dated January 15, 2008.
3. Learned counsel for the applicant submitted that the original work allotted to the applicants was completed within time. However, certain additional work was assigned. In execution thereof, there was delay for the reason that required drawing was not handed-over by the respondents, despite repeated request made by the applicants.
4. He further submitted that there is an arbitration clause in the General Conditions of contract for Railways. The applicant had issued notice on August 10, 2018 seeking appointment of an arbitrator. However, arbitrator was not appointed.
5. On the other hand, learned counsel for the respondents, submitted that the applicants had only executed about 88 per cent of the work. There was no fault on the part of the respondents; the delay was at the end of the applicants. Number of extensions were granted to the applicants to complete the project. Last extension was granted on November 20, 2010 but the project was not completed. Ultimately, vide communication dated August, 19, 2013 the contract was terminated. It was specifically mentioned in the letter that on account of non fulfillment of contract, the Railways reserve the right to claim damages under clause 62 of the General Conditions of Contract. He further submitted that the contract having been terminated on August 19, 2013, any notice seeking appointment of arbitrator with reference to the work, which was awarded to the applicants vide letter dated January 15, 2008 and was to be completed within the extended period, is highly belated and the claim is time barred. Even after issuance of notice dated August 10, 2018 seeking appointment of an arbitrator, the present applicant was filed more than one year later in this Court. The claim of the applicant being time barred, the appointment of Arbitrator is to be an exercise in futility. It was further submitted that this aspect can be gone into by this Court even at the stage of the appointment of Arbitrator as held by Hon’ble Supreme Court in Insurance Company Ltd. Vs. Boghara Polyfab Pvt. Ltd., (2009) 1 SCC 267, wherein referring to the earlier authority on the issue in SBP and Company Vs. Patel Engineering Limited and another (2005) 8 SCC 618, the Court identified and segregated the issues that may be raised in an application under Section 11 of the Act into three categories, second category whereof includes the aspect, “whether the claim is a dead (long-barred) claim or a live claim?”
6. Heard learned counsel for parties and perused the paper book.
7. In the case in hand, the contract was awarded to the applicants vide letter dated January 15, 2008 which was to be completed within a period of six months. The stand taken by the applicants is that certain additional work was assigned to be executed, which was delayed as the applicants were not furnished the drawings thereof. It is not in dispute that extensions were also granted to the applicant which last expired on November 20, 2010.
8. The stand of the respondents is that any delay in completion of project is not attributable to the respondents. It was only on the part of the applicants. Waiting for quite some time, when despite reminders dated October 26, 2012, August 12, 2013 and August 19, 2013 the applicants failed to complete the project, the contract itself was terminated vide letter dated August, 19, 2013, reserving t
Insurance Company Ltd. Vs. Boghara Polyfab Pvt. Ltd.
SBP and Company Vs. Patel Engineering Limited and another (2005) 8 SCC 618
Bharat Sanchar Nigam Limited and others Vs. Nortel Networks India Pvt. Ltd. (2021) 5 SCC 738
The Court emphasized the importance of timely claims and the need to satisfactorily explain any delay, highlighting the application of Article 137 of the Limitation Act, 1963 in determining the perio....
Claims for arbitration must be raised promptly upon accrual of rights; failure to do so results in dismissal due to limitation.
The court clarified that a previous dismissal of an application for appointment of an Arbitrator does not preclude the applicant from seeking appointment through the correct authority, and hypertechn....
The limitation period for seeking the appointment of an arbitrator begins only after a valid notice invoking arbitration is issued, and failure to appoint forfeits the right to do so.
Failure to appoint an arbitrator within the stipulated time results in the loss of the right to make the appointment. Appointment of an arbitrator by an ineligible person is void ab initio.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.