SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2022 Supreme(Cal) 1134

IN THE HIGH COURT OF CALCUTTA
Prakash Shrivastava, J.
Shree Laxmi Iron And Steel Works Private Limited - Appellant
Versus
Eastern Railway And Others - Respondent
A.P. No. 316 of 2020
Decided On : 18-01-2022

Advocates appeared:
Debnath Ghosh, Advocate, Avijit Dey, Advocate, Shankar Ranjan Sen, Advocate

Failure to appoint an arbitrator within the stipulated time results in the loss of the right to make the appointment. Appointment of an arbitrator by an ineligible person is void ab initio.

Headnote:

Arbitration - Appointment of Arbitrator - Arbitration and Conciliation Act, 1996 - Section 11 - 2903, 2904, 2905(b)

Fact of the Case:

The applicant submitted an offer in response to a tender and was issued a purchase order for supply of joggled fishplates. Dispute arose when the respondents refused to accept the materials, leading to a claim of damages. The applicant invoked the arbitration clause and sought appointment of an arbitrator, as the respondents failed to appoint one within 30 days.

Finding of the Court:

The court found that the respondents lost their right to appoint an arbitrator as they failed to do so within the stipulated time. The arbitration clause was undisputed, and a case was made to appoint an arbitrator to resolve the dispute.

Issues: Dispute over appointment of arbitrator, invocation of arbitration clause, failure of respondents to appoint arbitrator within 30 days.

Ratio Decidendi: The court held that the respondents lost their right to appoint an arbitrator by failing to do so within 30 days of demand. It was also established that the appointment of an arbitrator by a person who is de jure ineligible is void ab initio.

Final Decision: The court allowed the application and proposed the name of a retired Judge for appointment as arbitrator to resolve the dispute.

JUDGMENT

Prakash Shrivastava, CJ. - This application under Section 11 of the arbitration and Conciliation act, 1996 has been filed for appointment of arbitrator to resolve the dispute between the parties.

2. Case of the applicant is that the applicant had submitted offer in pursuance to the Notice Inviting Tender floated by the respondents, and, thereafter, purchase order dated 10th of august 2019 was issued to the applicant for supply of 850 sets of joggled fishplates as per the specifications mentioned in the Tender Documents. The delivery period, at the instance of the applicant, was extended by the Railways by a letter dated 26th November 2018. There was some dispute about the inspection by the inspecting agency. Hence, the delivery period at the request of the applicant was again extended up to 8th March 2019 by a letter dated 8th of January 2019. according to the applicant, thereafter, the materials were duly inspected by the inspecting agency and the applicant had dispatched 265 sets of joggled fishplates to the respondents on 25th February, 2019 but respondents had refused to accept it. Hence the dispute arose between the parties. In paragraph 23 of the a.P., the applicant has disclosed that he suffered the loss of damages to the tune of Rs. 90,57,903/- (Rupees Ninety Lakhs Fifty Seven Thousand Nine Hundred Three). The applicant, vide letter dated 26th of June 2020, had invoked the arbitration clause and had sent a panel of three senior advocates seeking concurrence of the respondents for appointment of arbitrator from the said panel. Case of the applicant is that even after the letter dated 26th of June 2020, no arbitrator was appointed nor the dispute was resolved within 30 days. Hence, the respondents have lost their right to appoint arbitrator and, therefore, the applicant has approached this Court for appointment of arbitrator.

3. The arbitration clause in the agreement is undisputed which reads as under:

    '2903 : Demand for arbitration:

    2903(i): In the event of any dispute or difference between the parties hereto as to the construction or operation of this contract, or the respective rights and liabilities of the parties on any matter in question, dispute or difference on any account, or if the Railway fails to make a decision within 120 days (as referred in 2902), then and in any such case, but except in any of the 'excepted matters' referred to in Clause 2902 of these Conditions, parties to the contract, after 120 days but within 180 days of their presenting their final claim on disputed matters shall demand in writing that the dispute or difference be referred to arbitration. Provided that where the claim is raised by Railways para 2903(i) shall not apply.

    2903(ii)(a): The demand for arbitration shall specify the matters which are in question, or subject of the dispute or difference as also the amount of claim item-wise. Only such dispute or difference, in respect of which the demand has been made, together with counter claims or set off, shall be referred to arbitration and other matters shall not be included in the reference.

    2903(ii)(b): The parties may waive off the applicability of Sub-Section 12(5) of arbitration and Conciliation act 1996 (as amended), if they agree for such waiver in writing, after dispute having arisen between them.

    2903(iii)(a): The arbitration proceedings shall be assumed to have commenced from the day, a written and valid demand for arbitration is received by the Railway.

    2903(iii)(b): The claimant shall submit his claims stating the facts supporting the claims alongwith all the relevant documents and the relief or remedy sought against each claim within a period of 30 days from the date of appointment of the arbitral Tribunal.

    2903(iii)(c): Respondent shall submit its defence statement and counter claim(s), if any, within a period of 60 days of receipt of copy of claims from Tribunal, unless otherwise extension has been granted by arbitral Tribunal.

    2903(iii)(d): Place or arbitration: The plac

      Click Here to Read the rest of this document
      1
      2
      3
      4
      5
      6
      7
      8
      9
      10
      11
      SupremeToday Portrait Ad
      supreme today icon
      logo-black

      An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

      Please visit our Training & Support
      Center or Contact Us for assistance

      qr

      Scan Me!

      India’s Legal research and Law Firm App, Download now!

      For Daily Legal Updates, Join us on :

      whatsapp-icon telegram-icon
      whatsapp-icon Back to top