IN THE HIGH COURT OF ALLAHABAD
MAHESH CHANDRA TRIPATHI, PRASHANT KUMAR, JJ.
Indian Oil Corporation Ltd. – Petitioner
Versus
State of U.P. and Others – Respondents
Writ (C) No. 31555 of 2022
Decided On : 18-01-2024
JUDGMENT :
PRASHANT KUMAR, J.
1. Heard Sri Ankush Tandon, learned counsel for the petitioner and Sri M.C. Chaturvedi, learned Senior Advocate assisted by Sri Alok Mishra, learned counsel for respondent nos. 3 and 4.
2. The petitioner is public sector undertaking, working under the aegis of Ministry of Petroleum and Natural Gas, Government of India. The preliminary business of the petitioner is to refine crude oil, market petroleum and petroleum products. To refine the crude oil, the petitioner has set up a refinery in Mathura. Though the petitioner had a Captive Power Plant, but it was not able to generate required amount of electrical energy, so the petitioner entered into an agreement on 30.11.1999 (hereinafter referred to as the ‘Principal Agreement’) with U.P. Power Corporation Limited (hereinafter referred to as ‘UPPCL’), to provide a facility which is commonly known as “Parallel Operating System.” The relevant clauses of the ‘Principal Agreement’ are reproduced hereunder:
It has been agreed by the consumer that during the continuance of this agreement in addition to the minimum consumption guarantee provided in the rate schedule Clause 5(b) at annexure-2, he shall pay to the supplier every month a charge at the rate of 10% (ten per cent) of the aforesaid minimum consumption per KVA for 44118 (corresponding to 37500 KW) which is subject to revision from time to time. At the current rate the ten per cent of MCG works out to Rs. 50/- per KVA per month & the amount so chargeable works out to Rs. 22,05,900/- month.
Provided that if in any revision, the minimum consumption guarantee is revised downwards, the consumer shall nevertheless, be liable to pay the charges under this clause at the rates as were charged and paid by consumer before the revision.
Provided always that in the event of non-payment or delayed payment of aforesaid charge by the due date specified in the bill, the consumer shall be liable to pay ‘Additional Charge’ as provided in rate schedule Clause 8(b) at Annex-2, without prejudice tot he right of the supplier to discontinue the parallel Operating.
Clause 19
This agreement shall subject herein before provided be and remain in force for one year from the date of commencement of supply (hereinafter called the initial period of supply) and thereafter from year to year basis on the terms and conditions herein contained.
Provided that either party shall be at liberty to determine this agreement at any time after the expiration of the initial period of supply on giving one month’s notice in writing of such intention, and on the expiration of such notice, this agreement shall absolutely cease and determine, but without prejudice to the rights and remedies if any, of either party, which may have accrued or arisen hereunder in the meantime.
Provided further that if the consumer ceases taking supply of electrical energy due to any reason, he shall be liable to pay to the Supplier necessary charges as per provision made in the Regulation framed by the Supplier under Section 49 and 79 of the Electricity (Supply) Act, 1948.”
3. The “Parallel Operating System” is an additional facility where one electrical system operates with the connectivity to another system in similar operating condition i.e. synchronized system having same voltage, frequency and phase difference. In a simplified form, it can be said that in case if there is any variation in voltage and frequency then the grid stabilizes the variation of voltage.
4. As per the ‘Principal Agreement’ the petitioner started paying for the “Parallel Operating System.” Subsequently, the petitioner managed to augment its own Captive Power Plant and realized that they do not have any further requirements of the “Parallel Operating System.”
5. On 3.8.2001, petitioner sent a letter to UPPCL requesting for amendment to the ‘Principal Agreement’ as there was no requirement of “Parallel Operating System.” This was followed by a number of other similar communications requesting for d
Dehri Rohtas Light Railway Co. Ltd. vs. District Board, Bhojpur
Kusheshwar Prasad Singh vs. State of Bihar and Others
Maharashtra State Electricity Distribution Company Ltd. vs. JSW Steel Limited and Others
Mrutunjay Pani vs. Narmada Bala Sasmal
Nirmala Anand vs. Advent Corporation Pvt. Ltd. and Others
PTC India Ltd. vs. Central Electricity Regulatory Commission
State of Maharshtra vs. Digambar
The Chairman, State Bank of India and Another vs. M.J. James
A party cannot charge for services not rendered, and cannot benefit from its own delay in amending an agreement, as established under Section 56(2) of the Electricity Act, 2003.
Supplementary bills can be raised for mistakes, but disconnection for non-payment after two years is prohibited under Section 56(2) of the Electricity Act, 2003.
A licensee cannot exercise the power of electricity disconnection for the recovery of arrears that are more than two years old, unless such sums were continuously shown as recoverable in previous bil....
The Electricity Board must adhere to statutory notice requirements before disconnection and cannot recover charges post-disconnection without such compliance.
The court established that an electricity company can issue revised bills for bona fide mistakes in billing, reinforcing the consumer's obligation to pay based on accurate meter readings.
New owners of properties are liable to pay fixed electricity charges of prior tenants, while charges deemed unlawful cannot be enforced against them.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.