IN THE HIGH COURT OF ALLAHABAD, LUCKNOW BENCH
Alok Mathur, J.
M/s. Oriental Structural Engineers Pvt. Ltd. - Petitioner
Versus
State of U.P. and another - Respondents
Civil Misc. Writ Petition No. 22622 of 2021
Decided On : 19-12-2024
JUDGMENT :
Alok Mathur, J.
Heard Sri Nitesh Jain, learned counsel for the petitioner as well as learned Standing counsel and Sri Sachin Upadhyay for the respondents.
2. The Petitioner who had been allotted a plot from the Greater Noida Industrial Development Authority (hereinafter referred to as GNIDA) has disputed the handing over of the possession of the said plot and has claimed benefit of the zero period policy of the respondents. The respondents on the other hand have rejected his claim of possession and proceeded to levy penalty and notice for cancellation of the allotment of the plot, and even the revision preferred before the State Government has been rejected leading to the present writ petition.
3. It has been submitted by learned counsel for the petitioner that on 12.3.2008 and 30.6.2008 notifications under Section 4 read with Section 17 of the Land Acquisition Act, 1894 were issued by the State Government for acquisition of land of 589.188 Ha. situated at village Patwari, Greater Noida, Gautam Budh Nagar. Subsequent to the acquisition, the land was developed and offered for allotment of institutional plots for setting up educational hub, University, Training centers, Schools, Hospitals and office plots for self-use of various sizes. The petitioner made an application on 30.5.2008 for allotment of a plot of 20,000 m² for the purpose of setting up an office for self-use and deposited 10% of the application amount. The application of the petitioner was successful, and he was informed that he has been allotted a plot of 20,000 m² for a total premium of Rs. 15.80 Crores. Considering that the petitioner has already paid 10% of the sale consideration, he was required to pay the 20% of the amount within 60 days of the allotment letter, and the balance 70% of the premium was to be paid in 12 half yearly installments with an interest of 12% from 12.7.2009 onwards.
4. According to the terms and conditions of the allotment, the petitioner was required to complete the construction over the plot within 5 years from the date of the allotment. Though by means of the letter of allotment 20,000 m² of space was allotted to the petitioner, but the plot number was never communicated, but he proceeded to deposit further 20% of the premium. It is only on 13/11/2009 that the GNIDA informed the petitioner that the plot of an area 20,007.52 m² has been allotted at plot No. 3, Techzone IV, Greater Noida, and that he was to complete the formalities to get the lease deed registered. On 16.3.2010 a lease deed was executed in favour of the petitioner and a formal letter of possession was also issued by the GNIDA on the same day.
5. It has been submitted that plot No. 3 Techzone IV Greater Noida was carved out from khasras Nos. 321, 323, 324, 325, 342, 343, 344, 340, 331 village Patwari, District Buddhnagar. The petitioner stated that despite possession certificates having been issued in favour of the petitioner, the actual physical possession of the said plot was never given to him, and therefore the petitioner made repeated representations to the respondents to hand over the actual physical possession.
6. It is stated that on 15.6.2010, the Manager Institutional wrote a letter to the Officer on Special Duty (Project, Greater Noida) to nominate some officer to hand over actual physical possession. According to the petitioner, the letter dated 15.6.2010 evidences the fact that actual physical possession was never given to the petitioner, and even subsequently a number of letters and representations by the petitioner did not yield the result.
7. It is stated that by means of letter dated 2.6.2011, the petitioner was informed that the revised lease plan has been received by the respondents according to which the total area of the plot of the petitioner has been reduced from 20,007.52 m² to 20,000.76 m² and accordingly a correction deed was executed on 24.6.2011. Simultaneously a corrected possession certificate was also signed and delivered to the petition
Balwant Narayan Bhagde v. M.D. Bhagwat
Banda Development Authority v. Moti Lal Agarwal
Gajraj and others v. State of U.P. and others
Indore Development Authority v. Manoharlal
Actual physical possession must be established for lease obligations; mere issuance of possession certificate is insufficient.
Authority must deliver physical possession of land to the allottee; failure to do so grants the right to zero period benefits under lease agreements.
The main legal point established in the judgment is that delay and laches in approaching the Court can lead to the dismissal of a writ petition, especially in cases where possession of the land has b....
Once land has been acquired, it cannot be restored to tenure- holders/persons interested, even if it is not used for the purpose for which it is so acquired. Once possession of land has been taken, i....
Acquisition proceedings lapse under Section 24(2) of the 2013 Act if neither possession is taken nor compensation is paid.
No reasonable explanation being given by the petitioners for such inordinate delay, this court should not go into the stale demand of the petitioners after lapse of years.
The court established that failure to notify landowners and to take possession in accordance with the law invalidates the land acquisition process.
The main legal point established in the judgment is that under Section 24(2) of the Fair Compensation Act, the acquisition proceedings would lapse if the possession of the land was not taken and comp....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.