2025 Supreme(All) 2606
IN THE HIGH COURT OF ALLAHABAD
Siddhartha Varma, Yogendra Kumar Srivastava, JJ.
Mrs Manju Rakesh - Petitioner
Vs.
State Of Up And Others - Respondent
WRIT - C No. 38488, 38495, 38521 of 2024
Decided On : 09-01-2025
Advocate Appeared:
For the Petitioner: Ravi Kant,Vatsala
For the Respondent: Ankit Prakash, Ashok Kumar Srivastava,C.S.C.,Mohd. Afzal
The High Court cannot interfere with ongoing insolvency proceedings under the Insolvency and Bankruptcy Code, emphasizing the need for petitioners to pursue remedies within that framework.
Headnote:(A) Real Estate (Regulation and Development) Act, 2016 - Section 8 - Insolvency and Bankruptcy Code, 2016 - Writ petitions filed by home buyers against the builder for delay in possession of flats and refund of amounts. The UPRERA had directed possession within a specified time, failing which refund was mandated. Petitioners sought to quash orders directing refund, claiming it was never requested. Court found challenge to refund order belated and noted ongoing CIRP proceedings, emphasizing that interference with such proceedings is not permissible. (Paras 3, 10, 12, 17)
(B) Writ Jurisdiction - The High Court's intervention in ongoing insolvency proceedings is limited, and petitioners must pursue remedies under the Insolvency and Bankruptcy Code. (Paras 14, 16)
Facts of the case:
Petitioners, home buyers in a delayed housing project, sought possession of flats after UPRERA's orders for refund due to non-compliance by the builder. Recovery certificates were issued but remained unexecuted. Insolvency proceedings against the builder were initiated. (Paras 3, 4, 6)
Findings of Court:
The court declined to entertain the writ petitions due to the ongoing CIRP, reinforcing that home buyers' claims are being considered within that framework. (Paras 17, 19)
Issues: Whether the petitioners can challenge the refund orders and seek possession despite ongoing insolvency proceedings. (Paras 8, 12)
Ratio Decidendi: The court held that allowing the writ petitions would interfere with the CIRP process, which is governed by the Insolvency and Bankruptcy Code, emphasizing the importance of finalizing the resolution plan. (Paras 14, 16)
Result: Writ petitions disposed of.
| Table of Content |
|---|
| 1. home buyers seek possession of flats due to builder's non-compliance. (Para 3 , 4 , 5 , 6 , 7) |
| 2. petitioners argue against refund orders and seek possession. (Para 8 , 9 , 10 , 11) |
| 3. court emphasizes alternative remedies under the insolvency act. (Para 12 , 13) |
| 4. supreme court reinforces the integrity of the cirp process. (Para 14 , 15 , 16) |
| 5. writ petitions not entertained; petitioners can pursue legal remedies. (Para 17 , 18 , 19) |
JUDGMENT :
1. Heard Ms Vatsala, learned counsel for the petitioners, Sri Ankit Prakash, learned counsel for respondent no.2, Sri Rohan Gupta, learned counsel for respondent no.3 and learned Standing Counsel for the State.
2. Learned counsel for the parties have agreed that all the writ petitions are based on similar set of facts and have sought similar reliefs, and that they may be heard and decided together.
3. The petitioners/home buyers claim to have been allotted residential flats in project ‘Knights Court’ - Jaypee Greens Wish Town, Sector-128, Noida, Uttar Pradesh developed by Builder-Respondent no.3/Jaiprakash Associates Ltd. Aggrieved by the delay in completion of the project and handing over of possession of the flats in question, the petitioners in Writ- C No.38488 and Writ-C No.38521 of 2024, filed complaints before the Uttar Pradesh Real Estate Regulatory Authority [UPRERA]which were allowed in terms of the orders dated 6.5.2019, with a direction to respondent no.3 to handover possession within a period of 45 days from the date of the order, and in case it was unable to do so, to refund the amount deposited together with interest.
4. It is stated that respondent no.3-Builder neither handed over possession of the residential flats in question, nor refunded the amount, hence, in regard to the petitioners in Writ-C No.38488 and Writ-C No.38521 of 2024, recovery certificates, bearing dates 18.12.2020 and 10.1.2020 were issued by the UPRERA. An agreement dated 22.1.2021 was entered into between respondent no.3-Builder and the Association of Home Buyers of the Project, for completion of project and handing over possession to all the home buyers under the provisions of the UPRERA. Thereafter, an order of rehabilitation under Section 8 of the Real Estate (Regulation and Development) Act, 2016 [Act, 2016]was passed by the UPRERA, directing completion of project and delivery of possession, within a specified time period. It has been asserted in Writ-C No.38488 of 2024 that upon consent being accorded by the petitioners, on 31.3.2021, an order was passed by the UPRERA, directing that recovery certificate issued pursuant to the order dated 6.5.2019 be kept in abeyance. The petitioners in Writ-C No.38521 of 2024 have also stated that they accorded their consent for completion of project and taking of possession consequent to the agreement dated 22.1.2021.
5. The petitioners in Writ-C No.38495 of 2024, also filed a complaint before the UPRERA, which was decided by means of an order dated 27.7.2021 wherein, keeping in view the order of rehabilitation which had been passed earlier, a direction was issued for refund of the amount on completion of the project after 30.4.2022. It is stated that due to non- compliance of the order by respondent no.3, the UPRERA issued a recovery certificate dated 22.5.2024, which has remained un-executed.
6. In due course of time, insolvency proceedings were initiated against respondent no.3-Builder on a petition filed by the Banks/Financial Institutions and a Resolution Professional [RP] was appointed by the National Company Law Tribunal [NCLT] to manage the affairs of respondent no.3-Builder.
7. The petitioners in Writ-C No.38488 and Writ-C No.38521 of 2024 submitted their claims on 15.6.2024 and 21.6.2024 respectively under the Insolvency and Bankruptcy (Insolvency Resolution Process for Corporate Persons) Regulations, 2016. [CIRP Regulations, 2016] The petitioners in Writ-C No.38495 of 2024 are stated to have sent an e-mail to the RP on 3.11.2024 for ‘conver