IN THE HIGH COURT OF JUDICATURE AT ALLAHABAD LUCKNOW BENCH
JASPREET SINGH, J.
M/s Transrail Lighting Ltd. – Appellant
Versus
Madhyanchal Vidyut Vitran Nigam Ltd. and Another – Respondents
Civil Misc. Arbitration Application No. 91 of 2024
Decided On : 14-05-2026
| Table of Content |
|---|
| 1. petitioner seeks recall of arbitrator appointment due to alleged conflict between general and special contract conditions. (Para 1 , 2 , 3 , 4) |
| 2. historical context of appointment and petitioner's reliance on novation of arbitration clauses. (Para 5 , 6 , 7) |
| 3. maintainability of recall petition and inherent power of high court as a court of record. (Para 8 , 9 , 10 , 11 , 12 , 13 , 14) |
| 4. limited scope of high court to review section 11 orders; limited to procedural lapses. (Para 15 , 16 , 17 , 18 , 19 , 20 , 21 , 22) |
| 5. review powers of court of record are narrow and reserved for preventing serious miscarriage of justice. (Para 23 , 24 , 25 , 26 , 27 , 28) |
| 6. application of waiver and estoppel principles when parties consent to arbitral tribunal structure. (Para 29 , 30 , 31) |
| 7. the court refuses to exercise recall powers where parties participated in formation of tribunal without objection. (Para 32 , 33) |
JUDGMENT :
JASPREET SINGH, J.
IA No. 3 of 2025 and IA No. 4 of 2025
1. The instant application for recall has been moved by the petitioner along with an application seeking condonation of delay, whereby the petitioner prayed that after condoning the delay the order dated 17.07.2025 and 07.08.2025 be recalled and its consequence would be that the mandate of nominee arbitrator appointed by this Court, on behalf of the respondents, in terms of Section 11(4) of the Arbitration and Conciliation Act, 1996 (for short, 'the Act of 1996') would be terminated.
2. Notices were issued on the aforesaid application on 26.11.2025 and in furtherance thereof the respondents have filed their objections on 12.03.2026.
3. Shri Abhinav Kumar Mathur and Ms. Sushmita Mukharjee, learned counsel for the petitioner submitted that the petitioner had preferred a petition under Section 11(6) of the Act of 1996 and the Court while exercising its power under Section 11(4) of the Act appointed a nominee arbitrator on behalf of the respondents.
4. It was submitted that the parties had entered in a contract which contained an arbitration clause. However, special conditions of contract prescribed appointment of a Sole Arbitrator for all disputes and claims which were valued upto Rs.25.00 Crores. It was further submitted that special conditions of contract could not be referred by the petitioner or by the respondent during the course of submissions and no specific reference was made to it in the pleadings of the petition under Section 11(6) of the Act of 1996. Thus, the said fact could not be brought to the notice of the Court and the appointment of the nominee arbitrator in terms of Section 11(4) of the Act of 1996 was made in terms of the general conditions of the contract, which stood novated by the special conditions of contract.
5. The Court while hearing the petition under Section 11(6) of the Act of 1996 and considering the submissions of the parties vide order dated 17.07.2025, found that the parties had entered into a contract which contained an arbitration clause. The Court also found that the disputes had occurred and the petitioner had invoked the arbitration clause appropriately and it had also nominated its arbitrator. Since, the respondents did not nominate its arbitrator, hence, the Court after receiving the consent from the proposed arbitrator appointed a nominated arbitrator on behalf of the respondents vide order dated 07.08.2025.
6. It was further submitted that the nomination of the respondents' party arbitrator was against special conditions of contract, which novated and superseded the arbitration clause contained in Clause 39 of the general conditions of contract.
7. It was also submitted that the aforesaid discrepancy could not be noticed and later the said fact came to the notice of the petitioner while undertaking a detailed examination of the contract documents. Immediately thereafter, acting with due diligence, this application for recall was moved and it was prayed that any delay in moving the said application be condoned, a
Municipal Corporation of Greater Mumbai and others v. Pratibha Industries Ltd.
Hindustan Construction Company Ltd. v. Bihar Rajya Pul Nirman Nigam Limited and others
Kapra Mazdoor Ekta Union v. Management of Birla Cotton Spinning and Weaving Mills Ltd. and others
The High Court lacks jurisdiction to review an order passed under Section 11 of the Arbitration and Conciliation Act, 1996, as the Act is a self-contained code and the Court becomes functus officio u....
The judicial nature of proceedings under section 11(6) of the Arbitration and Conciliation Act, 1996, and the requirement for providing an opportunity of hearing before the appointment of an Arbitrat....
The interpretation of Section 15(2) of the Arbitration and Conciliation Act, 1996 is that where the mandate of an arbitrator terminates, a substitute arbitrator shall be appointed according to the ru....
A Settlement Agreement can nullify an existing Arbitration Agreement, preventing disputes from being referred to arbitration.
Point of Law : S.13(2) provides that a party who intends to challenge appointment of an arbitrator shall, within fifteen days after becoming aware of the constitution of the arbitral tribunal or afte....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.