IN THE HIGH COURT OF JUDICATURE AT ALLAHABAD
AJIT KUMAR, SWARUPAMA CHATURVEDI, JJ.
South East U.P. Power Transmission Company Limited – Appellant
Versus
Prescribed Authority and Others – Respondents
Writ (C) No. 19391 of 2023, Writ (C) No. 17846 of 2025
Decided On : 24-04-2026
| Table of Content |
|---|
| 1. overview of factual matrix and background of the electricity demand dispute. (Para 1 , 2 , 3 , 4 , 5 , 6 , 7 , 8 , 9 , 10 , 11 , 12 , 13 , 14 , 15 , 16 , 17 , 18 , 19) |
| 2. parties argument regarding pre-cirp liability and applicability of clean slate doctrine. (Para 20 , 21 , 22 , 23 , 24 , 25 , 26 , 27 , 28 , 29 , 30 , 31 , 32 , 33 , 34 , 35 , 36 , 37 , 38 , 39 , 40 , 41 , 42 , 43 , 44 , 45 , 46 , 47 , 48 , 49 , 50 , 51 , 52 , 53 , 54) |
| 3. ibc contains non-obstante clause (section 238) overriding sector-specific legislations like electricity act. (Para 55 , 56 , 57 , 58 , 59 , 60 , 61 , 62 , 63 , 64 , 65 , 66 , 67 , 68 , 69 , 70 , 71 , 72 , 73 , 74 , 75 , 76 , 77 , 78 , 79 , 80 , 81 , 82) |
| 4. binding effect of approved resolution plans and extinguishment of unclaimed pre-cirp debts. (Para 83 , 84 , 85 , 86 , 87 , 88 , 89 , 90 , 91 , 92 , 93 , 94 , 95 , 96 , 97 , 98 , 99 , 100 , 101 , 102 , 103 , 104 , 105 , 106 , 107 , 108 , 109 , 110 , 111 , 112 , 113) |
| 5. quashing of illegal pre-cirp demand notices while permitting post-resolution claims. (Para 114 , 115 , 116) |
JUDGMENT :
SWARUPAMA CHATURVEDI, J.
1. Both writ petitions, filed under Article 226 of the Constitution of India, arise out of a similar grievance, wherein the respective petitioners challenge the demand notices issued to them towards electricity dues pertaining to the period prior to the commencement of the Corporate Insolvency Resolution Process (hereinafter referred to as “CIRP”) of the concerned companies, which are resolved long ago after following due procedure prescribed under Insolvency and Bankruptcy Code, 2016 (hereinafter referred to as “IBC”). In Writ C No.19391 of 2023, the petitioner seeks issuance of a writ, order or direction in the nature of certiorari for quashing the impugned demand notices, whereas in Writ C No.17846 of 2025, the petitioner, prays for issuance of a writ of certiorari to quash the impugned demand to the extent it pertains to the period prior to the approval of the resolution plan, and a writ of mandamus restraining the respondents from taking any coercive action pursuant to the said notices and subsequent actions.
2. Since the reliefs sought in both the petitions are substantially similar, and the matters arise out of a similar set of facts involving identical questions of law, both the petitions were taken up together for hearing and are being decided by this common order. However, the necessary facts pleaded in each writ petition, as well as the submissions advanced on behalf of the parties therein, are being noticed separately wherever required.
(I) Factual Matrix
3. The factual matrix in Writ C No. 19391 of 2023 is that the Isolux Corsan Concesiones S.A. (hereinafter referred to as “Isolux”) has received a letter of intent dated 05.07.2011 by the Uttar Pradesh Power Transmission Company Limited (hereinafter referred to as “UPPTCL”) to establish a 765 kV transmission system on a Build- Own-Operate-Maintain & Transfer (BOOT) basis at Mainpuri-Bara line.
4. Pursuant thereto, the Petitioner company was incorporated as a special purpose vehicle in September 2011 to implement and operate the said transmission system, and its 100% shareholding was subsequently acquired by Isolux on 16.12.2011. In furtherance to this, on 20.01.2012, the petitioner entered into Transmission Service Agreements with the distribution licensees (hereinafter referred to as “DISCOMs”) in the State of Uttar Pradesh.
5. Thereafter, on 25.09.2013, the petitioner applied to Respondent No.1 seeking a 630 KVA, 33 kV auxiliary power supply at the 400/220 kV Rewa Road GIS Sub-station. On 04.01.2014, the petitioner informed UPPCL of its requirement for two 33 kV auxiliary sources for safe operations, specifically indicating that one such source was being drawn through the tertiary winding of Inter-Connecting Transformer-II (hereinafter referred to as “ICT-II”). Subsequently, an Electrical Energy Supply Agreement dated 18.04.2015 came to be executed between the peti
Committee of Creditors of Essar Steel India Ltd. v. Satish Kumar Gupta
Ghanshyam Mishra & Sons (P) Ltd. v. Edelweiss Asset Reconstruction Co. Ltd.
RPS Infrastructure Ltd. v. Mukul Kumar
Paschimanchal Vidyut Vitran Nigam Ltd. v. Raman Ispat Pvt. Ltd.
Telangana State Southern Power Distribution Company Ltd. v. Srigdhaa Beverages
Pre-CIRP debts are extinguished upon approval of the Resolution Plan under the IBC, and the pendency of an appeal does not automatically stay the implementation of the approved Resolution Plan.
The 'Clean Slate' theory established by the Supreme Court in insolvency cases extinguishes all claims not included in the Resolution Plan, impacting the rights of creditors and other parties involved....
Claims against a successful resolution applicant for dues not presented during CIRP are extinguished after approval of the resolution plan, confirming the clean slate principle.
The approved Resolution Plan under the Insolvency and Bankruptcy Code binds all creditors, extinguishing claims not included, ensuring no surprise liabilities arise post-approval.
Once a resolution plan is approved under the Insolvency and Bankruptcy Code, all claims for periods prior to its implementation are extinguished and cannot be enforced against the corporate debtor.
The approval of a resolution plan under the IBC extinguishes all claims not included in the plan, including tax liabilities, ensuring a fresh start for the corporate debtor.
The approval of a resolution plan under the IBC extinguishes all claims not included in the plan, including tax liabilities.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.