SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2022 Supreme(UK) 186

IN THE HIGH COURT OF UTTARAKHAND AT NAINITAL
VIPIN SANGHI, R.C. KHULBE, JJ.
Unicon Builders and Contractors – Appellant
Versus
State of Uttarakhand and another - Respondents
Writ Petition (M/S) No. 3067, 3063 of 2018
Decided on : 19-09-2022

Advocates:
Advocate Appeared:
For the Appellant : Mr. Bhuwan Bhatt
For the Respondents: Mr. B.P.S. Mer, Mr. Pradeep Chamiyal, adv

The court emphasized the importance of the respondents providing a clear basis for their claims and considering the petitioner's submissions in compliance with the previous court direction.

Headnote:

Tendering Process - UDRP/PWD/07/RD/118 and UDRP/PWD/07/RD/119 - ITB Clause 40.1, ITB Clause 45.1, ITB Clause 45.2 - The court quashed the impugned order and remanded the matter to the respondents to clearly state the basis for claiming that the bids/rates submitted by the petitioner were substantially low. The respondents were directed to consider the analysis of rates furnished by the petitioner and pass a reasoned order.

Fact of the Case:

The petitioner participated in the tendering process for two works. The respondents required the petitioner to submit additional performance security, and upon refusal, sought to forfeit the bid security. The petitioner had previously filed a writ petition, which was disposed of with a direction to the respondents to consider the case in terms of Clause 40.1 of the Instructions to Bidders (ITB). The respondents passed an impugned order, but the court found it non-compliant with the previous order.

Finding of the Court:

The court quashed the impugned order and remanded the matter to the respondents to clearly state the basis for claiming that the bids/rates submitted by the petitioner were substantially low. The respondents were directed to consider the analysis of rates furnished by the petitioner and pass a reasoned order.

Issues: Requirement of additional performance security, compliance with ITB Clause 40.1, non-compliance of the impugned order with the previous court direction.

Ratio Decidendi: The respondents must clearly state the basis for claiming that the bids/rates submitted by the petitioner were substantially low and consider the analysis of rates furnished by the petitioner in compliance with the previous court direction.

Final Decision: The impugned order was quashed, and the matter was remanded to the respondents for further consideration and a reasoned order.

JUDGMENT :

Sri Vipin Sanghi, J.

The petitioner has preferred these two writ petitions in similar circumstances.

2. The petitioner participated in the tendering process in relation to two works, namely UDRP/PWD/07/RD/118 and UDRP/PWD/07/RD/119. Writ Petition (M/S) No. 3063 of 2018 relates to the first of these works, whereas Writ Petition (M/S) No. 3067 relates to the second work aforesaid.

3. For the purpose of ease, we are treating Writ Petition (M/S) No.3067 of 2018 as the lead matter, and taking note of the facts and circumstances in relation to the said case. The facts of the other case are also similar.

4. The estimated cost of the work in relation to the Package No. UDRP/PWD/07/RD/119 was Rs.1528.53 lacs. The bid submitted by the petitioner in response to the said Package was of Rs. 15,24,91,267.15. Thus, the bid of the petitioner was only about four lacs less than the estimated cost. The respondents issued the Letter of Acceptance on 23.09.2017, wherein the respondents, inter alia, required the petitioner to submit an Additional Security Performance Security to the tune of Rs.2,88,69,664.72 “for unbalanced bids in terms of ITB Clause 40”. The Communication, however, did not state as to how the petitioner’s bid was claimed to be “unbalanced”. It merely stated that the total Contract Price “excluding of GST and inclusive of levies and other duties is .12,92,29,887.40”, and that the “Total amount of GST payable at the time of deadline bid submission @ 18% is .2,32,61,379.73”.

5. Since the petitioner did not agree to furnish the Additional Performance Security-claiming that the same was contrary to the terms of the Contract, the respondents sought to forfeit the bid security of the petitioner.

6. The petitioner earlier preferred Writ Petition (M/S) No. 2798 of 2017. The case of the petitioner was that the respondents had not given any basis to claim that there was any justification to require the petitioner to furnish additional performance security under Clause 40.1 of the ITB. The said Clause reads as under:-

    “40.1 If the bid, which results in the lowest Evaluated Bid Price, is seriously unbalanced, front loaded or substantially below updated estimates in the opinion of the Employer, the Employer may require the Bidder to produce detailed price analyses (with breakdown of unit rates) for any or all items of the Bill of Quantities, to demonstrate the internal consistency and justification of those prices with the construction methods and schedule proposed. After evaluation of the price analyses, taking into consideration the schedule of estimated contract payments, the Employer may require that the amount of the performance security be increased at the expense of the Bidder to a level sufficient to protect the Employer against financial loss in the event of default of the successful Bidder under the Contract.”

7. The said writ petition was disposed of by the learned Single Judge with a direction to the respondents to consider the case of the petitioner in terms of Clause 40.1 of the Instructions to Bidders (ITB). The petitioner was required to give its explanation within a week, and the respondent-Employer was required to pass an order in accordance with law. The order further stated that “If the employer comes to the conclusion that the bid price of the petitioner is extremely low and work cannot be done, the employer would always be at liberty either to ask for the additional performance guarantee, or to cancel the bid and go for fresh bid, after explaining the changed circumstances in terms of public money”.

8. The respondents have now passed the impugned order dated 31.08.2018 stating it to be in compliance of the said order, wherein the respondents have stated as follows:-

    ^^ek0 mPp U;k;ky; uSuhrky }kjk ikfjr vkns'k ds dze esa vk[;k fcUnqokj fuEukuqlkj gS& fufonknkrk M/s Unicon Builders & Contractor }kjk vius i=kad UBC/PB/2018/551 fnukad 02-07-2018 }kjk bl dk;kZy; dks fnukad 02-07-2018 esa ek0 mPp U;k;ky; }kjk nh x;h ,d lI

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top