MADHYA PRADESH HIGH COURT
Alok Aradhe, J.
Deepak Nagle - Appellant
Versus
State of M.P. - Respondent
W.P. No. 10120 of 2013
Decided On : 20-03-2014
Termination - Contractual Employee - Clause 15 of the contract of appointment - S.N. Mukherjee vs. Union of India, (1990)4 SCC 594 - Secretary and Curator, Victoria Memorial Hall vs. Howrah Ganatantrik Nagrik Samity and others, (2010) 3 SCC 732 - Makhan Lal Ahirwar vs. State of M.P., W.P. No. 5098/2012
Fact of the Case:
The petitioner, a contractual employee, had his services terminated without proper opportunity of hearing. The termination was based on an inspection carried out behind the petitioner's back, and the reply submitted by the petitioner was not considered.
Finding of the Court:
The court found that the termination of the petitioner was stigmatic in nature and passed in violation of principles of natural justice. The impugned orders were quashed, allowing the respondents to take action against the petitioner in accordance with the law.
Issues: Validity of termination of a contractual employee, compliance with principles of natural justice, consideration of reply submitted by the petitioner.
Ratio Decidendi: Termination of a contractual employee must be in compliance with the principles of natural justice, including affording the employee proper opportunity of hearing and considering their submissions. The absence of reasons renders the order indefensible and unsustainable, particularly when subject to further challenge before a higher forum.
Final Decision: The orders dated 28-12-2012 and 22-1-2013 were quashed, allowing the respondents to take action against the petitioner in accordance with the law.
Judgment
Alok Aradhe, J.
1. With the consent of learned counsel for parties, matter is heard finally. In this writ petition the petitioner inter aha has assailed the validity of the orders dated 28-12-2012 and 22-1-2013.
2. Facts giving rise to filing of the writ petition briefly stated are that the petitioner was appointed as Sub-Engineer on contract basis vide order dated 9-1-2008. The petitioner got executed the work of construction of 500 meters of drain in Gram Panchayat Bada Gaon, Janpad Panchayat Teonthar, District Rewa. The work of construction of drain was commenced on 3-7-2010 and was completed on 31-8-2010 and a completion certificate was also issued on the same day. It is the case of the petitioner that drain of 500 meters in length was constructed with total expenditure of Rs. 2,82,393/-. The Sub Divisional Officer issued two show cause notices dated 5-10-2011 and 25-1-2011 contained in Annexures-P-6 and P-7, respectively to the petitioner in which inter aha it was alleged that the Gram Panchayat Badagaon had got the sanction of construction of drain of 250 meters in length under the guidance of the petitioner. In respect of the aforesaid work a complaint was received which was investigated into and it was found out that a sum of Rs. 2,83,393/- was spent against sanctioned amount of Rs. 2,84,000/- for construction of 225 meters drain in length against the sanctioned length of 250 meters. It was alleged that the petitioner had done excess valuation in respect of the work in question to the tune of Rs. 1,53,759/-. The petitioner was accordingly asked to show cause as to why his services be not dispensed with. The petitioner submitted reply to the aforesaid show cause notice. It was inter alia pointed out in the reply that total length of drain which was constructed was 500 meters but the investigating team has got the inspection done behind the back of the petitioner and therefore half of the length was measured whereas the entire work was done and the completion certificate in this regard was also issued. Thereafter, again a show cause notice dated 3-12-2012 was issued to the petitioner by the Collector. The petitioner submitted reply to the aforesaid show cause notice, however, by an order dated 20-12-2012 the services of the petitioner were dispensed with on the ground that his reply was not found satisfactory. Being aggrieved by the aforesaid order the petitioner preferred an appeal. The aforesaid order was affirmed in appeal by the Additional Commissioner vide order dated 22nd January, 2013. In the aforesaid factual background, the petitioner has approached this Court.
3. Learned counsel for the petitioner submitted that services of the petitioner who was a contractual employee have been terminated by a non-speaking order without affording him proper opportunity of hearing. It was further submitted that the investigation was carried out behind the back of the petitioner. In support of his submission learned counsel for the petitioner has placed reliance on order dated 20th November, 2012 passed in the case of Makhan Lal Ahirwar vs. State of M.P., W.P. No. 5098/2012. On the other hand learned Panel Lawyer has submitted that the opportunity of hearing was afforded to the petitioner and since the reply submitted by the petitioner was not found satisfactory, therefore, his services were dispensed with.
4. I have considered the respective submissions made by learned counsel for the parties and have perused the record. The petitioner was appointed on contract basis. Clause 15 of the contract of appointment provides that in case the petitioner is found guilty of any misconduct or is involved in any criminal activities, the competent authority shall afford an opportunity of hearing to the petitioner and can terminate the appointment. Thus, it is evident that before terminating the services of an employee who is employed on contract basis, an opportunity of hearing has to be afforded to the delinquent employee.
The main legal point established in the judgment is the binding effect of the settlement between the parties, the waiver of the right to seek re-employment by the workmen, and the entitlement of the ....
A lockout is justified if it is declared in response to an illegal strike or a strike that is in breach of a settlement or award.
The combination of eyewitness testimonies, recovery of the weapon used, and forensic examination results can establish guilt in criminal cases, even based on circumstantial evidence.
The conviction of an accused person under Section 27(3) of the Arms Act is not permissible in law if the accused is also charged with committing murder under Section 302 of the Indian Penal Code.
The court can enhance compensation based on the deceased's income and family dependency, and adjust the multiplier used by the Tribunal if found unjustified.
A valid signature must be in the candidate's own handwriting, as emphasized by the General Clauses Act and relevant case law.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.