IN THE HIGH COURT OF MADHYA PRADESH (INDORE BENCH)
PRAKASH SHRIVASTAVA, J.
INDIAN CONSTRUCTION CO (GUJ) LTD - Appellant
Vs.
INDORE MUNICIPAL CORPORATION AND ANR. - Respondents
Arbitration Case No. 14 of 2015
Decided On : 01-08-2017
Arbitration - Indore Municipal Corporation - Madhyastham Act, 1983 - Section 2(1)(g), Section 7(1), Section 2(1)(i) - The court examined the issue of whether the Indore Municipal Corporation is a public undertaking as defined in Section 2(1)(g) of the Madhyastham Act and concluded that it is substantially controlled by the State Government, making it a public undertaking. The court held that the applicant has a remedy to approach the statutory Arbitration Tribunal constituted under the Madhyastham Act and rejected the application under Section 11(6) of the Arbitration and Conciliation Act, 1996.
Fact of the Case:
The applicant sought the appointment of an independent arbitrator for a dispute with the Indore Municipal Corporation regarding a construction contract. The respondent argued that the applicant should seek arbitration under the Madhyastham Act and that the claim had become time-barred.
Finding of the Court:
The court found that the Indore Municipal Corporation is a public undertaking as defined in the Madhyastham Act and that the applicant has a remedy to approach the statutory Arbitration Tribunal under the Act. The court rejected the application under the Arbitration and Conciliation Act, 1996.
Issues: The core issue was whether the Indore Municipal Corporation is a public undertaking as defined in the Madhyastham Act and whether the applicant has a remedy before the Madhyastham Tribunal.
Ratio Decidendi: The court analyzed the provisions of the Madhyastham Act, specifically Section 2(1)(g) and Section 7(1), and concluded that the Indore Municipal Corporation is substantially controlled by the State Government, making it a public undertaking under the Act.
Final Decision: The court rejected the application under Section 11(6) of the Arbitration and Conciliation Act, 1996, and held that the applicant has a remedy to approach the statutory Arbitration Tribunal constituted under the Madhyastham Act.
Prakash Shrivastava, J.
By this arbitration case filed under Section 11(6) of the Arbitration and Conciliation Act, 1996 a prayer has been made by the applicant for appointing the independent arbitrator for resolving the dispute between the parties.
2. The case of the applicant is that the Respondent-Indore Municipal Corporation had awarded the contract to the applicant for construction of overflow spillway across river Gambhir and the work order dated 18.4.2007 was issued with stipulated period of 24 months. The completion of the work was delayed for certain reasons and the completion certificate was finally issued on 30.9.2012. Certain amount was withheld by the respondent-Municipal Corporation, therefor, the applicant had sent the letter dated 21.5.2012 and 26.9.2012. The defect liability period of 24 months expired on 30.9.2014, therefore, vide letter dated 13.10.2014 a request was made by the applicant for retaining Rs.20 Lakhs and releasing the balance amount but the respondent-Municipal Corporation retained more than the said amount and had released only Rs.45,32,727/-. According to the applicant, he is entitled to a sum of Rs.5,75,74,381.50. The applicant had served the notice dated 21.4.2015 on the Commissioner and made unsuccessful attempt to serve notice dated 21.4.2015 and 15.5.2015 to the Engineer-in-charge and the Project Officer. Thereafter notice dated 2.7.2015 was sent to appoint the panel of arbitrator in terms of the arbitration clause. Since no action was taken by the respondents, therefore, present arbitration case is filed.
3. The respondents have filed the reply taking the stand that the work awarded to the applicant was in the nature of Works Contract and the respondent-Indore Municipal Corporation is a public undertaking, therefore, the applicant has remedy to seek arbitration under the M.P. Madhyastham Adhikaran Adhiniyam, 1983 (For short "Madhyastham Act") and the present application is not maintainable and that the bills of the applicant have been settled and the claim has now become time barred.
4. Core issue is as to whether the Indore Municipal Corporation is a public undertaking as defined in Section 2(1) (g) of the Madhyastham Act and applicant has remedy before the Madhyastham Tribunal?
5. Counsel for both the parties have relied upon the judgments of this Court as well as the Hon'ble Supreme Court in support of their submission. In order to find out if the aforesaid issue is concluded by any of them, these judgments are examined at the first instance.
6. Learned counsel for the respondents has referred to the Full Bench judgment of this Court in the matter of Gulab Bai wd/o Shriram Chandra Sanotia and others Vs. Subhash Chandra, 2013 (3) MPLJ 434 but the said judgment was delivered in different context wherein the issue was in respect of the entitlement of a landlord, who was a retired employee of the Municipal Corporation, to approach the Rent Controlling Authority under Section 23-A of the M.P. Accommodation Control Act. In the definition of landlord under Section 23-J, retired servant of a Company owned and controlled either by the Central or State Government, are covered. The said definition is materially different from the definition of public undertaking given in Section 2(1)(g) of the Madhyastham Act. Even otherwise in the matter of Subhash Chandra Vs. Gulab Bai and others, 2016 (4) SCC 750, the Hon'ble Supreme Court has referred the matter to the larger bench for interpretation of Section 23(J)(ii) of the M.P. Accommodation Control Act.
7. In another judgment in the matter of Administrator, Municipal Corporation, Drug and others Vs. M/s. Janico Designers and Executors, Drug, 1991 AIR(MP) 233 before the Full Bench of this Court issue of arbitrability by Madhyastham Tribunal had come up, wherein the Municipal Corporation was superseded and administrator was appointed, therefore, the full bench had taken the view that for the dispute between the administrator and contractor executing
Subhash Chandra Vs. Gulab Bai and others
Om Construction Company Vs. Ahmedabad Municipal Corporation and Another
AI
The main legal point established in the judgment is the binding effect of the settlement between the parties, the waiver of the right to seek re-employment by the workmen, and the entitlement of the ....
A lockout is justified if it is declared in response to an illegal strike or a strike that is in breach of a settlement or award.
The combination of eyewitness testimonies, recovery of the weapon used, and forensic examination results can establish guilt in criminal cases, even based on circumstantial evidence.
The conviction of an accused person under Section 27(3) of the Arms Act is not permissible in law if the accused is also charged with committing murder under Section 302 of the Indian Penal Code.
The court can enhance compensation based on the deceased's income and family dependency, and adjust the multiplier used by the Tribunal if found unjustified.
A valid signature must be in the candidate's own handwriting, as emphasized by the General Clauses Act and relevant case law.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.