2021 Supreme(MP) 505

IN THE HIGH COURT OF MADHYA PRADESH
Mohammad Rafiq, CJ, and Vijay Kumar Shukla, J.
K & J Projects Pvt. Ltd. M/s v. Madhya Pradesh Road
Development Corporation &Another
Writ Petitions No. 1137 of 2021and 11239 of 2021 and (Jabalpur); Decided on 27.8.2021

Advocates:
Deepesh Joshi for petitioners; P.K. Kaurav, Advocate General with Aditya Khandekar for respondents.

Headnote:

(1) Tender -- debarment -- prospective bidder was obligated/required to examine and verify credentials of professional staff and had to certify that contents of their curriculum vitae (CV) were true and correct -- Request for Proposal clearly mandates that if any false information or mis representation is done, respondents can debar said employee as well as firm that submitted fabricated CV -- debarment upto 5 years can take place -- debarment for two years

-- not disproportionate. (1995) 3 SCC 334 and (2013) SCC Online MP 5471 referred to. (2021) 1 SCC 804 distinguished.

[Paras 27, 28 & 37

(2) Natural Justice -- opportunity of hearing -- tender -- debarment -- respondents issued show cause notice in clear terms to petitioner and its employee -- they submitted responses -- after considering them, orders of debarment were issued -- no illegality in decision-making process. (2014) 14 SCC 731 and (2014) 9 SCC 105 referred to. [Para 32

¼1½ fufonk && footZu && Hkkoh cksyh yxkus okys ds fy, deZpkfjo`an ds izek.ki=ksa dk ijh{k.k vkSj lR;kiu djuk ck/;dj@vko';d Fkk rFkk mls izekf.kr djuk Fkk fd muds djD;qye fo VkbZ ¼lh oh½ dh varoZLrq lR; vkSj lgh gS && izLrko ds vuqjks/k esa Li"Vr% vkKkfir fd ;fn dksbZ feF;k tkudkjh nh tkrh gS ;k nqO;Zins'ku fd;k tkrk gS rks izR;FkhZx.k mDr deZpkjh ds lkFk gh xढ+h gqbZ lh oh is'k djus okyh QeZ dks fooftZr dj ldrs gSa && 5 o"kZ rd dk footZu fd;k tk ldrk gS && nks o"kZ dk footZu && vuuqikfrd ughaA ¼1995½3 ,l lh lh 334 rFkk ¼2013½ ,l lh lh vkWuykbu ,e ih 5471 fufnZ"VA ¼2021½ 1 ,l lh lh 804 izHksfnrA ¼iSjk 27] 28 ,oa 37
¼2½ uSlfxZd U;k; && lquokbZ dk volj && footZu && izR;FkhZx.k us ;kph vkSj mlds deZpkjh dks Li"V 'kCnksa esa dkj.k crkvks lwpuk tkjh dh && mUgksaus mÙkj izLrqr fd, && mu ij fopkjksijkar footZu ds vkns'k tkjh fd, x, && fofu'p;u dh izfØ;k esa dksbZ voS/krk ughaA ¼2014½14 ,l lh lh 731 rFkk ¼2014½9 ,l lh lh 105 fufnZ"VA ¼iSjk 32

ORDER

Shukla, J.-- 1. Regard being had to the facts of the case and the reliefs sought in the present writ petitions, they were heard together and are being disposed of by a common order. For the sake of convenience and clarity the facts enumerated in WP-11371-2021 are taken note of.

2. Shorn or unnecessary details : The respondent No.1 Madhya Pradesh Road Development Corporation [for short, “the MPRDC”] invited tender for Consultancy of Independent Engineer for Operation & Maintenance (O & M) period on Completed Road Projects under BOT (Toll), BOT (Toll + Annuity) & BOT (Annuity) Mode for MPRDC for the State of Madhya Pradesh (hereinafter referred to as “the Project”) on 22.9.2020. Request for Proposal (for brevity “RFP) was issued by the respondents. The petitioner along with its lead partner – M/s K & J Projects Private Limited participated in the tender process and submitted its bid for the tender on 17.10.2020. The technical evaluation was declared on 25.1.2021 wherein the score of the petitioner was recorded to be 94.55 marks which is reflected in the Minutes of the Meeting of the Bid Evaluation Committee held on 21.1.2021. The petitioner further submits that as per sub-clause (ii) of Clause 5.5 of the Data Sheet, the technical proposal of a bidder must secure a minimum of 75 marks to be considered for the financial evaluation. A reference is made to Clause 5.5 (iii) of the Data Sheet. A revaluation was conducted on 9.2.2021, however, there was no change in the scores obtained by the petitioner, which scored the highest marks and thus, qualified for opening of the financial bid. The petitioner has referred to the Minutes of the Meeting of the Bid Evaluation Committee, dated 9.2.2021. It is stated that as a result of the petitioner’s highest score, it was qualified for the financial bid, wherein the petitioner was also the lowest bidder in the whole tender process.

3. It is setforth that pursuant to the petitioner’s qualification for the technical and financial bid on 16.2.2021, a complaint was received by the respondent No.2 on 18.2.2021 against the petitioner regarding the documents submitted by it from Neeraj Nigam. On the basis of the complaint dated 18.2.2021, the respondent No.2 issued a letter dated 31.3.2021 to the petitioner seeking clarification with regard to the difference of period of engagement of Mr. Akhil Khare shown in his Curriculum Vitae [hereinafter referred to as “CV”] submitted by the lead partner in association with the petitioner in the present Project and in another CV submitted in a project of M/s URS Scott Wilson India Private Limited, in association with the petitioner are not matching with each other. The CV of Mr. Akhil Khare was submitted as per Appendix B-5 under section 4 Format for submission of Technical Proposal of the RFP, as also uploaded in the Infracon portal.

4. It is putforth that in the meanwhile, the respondent No.2 had also sought the same clarification from M/s URS Scott Wilson India Private Limited as to the differences in the contents of the CV of Mr. Akhil Khare on 6.3.2021. In consequence of the letter dated 6.3.2021 M/s URS Scott Wilson India Private Limited sought clarification from Mr. Akhil Khare and Mr. Akhil Khare also replied, vide letter dated 12.3.2021.

5. The petitioner vide its reply dated 7.4.2021 to the letter dated 31.3.2021 issued by the respondent No.2 informed that the CV of Mr. Akhil Khare which was submitted in the present Project by the petitioner was taken from the Infracon Portal of the Ministry of Road Transport and Highways, Govt. of India and the CV submitted in the earlier Project of M/s URS Project was submitted as per requirements of that Project. For the present Project, the CV was obtained from Infracon Portal, wherein the Key Personnel submitted the details in an elaborate format containing his employment records. It is relevant to note that section 3 of the RFP issued to M/s URS Scott Wilson India Private Limited project provides the qualific

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top