IN THE HIGH COURT OF MANIPUR AT IMPHAL
Ahanthem Bimol Singh, J.
M/s Vijay Nirman Company Private Ltd. - Petitioner
Versus
Union of India, represented by the Executive Engineer, Manipur Project Division, Central Public Works Department - Respondent
WP(C) No. 894 of 2022
Decided On : 06-09-2024
| Table of Content |
|---|
| 1. details of contract execution and issues faced (Para 2 , 4 , 5 , 6 , 9) |
| 2. provisions of clause 10b and 13 related to mobilization advance (Para 3 , 11 , 12 , 13 , 21) |
| 3. petitioner's claims regarding cash flow and project issues (Para 7 , 8) |
| 4. enforcement of payment demands by respondent and legal grounds (Para 10 , 16 , 17 , 18) |
| 5. court's view on validity of demands and final resolution (Para 25 , 26) |
JUDGMENT :
Ahanthem Bimol Singh, J.
[1] Heard Ms Jyoti Mendiratta, learned counsel assisted by Mr. T. Momo, learned counsel appearing for the petitioner and Mr. Kh. Samarjit, learned DSGI assisted by Mr. N. Nongdamba, learned counsel appearing for respondent.
The present writ petition had been filed challenging the Demand Letter dated 20-04-2021 of the Executive Engineer, Manipur, CPWD, Tulihal Airport, Imphal, to claim and recover from the petitioner the alleged mobilization advance along with the interest amounting to Rs. 17,17,91,085/- coupled with the prayer for quashing the Memorandum dated 18-07-2022 issued by the said E.E. under Clause 29 of the General Conditions of Contract for withholding and recovery of departmental dues from the dues payable to the petitioner.
[2] The brief facts of the present case are that on behalf of the President of India, the respondent issued a Tender Notice dated 09-12-2014 along with information and instruction for bidders inviting e-tenders from interested and eligible tenderers for construction of a multipurpose building for the National Institute of Technology (NIT) at Langol, Imphal. The components of work includes pile foundation, internal water supply, sanitary installations, UG Sump, development and bulk services, internal electrical installations, HVAC Electric Sub-station, lifts, DG sets, fire alarm and fire fighting system.
The bids were invited by the respondent on a lumpsum basis and the petitioner submitted lumpsum bid for all the works specified in the tender documents altogether amounting to Rs. 2,10,22,70,513/- (Rupees two hundred ten crores twenty two lakhs seventy thousand five hundred and thirteen only) which included both civil and electrical works for the multipurpose building at NIT on the understanding that the time frame detailed in the tender and the contract provisions prescribed will be adhered to by the respondent. The bid submitted by the petitioner was accepted by the respondent and the same was communicated to the petitioner by a letter dated 02-03-2015. Pursuant thereto, an agreement was executed between the petitioner and the respondent for carrying out both civil and electrical works and the stipulated time for completion of the contract work was 730 days commencing from 24-03-2015.
[3] Clause 10B(ii) of the General Conditions of Contract (GCC) provides for availing mobilization advance by the Contractor not exceeding 10 percent of the tender value in the manner prescribed therein. For ready reference, the provision of Clause 10B(ii) of the GCC is reproduced hereinbelow:-
“10B(ii) Mobilization advance not exceeding 10% of the tendered value may be given, if requested by the contractor in writing within one month of the order to commence the work. Such advance shall be in two or more installments to be determined by the Engineer-in-Charge at his sole discretion. The first installment of such advance shall be released by the Engineer-In-charge to the contractor on a request made by the contractor to the Engineer-in-Charge in this behalf. The second and subsequent installments shall be released by the Engineer-in-Charge only after the contractor furnishes a proof of the satisfactory utilization of the earlier installment to the entire satisfaction of the Engineer-in-Charge.
Before any installment of advance is released, the contractor shall execute a Bank Guarantee Bond from Scheduled Bank for the amount equal to 110% of the amount of advance and valid for the contract period. This (Bank Guarantee from Scheduled Bank for the amount equal to 110% of the
A respondent cannot recover mobilization advance where work was suspended and disputes remain unresolved, violating contract terms.
The defect liability period, joint venture agreements, and dispute resolution clauses in contracts were central to the court's decision.
Writ jurisdiction cannot be used solely for granting interim relief. Disputed factual matters are not within the purview of writ jurisdiction.
The court upheld the binding nature of the contract, ruling that the Plaintiff's claims were untenable due to failure to exercise contractual options and were barred by limitation.
The main legal point established in the judgment is the entitlement to extra work payment and interest on delayed payments under the terms of the contract and the Interest Act, 1978.
The approval of a resolution plan under the IBC Code, 2016 extinguishes any debt not part of the plan and binds the stakeholders to the plan.
Strict compliance with contractual terms is required for bank guarantees to be enforceable, safeguarding against unauthorized liabilities.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.