CALCUTTA HIGH COURT
Kalyan Jyoti Sengupta and Asim Kumar Mondal, JJ.
Damodar Valley Corporation —Appellant
versus
Bhaskar Sharchi Alloys Ltd
and Ors. —Respondents
AST Nos. 191 of 2012 with AST No. 192, 120, 123 and 125 of 2012
Decided on 16.8.2012
Result: Appeals dismissed.
K.J. Sengupta, J.—The instant appeal has been preferred against the judgment and order dated 4th July 2012 passed by the learned Single Judge refusing to vacate interim order passed earlier. The fact which has triggered to filing of the writ petition being No. 11813 (W) of 2011 alongwith other matters is shortly put hereunder:
2. The Central Electric Regulatory Commission (hereinafter as Commission) one of the respondents in the appeal as well as in the writ petition in exercise of the power granted under terms and conditions of Tariff Regulations inserted new Clause (4) in the Regulation 5 of C.E.R.C. by which the Commission has empowered itself to grant provisional tariff up to 95% of the annual fixed cost of the project claimed in the petition subject to adjustment after the final tariff has been issued and the said amended provision was sought to be applied for revising the tariff for the period 2009-2014 and thereafter decided provisionally by an order dated 23rd June, 2011 allowing 70% annual fixed cost of the project as has been allowed to N.T.P.C. The tariff application of appellant made before the C.E.R.C. for determination of 2009-14 has been published and no objection has been received from any corner. As per the aforesaid order dated 23rd June, 2011 of the Commission the appellant started raising bills for electricity charges at enhanced rate. Soon thereafter the respondent-writ petitioner alongwith other persons affected filed writ petitions challenging validity and legality of the said Regulation 5 (4) and also the above order passed thereunder taking various grounds. It appears from the record that identical challenge was made against the decision of the Commission of amendment of the Regulation and also order passed thereunder, and further demand of payment by the appellant at an increased rate in the Jharkhand High Court. In the writ petitions filed in the Jharkhand High Court interim order was passed in effect restraining the appellant herein from demanding any amount on the basis of the increased tariff. During pendency of the writ petition in the Jharkhand High Court above batch of writ petitions were filed in this Court also. It appears from the record that after hearing all the parties the learned Single Judge passed an interim order on 11th August, 2011 restraining, the appellant from disconnecting the electricity supply line of the writ petitioners in connection with the aforesaid demand made in terms of the order passed by the Commission. From the record it appears that from time to time this interim order was directed to continue and till date as stated hereinafter it was allowed to be continued by both the parties.
Thereafter on 21st March, 2012 Jharkhand High Court dismissed all the writ petitions and interim order passed thereunder was vacated. The writ petitioners in the Jharkhand High Court thereafter filed an S.L.P. against the aforesaid order of dismissal before the Supreme Court. The Hon’ble Supreme Court entertained the hearing of the S.L.P., but declined to pass any interim order. Soon thereafter on 17th day of April, 2012 an application was filed before the learned Single Judge for vacating of the interim order taking the ground that identical point has been decided by Jharkhand High Court against all the consumers and in favour of D.V.C. and upheld action and decision of the Commission. Therefore there was no justification of continuation of the interim order passed earlier. It is also alleged in the application that the basis of passing interim order by the learned Single Judge and as extended from time to time was interim relief granted by Jharkhand High Court. When this interim order disappeared with the dismissal of the writ petitions followed by refusal to grant interim relief by the Hon’ble Supreme Court there is no plausible reason to stay the hands of the D.V.C. with subsisting interim order. After dismissal as above, in Jharkhand area most of the consumers are now compell
The main legal point established in the judgment is the binding effect of the settlement between the parties, the waiver of the right to seek re-employment by the workmen, and the entitlement of the ....
A lockout is justified if it is declared in response to an illegal strike or a strike that is in breach of a settlement or award.
The combination of eyewitness testimonies, recovery of the weapon used, and forensic examination results can establish guilt in criminal cases, even based on circumstantial evidence.
The conviction of an accused person under Section 27(3) of the Arms Act is not permissible in law if the accused is also charged with committing murder under Section 302 of the Indian Penal Code.
The court can enhance compensation based on the deceased's income and family dependency, and adjust the multiplier used by the Tribunal if found unjustified.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.