DELHI HIGH COURT
V.K. Jain, J.
M/s. Linde Heavy Truck Division Ltd. —Plaintiff
versus
Container Corporation of India Ltd.
and Anr. —Defendants
CS(OS) 23/2012
Decided on 16.10.2012

Important Points

IMPORTANT POINT
If the agreement between the parties requires or contemplates a further or fresh consent for reference to arbitration, it would not constitute an arbitration agreement.

Subject

Arbitration Law - Arbitration Agreement

Act Referred

ARBITRATION AND CONCILIATION ACT : S.8

Headnote

Arbitration and Conciliation Act, 1996—Section 8—Suit for money recovery alleging material breach of terms of contract by defendant—Stay of suit prayed by defendant referring to arbitration in terms of contract—Though clause in the contract gave an option to one of the parties to seek reference of disputes to arbitration it did not mandate and compulsory arbitration for adjudication of such dispute—If agreement between parties required or contemplated a further or fresh consent for reference to arbitration, it would not constitute an arbitration agreement—Application was liable to be dismissed.

       Held: From careful scrutiny of clauses 15.3 to 15.6 of the agreement between the parties, it would be seen that the expression “may” has been used only in clause 15.5. In clause 15.3, relating to jurisdiction of the Courts, the expression used is “shall” which indicates mandatory nature of the term agreed between the parties with respect to territorial jurisdiction of the Court. Similarly, in clause 15.4 dealing with negotiations, the expression used is “shall”, clearly implying that it would be mandatory for the parties to make efforts to resolve their disputes by way of negotiations. On the other hand, though clause 15.5 gives an option to one of the parties to seek reference of the disputes to arbitration as per the rules of Standing Committee on Public Enterprises, it does not mandate a compulsory arbitration for adjudication of such disputes. In case arbitration is sought by one party to the dispute, the other parties had an option, whether to agree for resolution by arbitration or not and the party seeking arbitration could not compel the other party to go through the process of arbitration. Normally, the arbitration clause stipulates that the disputes between the parties shall be referred to arbitration and the expression “may” is not used in such clauses, though it can hardly be disputed that mere use of the expression “may” would not be determinative in every case and in a given case, the terms and conditions and/or the conduct of the parties may lead to an inference that despite using the expression “may” the parties had, in fact, agreed for a compulsory arbitration to resolve their disputes. The arbitration clause in the case before this Court is more or less similar to the arbitration clause in Wellington Associates Ltd. (supra). This clause, in my view, does not indicate a firm determination of the parties and binding obligation on their part to resolve their disputes through arbitration. It merely gives an option to either of them to seek arbitration and on such an option being exercised, it would be for the other party whether to accept it or not. As held by Supreme Court in Jagdish Chander (supra), if the agreement between the parties requires or contemplates a further or fresh consent for reference to arbitration, it would not constitute an arbitration agreement. The view taken by the Apex Court was that if the agreement between the parties provides that in the event of any dispute, they may refer the same to arbitration that would not constitute a binding arbitration agreement. In the case before this Court, clause 15.5 of the agreement envisages a fresh consent for arbitration, in case the option for arbitration is sought to be exercises by one of the parties to the disputes. Therefore, it does not constitute a binding arbitration agreement. (Para 7)

        Result: Application dismissed.

       

Counsel for the Parties:
For the Plaintiff:Mr. Abhimanyu Bhandari, Ms. Aakansha Munjal and Mr. Nikhil Singhvi, Advocates.
For the Defendants: Through Counsel.

JUDGMENT

V.K. Jain, J.—This is a suit for recovery of Rs 11,71,46,949/-. The case of the plaintiff is that it entered into an agreement dated 04.07.2007 with defendant No. 1 for manufacture, supply and commissioning of 15 Reach Stackers, alongwith operation and maintenance of those stackers, at the specified terminals of defendant No. 1, for a period of 5 years. The plaintiff alleges material breach of the terms of the contract by defendant No. 1 and claims that an amount of Rs 4,92,73,207/- is due and payable to it towards the supply, operation and maintenance of machines. The contract was terminated by defendant No. 1 vide letter dated 24.05.2011. The bank guarantees furnished to it by the plaintiff were then invoked by defendant No. 1. The plaintiff is claiming

Rs. 56,68,000/- alleging that the invocation of the bank guarantees was illegal. Some other amounts have also been claimed in the present suit, thereby raising the total claim to

Rs. 11,71,46,494/-

2. IA No. 2153/2012 has been filed by defendant No. 1 seeking stay of the suit and reference to arbitration in terms of clause 15 of Section (iii) of the contract between the parties. The application has been opposed by the plaintiff primarily on the ground that there is no arbitration agreement between the parties.

3. Clauses 15.3 to 15.6 of the contract are relevant and read as under:-

“15.3 Jurisdiction of Courts: the Courts of the place from where the acceptance of tender has been issued shall alone have jurisdiction to decide any dispute arising out of or in respect of the contract i.e. New Delhi (INDIA).

15.4 In case of any dispute or difference whatsoever arising between the parties out of the relating to the construction, interpretation, application, meaning, scope operation or effect of this contract or the validity or the breach thereof, CONCOR and supplier shall make very effort to resolve amicable by direct informal negotiation any disagreement or dispute arising between them under or in connection with the contract.

15.5 If, after 30(thirty) day from the commencement of such informal negotiation, CONCOR and the supplier have been unable to resolve amicably the contract dispute, either party may require that the dispute be referred for resolution by arbitration in accordance with the rules of Arbitration of the “Standing Committee on Public Enterprises” of India (SCOPE) from the “Conciliation and Arbitration” and award made in pursuance thereof shall be binding on the parties.

15.6 During settlement of disputes in arbitration proceedings, both parties shall be obliged to carry out their respective obligation under the contract.”

4. In Wellington Associates Ltd. v. Kirit Mehta, (2004) 4 SCC 272 clause 4 and 5 of the agreements between the parties read as under:-

“4. It is hereby agreed that, if any dispute arises in connection with these presents, only courts in Bombay would have jurisdiction to try and determine the suit and the parties hereto submit themselves to the exclusive jurisdiction of the courts in Bombay.”

5. It is also agreed by and between the parties that any dispute or differences arising in connection with these presents may be referred to arbitration in pursuance of the Arbitration Act, 1947, by each party appointing one arbitrator and the arbitrators so appointed selecting an umpire. The venue of arbitration shall be at Bombay.

Holding that clause 5, extracted above, does not constitute a firm or mandatory arbitration clause, Supreme Court, inter alia, held as under:-

“21. Does clause 5 amount to an arbitration clause as defined in Section 2(b) read with section 7? I may here state that in most arbitration clauses, the words normally used are that “disputes shall be referred to arbitration”. But in the case before me, the words used are “may be referred”.

22. It is contended for the petitioner that the word “may” in clause 5 has to be construed as “shall”. According to the petitioner’s counsel, that is the true intention