SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

KERALA HIGH COURT
B. Kemal Pasha, J.
P.C. Alexander —Appellant
versus
K.E. Joseph @ Benny —Respondent
RSA Nos.585 and 588 of 2017
Decided on 4.10.2017

Counsel for the Parties:
For the Appellant:Sri. Cherian Gee Varghese, Sri. P. Haridas and Sri. P.C. Shijin, Advocates
For the Respondent:Sri. Mathew John (K) and Sri. Domson J. Vattakuzhy, Advocates

IMPORTANT POINT
Whatever be time period of permissive user, it would not ripen into a right of acquisition by prescription.

Headnote:Indian Easements Act, 1882—Section 15—Easement by Prescription—Right of way should be peaceably and openly enjoyed by claimant as an easement and as of right, without interruption for 20 years—Whatever be time period of permissive user, it would not ripen into a right of acquisition by prescription—Courts below have appreciated evidence in its correct perspective and have arrived at correct conclusion—Appeals dismissed. (Paras 13 and 16)

       Result: Appeals dismissed.

       

JUDGMENT

B. Kemal Pasha, J.—O.S.Nos.4/2009 and 9/2009 of the Munsiff’s Court, Thiruvalla were jointly tried. O.S.No.4/2009 was dismissed with costs whereas; O.S.No.9/2009 was decreed with costs. The plaintiff in O.S.No.4/2009, who is the defendant in O.S.No.9/2009, preferred A.S.Nos.5 of 2015 and 6 of 2015 before the Subordinate Judge’s Court, Thiruvalla challenging the judgments and decrees of the Munsiff’s Court. Both these appeals were dismissed with costs by the lower appellate court, and hence these second appeals.

2. Both the suits are for perpetual injunction. O.S.No.4/2009 was filed by the appellant herein for a decree of perpetual injunction restraining the respondent herein from obstructing his user of plaint schedule item No.3 pathway. The appellant claims that the predecessor-interest of the plaint schedule item No.1 property, and thereafter the appellant had been making use of plaint schedule item No.3 pathway, continuously and openly as of right, for ingress and egress to the plaint schedule item No.1 property for more than 70 years, prior to the filing of the suit. Precisely, what has been pleaded is the right of easement by prescription over plaint schedule item No.3 pathway. For having access to the plaint schedule item No.3 pathway three stone pillars are laid over the narrow watercourse passing through the western side of the plaint schedule item No.1 and the said stone pillars are being used as a small culvert. The said pathway continues through the northern extremity of plaint schedule item No.2 property belongs to the respondent, and joins the road at the western side of plaint schedule item No.2.

3. The respondent contended that there is such a pathway in existence, whereas its width is only two feet. The total width of the three stone pillars laid over the watercourse is only 22 inches. According to the respondent, the appellant had constructed his residential building in plaint schedule item No.1 property just 15 years back to the date of the filing of the suit. As a shortcut for taking building materials into the plaint schedule item No.1 property, the appellant sought permission from the father of the respondent to pass through the northern extremity of plaint schedule item No.2. Consequently, the father of the respondent permitted the appellant to cause the taking of building materials through the northern extremity of the said property, for which the appellant laid the said three stone pillars over the watercourse separating these two properties. According to the respondent, the user of the appellant over the said pathway for some time was merely permissive and it has never ripened into a right of easement by prescription.

4. The respondent herein filed O.S.No.9/2009 against the appellant herein as a suit for perpetual injunction for restraining the appellant and his men from trespassing into any portions of his property, from cutting open a pathway through his property, from changing the lie and nature of the said property, from committing waste on the property etc. A written statement was filed by the appellant taking up the very same contentions as in the plaint in O.S.No.4/2009. As aforesaid, O.S.No.4/2009 stands dismissed and O.S.No.9/2009 stands decreed in terms of the plaint.

5. These Second Appeals are admitted on the following substantial questions of law:

“(1) Is the lower appellate court justified in dismissing the appeal, after dismissing the application filed by the appellant under Order 41 Rule 27 of the Code of Civil Procedure seeking admission of certain documents, which go to show that the appellant was residing there even 25 years back?

(2) Is the lower appellate court justified in not remitting the case to the trial court for enabling the appellant to produce those documents and to get it marked, when those documents show easement by prescription?

(3) Are the courts below justified in denying reliefs to the appellant, when an inchoate right has been established?”

6. Heard t













Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top