IN THE HIGH COURT FOR THE STATE OF TELANGANA AT HYDERABAD
P.NAVEEN RAO, J.
M/s. Indu Projects Limited, rep.by its Chief Operating Officer, Mr. B.V. Bhaskar Reddy. - Appellant
Versus
Telangana Micro & Small Enterprises Facilitation Council, rep.by its Chairman, Commissionerate of Industries, Chirag Ali Lane, Hyderabad and another. – Respondents
W.P. No. No.24112 of 2016
Decided on : 12-11-2019
Provisions of the Arbitration and Conciliation Act, 1996 - Infrastructure conglomerate working - Field of building construction - Petitioner claims to be the infrastructure conglomerate working in the field of building construction, pipeline works, power plants, mining, etc. GMR awarded the contract for civil and structural works for establishing 15MW Solar Power Plant in Charanaka village of Patan District in the State of Gujarat - Value of the contract - Consequently, petitioner issued letter of intent in favour of 2nd respondent for supply, fabrication and erection of cold rolled structures including transportation and installation of modules along with necessary civil and structural works for foundation and support structures for MW Solar Power Plant -
Finding of the Court:
it was contended that dispute has arisen in respect of transactions entered, when GCIL was not registered under the Act and therefore does not answer the description of ‘Supplier’ and therefore Council has no jurisdiction and reference was made without affording sufficient opportunity - Both contentions were rejected - In the peculiar facts of the case, none of the decisions cited by learned counsel come to the aid of 2nd respondent - As the council erred in not conducting conciliation proceedings before proceeding to hold arbitration proceedings defeating the very objective of the scheme of the Act as codified in Section 18 of the Act, 2006 and is bereft of reasons in support of the decision, it is ex facie illegal and liable to be set aside -
Result: Writ Petition is allowed.
ORDER :
Heard Sri Vedula Srinivas learned counsel for petitioner, learned Government Pleader for Industries and Commerce for respondent no.1, and Sri P.Vishnuvardhana Reddy learned counsel for 2nd respondent.
2. Facts on record as averred in the affidavit filed in support of the writ petition and in the counter affidavit filed by the 2nd respondent disclose respective stands as under:
3. Petitioner claims to be the infrastructure conglomerate working in the field of building construction, pipeline works, power plants, mining, etc. GMR awarded the contract for civil and structural works for establishing 15MW Solar Power Plant in Charanaka village of Patan District in the State of Gujarat. The value of the contract was Rs.9,59,05,479/-. Consequently, petitioner issued letter of intent dated 04.06.2011 in favour of 2nd respondent for supply, fabrication and erection of cold rolled structures including transportation and installation of modules along with necessary civil and structural works for foundation and support structures for 15 MW Solar Power Plant. The letter of intent binds both parties. Clause-15 provides for dispute resolution mechanism. It requires the parties to refer a dispute to a panel of three arbitrators and should be decided under the provisions of the Arbitration and Conciliation Act, 1996 (Act, 1996). Petitioner alleges that 2nd respondent was negligent in performing his responsibilities under the letter of intent dated 04.06.2011 resulting in his failure to comply with the obligations with his Principal and the Principal was threatened to cancel the work order. Petitioner alleges that due to the negligent attitude, delay in execution of work and poor quality of work of the 2nd respondent, petitioner suffered huge damages and incurred huge loss, which may be around Rs.14.00 crores.
4. On the contrary, 2nd respondent claims that he executed the work in accordance with the contract entered with the petitioner. In terms of the contract, 2nd respondent is entitled to receive an amount of Rs.17,10,22,992/-, whereas petitioner paid only Rs.13,84,91,146/-. Remaining outstanding is Rs.3,35,31,846/- and despite the repeated requests and follow up action, petitioner failed to release the amount within a reasonable time. In the peculiar circumstances, 2nd respondent availed the remedy provided by the Micro, Small and Medium Enterprises Development Act, 2006 (for brevity, ‘Act, 2006’), submitting the claim petition before The Micro and Small Enterprises Council (for brevity hereinafter referred to as the Council) claiming that 2nd respondent is entitled to payment of balance amount and interest computing total due as Rs.7,78,93,992/-.
5. The first respondent Council by order dated 20.02.2016 directed the petitioner to pay the balance amount due as claimed by the 2nd respondent and Rs.6,64,68,829/- as interest, and total amount quantified as Rs.10,16,40,931/-. It also ordered interest with monthly rests at three times bank rate prevailing as on the date of award as notified by the RBI on the amount adjudicated by the Council. Aggrieved thereby and challenging the said decision, this writ petition is filed.
6. Sri Vedula Srinivas made the following submissions:
(ii) He would submit that the contract was entered on 04.06.2011, whereas 2nd respondent registered itself as Small Scale Industry (SSI) with the District Industrial Centre at Balanagar, Hyderabad on 23.04.2012 and, therefore, the 2nd respondent cannot avai
Deepak Babaria and another vs. State of Gujarat and others
Purbanchal Cables and conductors Private Limited v. Assam State Electricity Board and another
State of Orissa and others v Chandra Nandi
Venshiv Pharma Chem (P) Ltd., Hyderabad and another v. State Bank of India and others
Whirlpool Corpn. v. Registrar of Trade Marks [(1998) 8 SCC 1]
The main legal point established in the judgment is the binding effect of the settlement between the parties, the waiver of the right to seek re-employment by the workmen, and the entitlement of the ....
A lockout is justified if it is declared in response to an illegal strike or a strike that is in breach of a settlement or award.
The combination of eyewitness testimonies, recovery of the weapon used, and forensic examination results can establish guilt in criminal cases, even based on circumstantial evidence.
The conviction of an accused person under Section 27(3) of the Arms Act is not permissible in law if the accused is also charged with committing murder under Section 302 of the Indian Penal Code.
The court can enhance compensation based on the deceased's income and family dependency, and adjust the multiplier used by the Tribunal if found unjustified.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.