IN THE HIGH COURT FOR THE STATE OF TELANGANA AT HYDERABAD
M.S. RAMACHANDRA RAO, K. LAKSHMAN, JJ.
BVG India Limited – Appellant
Versus
Vijai Electricals Limited and Another – Respondents
C.O.M.C.A. No. 62 of 2019
Decided On : 08-01-2020
Arbitration and Conciliation Act, 1996 - Section 37, 9 - Arbitration Agreement - Appointment of Arbitrator - Whether the Court can injunct the 1st respondent from invoking the Bank Guarantee?Whether the court can direct the 1st respondent to deposit an amount of Rs. 13,55,84,531/- (Rupees Thirteen Crores fifty five lakhs eighty four thousand five hundred and thirty one only) or to furnish the security equal to the said amount?”
-
Facts of the Case:
Application filed under Section 9 of the Arbitration and Conciliation Act, 1996 filed by the appellant - State Electricity Distribution Company Limited (MSEDCL) entered into a contract with the 1st respondent for execution of the design, test, supply, transport, construction, erection, testing and commissioning of sub-transmission lines, distribution lines, new sub-stations, augmentation of existing sub-stations, distribution of transformers of varying capacities and other allied works for the works under the Infrastructure Plan Phase-I ( project on ‘Turnkey’ basis under bid package - sub-contract also contemplated that the 1st respondent shall open a Special Escrow Account with two signing authorities representing each party- one from the appellant and one from the 1st respondent; and that the amount realized from MSEDCL (employer) after all due deductions against each invoice was required to be deposited in the same account with Standing Instructions to the Bank to transfer automatically 4% of the received amount to the 1st respondent’s account and 96% of the received amount to the appellant’s account against an invoice to the 1st respondent by the appellant. It was further stated that any balance due to either by the 1st respondent or the appellant will paid within 7 working days from the date of receipt of the amount from MSEDCL, after joint reconciliation by both the appellant and the 1st respondent
Finding:
petitioner has been able to make out a strong case against the respondent, particularly, when the respondent has received the amount from the employer and it is avoiding to clear the due amount and is raising the flimsy reasons, and when it appears to the Court to be just and convenient, the Court has ample power to exercise its discretion to secure the amount even when the condition of the company is solvent, under Sections 9(1)(ii)(b) and (e) of the Arbitration and Conciliation Act, 1996- Having admitted prima-facie in the annexure to the e-mail that after reconciliation of accounts, a sum was payable by the 1st respondent to the appellant, the 1st respondent disputed the said quantum in the counter in the O.P. and admitted that only is payable to the appellant - Conduct of the 1st respondent does not appear to be bonafide, more so, when it failed to open the Special Escrow Account having agreed to do so in the subcontract agreement entered into by it with the appellant -
Result: Appeal is allowed
JUDGMENT :
M.S. RAMACHANDRA RAO, J.
1. This appeal is preferred under Section 13 of the Commercial Courts, Commercial Division and Commercial Appellate Division of High Courts Act, 1915 r/w. Section 37 of the Arbitration and Conciliation Act, 1996, by the appellant challenging the order dated 26.08.2019 in COP No. 68 of 2018 passed by the Judge, Commercial Court-cum-XXIV Additional Chief Judge, City Civil Court, Hyderabad, in an application filed under Section 9 of the Arbitration and Conciliation Act, 1996 filed by the appellant.
2. On 03.10.2008, the Maharastra State Electricity Distribution Company Limited (MSEDCL) entered into a contract with the 1st respondent for execution of the design, test, supply, transport, construction, erection, testing and commissioning of sub-transmission lines, distribution lines, new sub-stations, augmentation of existing sub-stations, distribution of transformers of varying capacities and other allied works for the works under the Infrastructure Plan Phase-I ( project on ‘Turnkey’ basis under bid package No. CE (Dist)/Infra Plan-I/Mumbai/07-08 for tender No. T-16 for works in Baramati, Kedgaon, and Manchar Divisions under Pune Rural Circle of Pune Zone pursuant to a letter of Award in favour of the 1st respondent granted on 05.09.2008.
3. The total value of the works was Rs. 273.53 Crores and the work was to be executed in 48 months. Later the value of the work was enhanced to Rs. 300.33 Crores.
4. The 1st respondent then sub-contracted some of these works to the appellant under a sub-contract agreement dated 04.11.2011 and the value of the works under the said agreement was Rs. 91.82 Crores. The scope of the work entrusted to the appellant by the 1st respondent as mentioned in the said sub-contract agreement is as under:
“Scope of Work: Subject to approval for sub-contract as also approval to the extension of period for completion by at least about 12 months by the Employer, the Contractor hereby awards the sub-contract to the Sub-Contractor to design, test supply, transport, construct, erect, test and commission sub-transmissions lines, distribution lines, new sub-stations, augmentation of existing sub-stations, distribution transformers of varying capacities and other allied works including provided a two year guarantee (defect liability) period and five years guarantee from the date of commissioning for specified products viz. transformers, Breakers, Conductors etc., for the part of the works as detailed in Annexure-I to this agreement under the Infrastructure Plan Phase-I project on “Turnkey” basis under bid package number CE (Dist)/Infra-plan Phase-I/Mumbai/07-08 for tender No. 16 for Works in Bharamati, Kedgoan and Manchar Divisions under Pune Rural Circle Pune.”
5. Under the terms of the said agreement, the appellant was under an obligation to furnish a Performance Bank Guarantee towards 5% of the Value of the sub-contract awarded to it for a period as stipulated by MSEDCL and the said Bank Guarantee was to be issued by a Scheduled Bank having a branch at Hyderabad (clause f). It was to be irrevocable and unconditional and a right was reserved to the 1st respondent to invoke the said Bank Guarantee for any default of the contractual obligations by the appellant under the agreement by giving a minimum of 15 days prior notice.
6. The sub-contract also contemplated that the 1st respondent shall open a Special Escrow Account with two signing authorities representing each party- one from the appellant and one from the 1st respondent; and that the amount realized from MSEDCL (employer) after all due deductions against each invoice was required to be deposited in the same account with Standing Instructions to the Bank to transfer automatically 4% of the received amount to the 1st respondent’s account and 96% of the received amount to the appellant’s account against an invoice to the 1st respondent by the appellant. It was further stated that any balance due to either by the 1st respondent or the app
SupremeToday
The main legal point established in the judgment is the binding effect of the settlement between the parties, the waiver of the right to seek re-employment by the workmen, and the entitlement of the ....
A lockout is justified if it is declared in response to an illegal strike or a strike that is in breach of a settlement or award.
The combination of eyewitness testimonies, recovery of the weapon used, and forensic examination results can establish guilt in criminal cases, even based on circumstantial evidence.
The conviction of an accused person under Section 27(3) of the Arms Act is not permissible in law if the accused is also charged with committing murder under Section 302 of the Indian Penal Code.
The court can enhance compensation based on the deceased's income and family dependency, and adjust the multiplier used by the Tribunal if found unjustified.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.