IN THE HIGH COURT FOR THE STATE OF TELANGANA AT HYDERABAD
G. Radha Rani, J.
Bolusani Gowri Shankar S/o. Satyanarayana, and Others - Petitioners
Versus
The State of Telangana, Rep. by Principal Secretary Industries and Commerce Department, Secretariat, Hyderabad, Telangana and Others - Respondents
Writ Petition No.10774 Of 2022
Decided On : 16-06-2022
Mandamus - Sand De-casting - Telangana State Mining Rules, 2015 - Rule-7 - Eco Sensitive Zone - Environmental Clearance - National Board for Wild Life - Supreme Court Orders - Ministry of Environment and Forests Guidelines
Fact of the Case:
The petitioners sought a writ of Mandamus to declare the action of the 5th respondent in stopping the de-casting of sand from their patta lands as arbitrary, illegal, and violative of Article 21 of the Constitution. The petitioners' lands were casted with sand due to flash floods, and they sought permission for de-casting as per the Telangana State Mining Rules, 2015. The District Level Sand Committee (DLSC) granted permission subject to certain conditions, but the Forest Department issued notices to stop the de-casting, citing the area as falling within the Eco Sensitive Zone (ESZ) of Eturunagaram Wild Life Sanctuary.
Finding of the Court:
The court found that the petitioners' lands were abutting the river bed and not within the river course, and hence, did not require Environmental Clearance. The court also noted that the Ministry of Environment, Forest and Climate Change guidelines permitted ongoing agricultural practices by local communities within the ESZ. The court held that the notices issued by the Forest Department were without power or authority and violative of Article 21 of the Constitution. The court set aside the notices and directed the respondents not to interfere with the de-casting of sand from the petitioners' lands.
Issues: The main issue was whether de-casting of sand from the petitioners' patta lands required prior clearance from the Standing Committee of the National Board for Wild Life on the ground that the lands were within the Eco Sensitive Zone.
Ratio Decidendi: The court relied on the Telangana State Mining Rules, 2015, Ministry of Environment, Forest and Climate Change guidelines, and Supreme Court orders to determine that the petitioners' de-casting activity did not require prior clearance from the Standing Committee of the National Board for Wild Life. The court also considered the specific location of the petitioners' lands and the purpose of creating Eco Sensitive Zones.
Final Decision: The court allowed the writ petition, set aside the notices issued by the Forest Department, and directed the respondents not to interfere with the de-casting of sand from the petitioners' lands as permitted by the DLSC. No costs were awarded.
ORDER :
1. This petition is filed to issue a writ of Mandamus declaring the action of the 5th respondent in issuing notices dated 18.12.2021 and 01.01.2022 directing to stop de-casting of sand from the patta lands of the petitioners, as arbitrary, illegal and violative of Article 21 of the Constitution and to set aside the same with a consequential direction to the 5th respondent not to interfere.
2. Heard the learned counsel for the petitioners, the learned Government Pleader for Mines and Geology representing the respondent Nos.1 to 4 and the learned Government Pleader for Forests representing respondents No.5 to 7.
3. The learned counsel for the petitioners submitted that the petitioners were the owners and possessors of marginal extent of patta lands in Eturunagaram village. The said lands were near Jampanna Vagu river coast. Due to flash floods in the rainy season, the said lands were casted with sand and the thickness of the sand deposited was about three meters in the area. Since the Telangana State Mining Rules, particularly, Rule-7 provided for de-casting of mines from patta lands, the petitioners made independent applications dated 08.06.2020 before the Assistant Director of Mines and Geology Department, who was the Member Convenor of the District Level Sand Committee (DLSC). A joint inspection was conducted on 12.06.2020 and proposals were discussed in the DLSC meeting held on 04.12.2020. Since all the officers, forming part of the Joint Committee, were of the considered opinion that sand had to be de-casted to make the lands fit for agricultural operations, the DLSC had issued proceedings dated 29.06.2021 according permission for de-casting of sand of 2,09,130 cubic meters from the patta lands of the petitioners through M/s. Telangana State Mineral Development Corporation Limited (TSMDC) subject to certain conditions. The petitioners entered into agreements with M/s.TSMDC as per the amended Rule-7 of the Telangana State Sand Mining Rules, 2015 (for short, ‘Rules, 2015’). Pursuant to the agreements entered, the de-casting operations commenced immediately. Subsequently, the Forest Range Officer, Eturunagaram (South) WLM issued letter dated 18.12.2021 stating that the subject area was falling under Eco Sensitive Zone (ESZ) of Eturunagaram Wild Life Sanctuary and directed to stop the de-casting operations in the patta lands. Immediately, the TSMDC addressed a letter dated 17.01.2022 to the District Collector, Mulugu informing that the Forest Officials were interfering with the de-casting operations on the alleged ground that the subject lands were falling in ESZ and it was also informed in the said letter that de-casting of sand from patta land was purely a time bound action to make the agricultural lands fit for agriculture. According to TSMDC, the area was not notified as ESZ. No draft map was available in the public domain. The de-casting operations could not be stopped as these areas were not even notified under the Wild Life Laws. The Assistant Director of Mines and Geology also addressed a letter to the District Forest Officer, Mulugu on 24.12.2021 stating that none of the area under question had been notified so far and there was no proposal even sent by the District Forest Officer from District Level seeking to notify the subject areas falling under ESZ. The particular village of Eturunagaram was not part of the villages and not part of the Geo-coordinates included in the said proposal to include certain habitations to be part of ESZ area. The Eco Sensitive Committee proposed inclusion of 33 villages in which Eturunagaram village was not found and requested the District Forest Officer not to stop the sand mining in the mentioned area and that the Forest Department had no locus standi in declaring the Eco Sensitive Zone even without sending the draft, and hindering the operations would attract penal provisions under Section 188 IPC. Despite the above two letters addressed by the District Collector and the Assist
Hon’ble Apex Court made it clear that no direction either interim or final was given by it prohibiting even mining activities within 10 kms. of the boundaries of National Parks or Wildlife Sanctuarie....
Environmental clearance upheld despite initial clerical errors in forest certificate where site verified 1.8km from sanctuary outside notified ESZ; no wildlife clearance needed; mining prohibited wit....
Environmental Clearance upheld for sand mining outside notified ESZ (2 km) and 1.8 km from wildlife sanctuary boundary; corrected typographical errors in forest certificates do not invalidate process....
In times of disasters, the Disaster Management Act, 2005 will and should override the provisions of other laws, because the Act, 2005 is intended to protect the very life of the citizens, without whi....
The insistence in Ext.P8 office memorandum for prior clearance from the Standing Committee for projects within 10 kilometres from National Parks was unsustainable in law as it did not follow the proc....
Valid District Survey Report approved by SEIAA mandatory before sand mining auctions/leases; State amendments without statutory appraisal illegal; mining without it violates environmental laws.
Valid SEIAA-approved DSR mandatory precondition for sand mining auctions, EC grants; State cannot amend without statutory appraisal/approval; invalid DSR voids leases/EC; operations illegal, compensa....
Protection of Ecology – Necessity to have ESZs is to provide a buffer zone around Protected Areas – Rights of villagers residing in Protected Areas are required to be settled in accordance with provi....
Dredging permitting commercial removal of river bed minerals in eco-sensitive zones constitutes illegal mining requiring environmental clearance, not exempt under disaster management; attracts pollut....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.