SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Telangana) 761

IN THE HIGH COURT FOR THE STATE OF TELANGANA AT HYDERABAD
K. LAKSHMAN, J.
Urbanwoods Realitty LLP - Applicant
Vs.
Mrs. Uma Rastogi (died) and another - Respondents
Arbitration Application No.41 Of 2023
Decided On : 09-06-2025

Advocates:
Advocate Appeared:
For the Applicant : Mr. Sunil B.Ganu,Ld.Sr.Counsel Rep. Mrs.Manjari S.Ganu, Ld.Counsel
For RespondentNo.2: Mr. Avinash Desai, Ld.Sr.Counsel Rep. Mr.Vadeendra Joshi, Ld.Counsel

An arbitration clause survives the termination of the substantive contract, allowing disputes to be resolved by the arbitrator regardless of the contract's lapse due to time constraints.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Sections 11 (5) & (6) - Appointment of sole arbitrator sought based on disputes arising from a Memorandum of Understanding (MoU) and agreement of sale - Respondents claimed termination of the contracts due to efflux of time, but court held that arbitration clauses remained enforceable. (Paras 10, 14, 16)

(B) Arbitration Agreements - The court reaffirmed the principle of separability, stating that an arbitration clause survives irrespective of the substantive contract's termination, allowing disputes to be resolved by arbitration rather than by the courts. (Paras 14, 48)

Facts of the case:
The Applicant entered into an MoU with the Respondents for joint development of land, with stipulated terms regarding payments and obligations for both parties. Disputes arose regarding the alleged termination of these agreements and the continuation of arbitration clauses within them.

Findings of Court:
The court found that a valid arbitration agreement exists between the parties and that it cannot be terminated merely because the substantive agreements may have lapsed due to efflux of time.

Issues: Whether the arbitration clause in the agreement of sale was effectively terminated alongside the main contract by efflux of time.

Ratio Decidendi: The court held that since arbitration clauses are independent agreements, their validity persists despite the termination of the substantive contract, thus allowing the dispute to be resolved through arbitration.

Result: The arbitration application is allowed, appointing a sole arbitrator.

Table of Content
1. basis for invoking arbitration. (Para 1 , 2 , 3 , 4)
2. payments and project timelines. (Para 5 , 6 , 7)
3. issues of termination and its implications. (Para 8 , 9 , 10 , 11 , 13)
4. stance on insufficient stamping. (Para 12 , 14)
5. doctrine of separability. (Para 15 , 16)
6. interconnected agreements and clear intention to arbitrate. (Para 17 , 18)
7. outcome of the arbitration application. (Para 20)

ORDER :

K. LAKSHMAN, J.

The present Arbitration Application is filed under Section 11 (5)& (6) of the Arbitration and Conciliation Act, 1996 (hereinafter ‘the Act, 1996’) seeking appointment of a sole arbitrator.

2. Heard Mr. Sunil B. Ganu, learned senior counsel representing Mrs. Manjari S. Ganu, learned counsel for the Applicant and Mr. Avinash Desai, learned senior counsel representing Mr. Vadeendra Joshi, learned counsel for 2nd Respondent.

3. The Applicant is a developer. The Respondents are the owners of land admeasuring Ac. 2.00 Gts. in Sy. Nos. 9 and 10 situated at Khajaguda Village, Serlingampally Mandal, Rangareddy District (hereinafter ‘subject land’). The parties herein had entered into a Memorandum of Understanding (hereinafter ‘MoU’) dated 01.07.2020. The said MoU was for joint development of the subject land as a real estate project.

4. Under the terms of the MoU, the subject land was to be developed within a period of 48 months and a mutual extension of 12 months was permissible. The Respondents, under the MoU were entitled to 2,10,000 sq. feet of constructed area. Further, the Respondents were to receive Rs. 10 crores as refundable security deposit. Out of the said Rs. 10 crores, Rs. 1 crore was to be paid on the date of the MoU and remaining Rs. 9 crore on or before execution of a development agreement within 30 days of the MoU. The said MoU imposed certain obligations on both the parties. The MoU stated that the Respondents shall provide the relevant title documents and execute ‘transaction documents’ including agreement of sales before 10.07.2020. Likewise, it was provided that the Applicant, in addition to paying the refundable security deposit, shall also execute ‘transaction documents’.

5. Thereafter, an agreement of sale dated 01.07.2020 was executed whereby the Respondents agreed to sell the subject land for a sale consideration of Rs. 80 crores. The said agreement stated that out of the total sale consideration of Rs. 80 crores, the Applicant shall pay Rs. 2 crore on the date of the MoU, Rs. 18 crores within thirty (30) days of the agreement, and the remaining Rs. 60 crores within six (06) months from the date of the agreement which can be further extended by three (03) months.

6. The Applicant claims that the proposed development project required several approvals, permissions, and NOCs which would require significant time. Therefore, according to the Applicant, the parties agreed that the timelines mentioned in the MoU will not be strictly adhered to.

7. The Applicant contends that all the efforts to obtain the relevant approvals were being made. Further, the Applicant claims that it had paid a total of Rs. 13,52,80,000/- as on 01.01.2023. According to the Applicant, despite all its efforts, it had learnt that the Respondents were trying to enter into development agreements with third parties. Therefore, they filed an application under Section 9 of the Act, 1996. The said application was allowed vide order dated 19.08.2024 and a temporary injunction restraining the Respondents from alienating the subject property or creating encumbrances was granted.

8. Thereafter, an arbitration notice dated 10.01.2023 invoking the following clauses in the MoU dated 01.07.2020 and the agreement of sale dated 01.07.2020:

Clause in Memorandum of Understanding dt 1-7-2020 on page 5 reads as under:-

"In case of any conflict with the terms of this Binding Term Sheet shall be mutually resolved through a jointly appointed Arbitrator, whose resolution judgment shall be final and binding between the parties."

The Arbitration

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon telegram-icon
whatsapp-icon Back to top