IN THE HIGH COURT FOR THE STATE OF TELANGANA AT HYDERABAD
K. LAKSHMAN, J.
BNB Infracon India Pvt. Ltd. - Appellant
Versus
South Central Railway, Secunderabad and Another - Respondents
Arb. Application No. 59 of 2024
Decided On : 25-11-2024
ORDER :
1. The parties and lis involved in all the three applications are common and therefore, they were being heard together and disposed of by way of this common order.
2. Heard Sri M. Sridhar, learned counsel for the Applicants, Sri V.T. Kalyan, learned counsel appearing for respondent and Sri B.Mohan, learned counsel appearing for 2 nd respondent/formal party.
3. These applications are filed under Section 11(5 and 6) of the Arbitration and Conciliation Act, 1996 (for short, ‘the Act’) to appoint an Arbitrator to adjudicate the disputes between the parties.
CONTENTIONS OF THE APPLICANT:
4. The applicant is a private limited company and engaged in the business of construction and real estate activities. 1 st respondent has issued e-tender notice dated 05.11.2019 for proposed construction of quarters and the applicant having participated in the said tender, stood as a successful bidder.
5. The details of the tender notice, nature of work, costs of work, date of letter of acceptance are mentioned in the tabular form:-
| A.A. No. | Date of E-Tender | Nature of work, | Costs of work accepted Rs. | Date of letter of acceptance |
| 59/ 24 | 05.11.2019 | constructions of sw-1 construction of Type -IV quarters at Bellampally-2Nos, sw-2 construction of Type-II Quarters at Bellampally-10 Nos | 2,38,13,215. 58 | 10.03.2023 |
| 60/ 24 | 05.11.2019 | construction of Type-II Quarters 8 numbers at Ramagundam. | 1,39,63,03 2.39. | 11.02.2020 |
| 61/ 24 | 05.11.2019 | construction of sw-1 construction of Type-IV quarters at Armur-1 Number, Karimnagar-3 for Numbers, sw-2 construction of Type-III quarters at Armur-1 Number, sw-3 for construction of Type-II quarters at Armur-6 Numbers. | 2,96,28,17 1.13/- | 25.02.2020 |
| 63/ 24 | 05.11.2024 | constructions of office building of ADEN/KRMR, SSE/Works/KRMR, SSE/P.way/ARMU, sw-2 proposed construction of | 3,56,09748 .96/- | 25.02.2020 |
| stores shed to SSE/P.way/KRMR and SSE/P.way/ARMU, sw3- LPJL-NZB-improvement of staff quarters at KRMR, GDRA, LPJL Stations of 1st respondent at Armur, Karimnagar, Gangadhara, Lingampet and Jagityal. |
6. It is the contention of the applicant that a contract agreement was entered between the applicant and the 1 st respondent on 09.02.2021 for execution of aforesaid works. Vide letter dated 02.02.2021, it has informed to 1 st respondent that the period of contract work was already ended. Even then, 1 st respondent neither entered into agreement nor supplied drawings. The applicant has received structural designs of drawings from M/s. Arch view Designs Private Limited and vide letter dated 01.03.2021, it had submitted the same to 1 st respondent for their approval. As there was no response from the 1 st respondent, the applicant again addressed a letter dated 31.03.2021 requesting 1 st respondent to approve the drawings and also informed that the applicant had already started the miscellaneous works.
7. The applicant addressed letters dated 19.05.2021, 22.06.2021, 16.07.2021, 30.08.2021 to 1 st respondent but there was no response.
8. On the other hand, vide letter 23.10.2021, 1 st respondent issued notice of termination of contract dated 09.02.2021 to the applicant stating that applicant could not complete the work within the stipulated date of completion/mutually extended date of completion, that the applicant had failed to apply for further extension of period of completion on valid and reasonable grounds as acceptable, that 1 st respondent would claim damages under Clause-62 of General Conditions of Contract (GCC) in addition to forfeiting the Earnest Money Deposit (EMD) and encashing the Performance Guarantee (PG) submitted by the applicant. Therefore, applicant invoked arbitration Clause 64(3) of the GCC for adjudication of disputes between the applicant and respondent. The applicant filed an application vide O.P.No.13 of 2021 under Section 9 of the Act, and learned I Additional Chief Judge, City Civil Court, Secunderabad granted status quo which is subsisting. Since there are disputes between the applicant and 1 st respondent which are arbitrble in natu
Disputes arising from a construction contract are arbitrable, and failure to follow conciliation procedures does not bar the appointment of an arbitrator.
Point of Law : The very purpose of the A & C Act is to enable a party to invoke an arbitration clause at the earliest and for the arbitration to be completed at the earliest.
2020 Rules which came into force from the date of their publication in the Official Gazette, i.e. 12.02.2020, cannot be given retrospective effect. The intention of Government of India to make the 20....
The main legal principle established in the judgment is that parties must adhere to the pre-arbitral procedure outlined in the contract before seeking the appointment of an arbitrator, and failure to....
Arbitration - Merely because the panel of arbitrators are the retired employees who have worked in the Railways, it does not make them ineligible to act as the arbitrators.
The court emphasized the limited jurisdiction of the referral court under Section 11(6a) to examine the existence of an arbitration agreement and the need for a prima facie review to determine the ar....
The main legal principle established in the judgment is the procedure for appointing arbitrators under the amended Act and the modified Clause 64 of the GCC, emphasizing the ineligibility of certain ....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.