SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2024 Supreme(Gau) 32

IN THE HIGH COURT OF GAUHATI, NAGALAND, MIZORAM AND ARUNACHAL PRADESH
Arun Dev Choudhury, J.
R L Construction – Petitioner
Versus
North East Frontier Railway and Ors. – Respondents
Arb.P./26 of 2022
Decided On : 08-02-2024

Advocates:
Advocate Appeared:
For the Petitioner:Mr G N Sahewalla, Mr. M Sahewalla, Advocate
For the Respondents: Ms. B Sarma, CGC

The court emphasized the limited jurisdiction of the referral court under Section 11(6a) to examine the existence of an arbitration agreement and the need for a prima facie review to determine the arbitrability of disputes at the referral stage.

Headnote:

Arbitration - Construction Contract - Arbitration and Conciliation Act, 1996, Section 11(6)

Fact of the Case:

The petitioner entered into a construction contract with the respondent Railways. Disputes arose regarding the progress of the work, leading to termination of the contract by the Railways. The petitioner invoked various clauses of the contract and filed an application under Section 11(6) of the Arbitration and Conciliation Act, 1996 for appointment of an arbitrator.

Finding of the Court:

The court found that the existence of the arbitration agreement and the petitioner's privity to the contract were not disputed. The court limited its jurisdiction to examining the existence of an arbitration agreement, as per the provisions of Section 11(6a) of the Act.

Issues: The main issue was the arbitrability of the dispute, particularly whether the disputes fell within the scope of the arbitration clause or were non-arbitrable.

Ratio Decidendi: The court held that the determination of whether the disputes were arbitrable should be decided by the arbitral tribunal. It emphasized that at the referral stage, a prima facie review is required to weed out manifestly non-arbitrable disputes.

Final Decision: The court allowed the petition, appointing a former Chief Justice as the sole arbitrator. It directed the parties to raise the issue of arbitrability before the arbitrator.

JUDGMENT :

Heard Mr. GN Sahewalla, learned Senior counsel assisted by Mr. M Sahewalla, learned counsel for the petitioner. Also heard Ms. B Sarma, learned CGC.

2. The present application is filed under Section 11 (6) of the Arbitration and Conciliation Act, 1996. The background fact of the present case can be summarised as follows:

    I. Pursuant to a tender process issued by the respondent Railways for execution of work “construction of Sub-structure over pile foundation for major bridges No. 37 (24.4 X 3 Composite Girder) at Ch.13.831 km & Construction of ROB No. 18 at Km 6.1 (Span 1X8.7 m RCC Box), including other ancillary works in between stations Bairabi and Sairang in connection with the construction of new BG Railway Line from Bairabi to Sairang (Mizoram)”, on 01.03.2019 a letter of acceptance was issued by the Railways.

II. Accordingly, a contract was executed into between the parties on 10.01.2020.

III. Subsequently, a dispute regarding the progress of the work was raised by the respondent Railways and accordingly on 10.03.2021, a 7 days notice under Clause 20 of Standard General Condition of contract was issued asking the petitioner to commence the work/ to make good the progress work. It was further provided in the said notice that on failing to adhere to the demand on expiry of the 7 days period the contract will be rescinded and the contract work under the contract will be carried out independently without the participation of the petitioner and it was further proposed in the event of failure, the security deposit shall be forfeited.

III. On 09.03.2020, the Railways advised the petitioner to extend the contract as contract was supposed to expire on 30.04.2020 and it was further advised to submit an application with proper justification for consideration of the extension.

IV. Subsequently, by an order dated 30.04.2020, an extension for completion of the work was granted up to 31.03.2021.

V. Thereafter, by another communication dated 23.07.2020, the Railways instructed the petitioner to apply for work permit to the Government of Mizoram through the Office of the Railway so as to facilitate movement of the staff and labour at Mizoram from outside. Such communication reflects that in the meantime, the ongoing construction in Bairabi Sairang project has been hampered due to Covid-19 and subsequent lockdown.

VI. Thereafter, by a communication dated 09.03.2021, the petitioner issued a communication to the respondent for foreclosure of the works due to applicability of force majeure under Clause 17 of the GCC, in view of Covid-19 pandemic and the border unrest between Assam and Mizoram and abnormal increase in materials and labour cost in connection with the work.

VII. Accordingly, a prayer was made for foreclosure of the work under Clause 17 of the GCC sympathically without risk and cost.

VIII. Thereafter, by a communication dated 01.03.2021, the Railways issued a notice under Clause 62 of the GCC to start the work.

IX. Subsequently, on 10.03.2021 alleging that the petitioner could not start the work within the demanded period of 7 days under the notice dated 01.03.2021, a notice of 48 hours in terms of Clause 62 of GCC was issued to the petitioner to commence the work.

X. Subsequently, by yet another communication dated 15.03.2021, the contract was rescinded in terms of Clause 62 of the GCC in view of the failure of the petitioner to resume work even after the 48 hours notice and a decision was taken by the Railways that the contract will be carried out independently without participation of the petitioner and the petitioner as an individual or a partnership firm / JV was debarred from participating in the tender process for execution of the balance work and it was further decided to forfeit the security deposit and performance guarantee.

XI. Thereafter, an application under Section 9 of the Arbitration and Conciliation Act, 1996 was preferred by the petitioner, which was registered as Misc Arbitration Case No. 13/2021.

X

      Click Here to Read the rest of this document
      1
      2
      3
      4
      5
      6
      7
      8
      9
      10
      11
      SupremeToday Portrait Ad
      supreme today icon
      logo-black

      An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

      Please visit our Training & Support
      Center or Contact Us for assistance

      qr

      Scan Me!

      India’s Legal research and Law Firm App, Download now!

      For Daily Legal Updates, Join us on :

      whatsapp-icon Back to top