SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Telangana) 1749

IN THE HIGH COURT FOR THE STATE OF TELANGANA AT HYDERABAD
NAGESH BHEEMAPAKA, J.
M/s.Kesari Marine Service – Appellant  
Versus
The Indian Oil Corporation Limited – Respondent 
Writ Petition No. 16559 of 2025
Decided On : 07-11-2025

Advocates:
Advocate Appeared:
For the Appellant : S N CHIDAMBARA SASTRY
For the Respondent: DOMINIC FERNANDES SC FOR IOCL

The court held that the cancellation of a Letter of Acceptance was arbitrary as it was based on a miscalculation of the 30-day compliance period, violating principles of natural justice.

Headnote:(A) General Clauses Act, 1897 - Provisions regarding exclusion of a day for computation of time - Tender conditions and natural justice principles applied in contractual disputes. (Paras 10, 12, 19)

(B) Tendering Process - Requirement for contractors to comply with timelines prescribed for readiness - The unjust cancellation of Letter of Acceptance on a baseless premise is arbitrary. (Paras 4.1, 17)

(C) Judicial Review - Courts should avoid interfering in commercial contract matters unless there are substantial violations of procedural fairness. (Paras 13, 15)

Facts of the case:
The petitioner, a barge operator, contested the cancellation of its Letter of Acceptance for failing to position its barge within 30 days, which was claimed to have been calculated incorrectly due to a misunderstanding of February's days. The Court previously found the cancellation arbitrary and urged reconsideration, leading to the present petition due to further unjustified cancellation.

Findings of Court:
Upon review, the Court established that the cancellation based on an earlier incorrect premise lacked legal justification and mandated that the petitioner must be allowed to fulfill its contract obligations as per prior agreements.

Issues: The primary issue revolved around the calculation of time for compliance with contract conditions and adherence to principles of natural justice in contract cancellations.

Ratio Decidendi: The cancellation was deemed mechanical and arbitrary because the 30-day period had not lapsed when the contract was cancelled. The authorities failed to follow lawful procedures, leading to injunctions against their actions.

Result: Petition allowed, and the prior cancellation set aside.

Table of Content
1. procedural compliance in tender processes (Para 1)
2. inadequate opportunity for defense in contract cancellations (Para 4)
3. re-examination of previously adjudicated disputes (Para 10 , 11 , 12)
4. judgment on re-establishing contractual obligations (Para 20 , 21)

ORDER :

1. The case of petitioner is that pursuant to the Tender Notice issued by the 1st respondent for Bunker supply of black oil and white oil through tanker barges to the coastal/foreign run sea going vessels berthed at inner harbor, outer harbor, and outer anchorage of Vizag Port, Petitioner along with others submitted tenders. The name of Petitioner's barge is CAPSTAR-1. After getting fully satisfied about Petitioner's barge, the 1st Respondent accepted the tender submitted by them. Petitioner tendered for 30% transportation of the Oil and it stood as L2 among the Tenderers, L1 being for 50% transportation. It is submitted that the 1st Respondent issued Letter of Acceptance (LOA) dated 20.02.2025, as per which, the period of contract is three years from the date of the LoA, extendable for a further period of 9 months on mutual consent, in line, with GeM conditions. It is stated Petitioner had complied with all the formalities for clearance of its berth from Kakinada Port to Vizag Port for transporting the black oil/white oil, as per the requirement and the work orders of the 1st Respondent in accordance with the LOA.

1.1. It is stated, the 1st Respondent issued Petitioner Work Order dated 12.03.2025 for transporting white oil and black oil to coastal and foreign-run vessels stationed at Vizag Port through tanker barges (small category barges). Under the relevant Rules and Regulations governing the movement of barges, petitioner applied on 03.03.2025 for clearance of its Barge from Kakinada port; the said port delayed issuance of clearance. Thereafter, on 12.03.2025, the 1st Respondent issued work order which should be followed by due execution of the prescribed Contract and issuance of LOA. As Kakinada port was delaying clearance, petitioner re-submitted its Application on 22.03.2025. As there was no response, petitioner filed Writ Petition No. 8234 of 2025 and Kakinada Port issued clearance. By an e mail, petitioner informed the 1st Respondent that its Barge would be ready in all respects at Vizag port by 27.03.2025.

1.2. As per normal practice and procedure in vogue, the 1st Respondent has to follow up the said LOA with a written prescribed contract and issuance of LOA for transportation of the oil, pursuant to the said work order. The 1st Respondent did not get the prescribed contract duly executed by Petitioner and no LOA was issued to petitioner. Petitioner received an e mail dated 21.03.2025 from the 1st Respondent to position the Barge within 30 days from the date of LOA i.e by 21.03.2025 failing which, the said LOA is liable for cancellation. According to petitioner, this communication is illegal and impermissible, as, by 21.03.2025, 30 days did not expire from the date of the LOA. The 1st Respondent failed to notice that February has only 28 days.

1.3. Petitioner sent e mail dated 28.03.2025 informing that its Barge arrived at Vizag port on 28.03.2025 and is ready for the procedural inspections by the 1st Respondent, followed by e mail dated 29.03.2025 informing the 1st Respondent that survey of its Barge by Vizag port was completed and that VPT Harbour Craft license was also issued by the said port. Again, on 01.04.2025 at 12.58 hours, by another e mail all these aspects were communicated to the 1st Respondent requesting them to issue Letter of Intent for transportation of oil, as per the said work order given to petitioner. However, Petitioner received an e-mail dated 01.04.2025 (at 19.25 hours) from one of the officials of the 1st Respondent stating that as per the earlier e mail dated 21.03.2025, the said LOA issued to petitioner stands cancelled, as, by 21.03.2025, they did not keep its barge ready. It referred to "Point 4 in the Tend

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top