SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Online)(APTEL) 10

APPELLATE TRIBUNAL FOR ELECTRICITY
Ramesh Ranganathan, Chairperson, Seema Gupta, Technical Member (Electricity)
Maharashtra State Electricity Distribution Company Limited – Appellant
Versus
Central Electricity Regulatory Commission – Respondent
APPEAL NO. 232 OF 2025 | IA NO. 1114 OF 2025 | IA NO. 1192 OF 2025



Advocates:
For the Appellants/Petitioners: Ramanuj Kumar, Vishal Binod, Aditya Dubey, Sagnik Maitra, Rimali Batra, Abhishek Lalwani
For the Respondents: Anand K. Ganesan, Swapna Seshadri, Ritu Apurva, Karthikeyan M.

An issue finally decided by the Supreme Court cannot be re-agitated in a fresh proceeding before a lower tribunal, even if the party relies on a subsequent event that is based on grounds already rejected in the earlier litigation.

Headnote:(A) Electricity Act, 2003 - Sections 79(1)(f), 111, 111(3) - Code of Civil Procedure, 1908 - Section 11 (Explanations III, IV, V) - Limitation Act, 1963 - Constitution of India - Article 141 - The principle of res judicata, including constructive res judicata, applies to proceedings before regulatory commissions and appellate tribunals, barring re-agitation of issues that were directly and substantially in issue in earlier proceedings between the same parties, or which they might and ought to have raised. An order of a competent court, even if erroneous, is binding inter-parties and cannot be overturned in collateral proceedings. (Paras 68, 71, 76, 82, 87, 97)

(B) Electricity Act, 2003 - Power Purchase Agreement - Termination - Unilateral termination of a non-determinable contract by one party is impermissible in law, especially when the grounds for termination have been explicitly rejected by judicial pronouncements. Where a contract does not contain a termination clause and the party suffering the termination has been ready and willing to perform, the burden to establish the validity of the termination lies on the terminating party, not the other. A unilateral termination based on grounds that have been judicially invalidated does not extinguish obligations under the contract and amounts to a breach by repudiation. (Paras 100, 102, 103, 104, 105, 106)

(C) Electricity Act, 2003 - Constructive Res Judicata - Explanation IV to Section 11 CPC applies to appellate stages. A party which had the opportunity to raise a ground in a prior appeal but failed to do so is barred from raising it in subsequent proceedings. Filing a civil appeal and a review petition before the Supreme Court on the same issue, which were dismissed, also attracts Explanations III and V to Section 11 CPC, barring the same issue from being re-litigated in a fresh proceeding. (Paras 76, 80, 84, 86)

Facts of the case:
The Appellant, a distribution company (MSEDCL), filed an appeal against the order of the Central Electricity Regulatory Commission (CERC) which dismissed its petition (No. 276/MP/2024) as not maintainable. MSEDCL's petition sought to declare invoices raised by the Respondent, a generating company (RGPPL), as void, arguing that the Power Purchase Agreement (PPA) between them had been unilaterally terminated by MSEDCL in 2014. The CERC held that the issue of the PPA's termination was barred by the principles of res judicata and constructive res judicata, as it had been raised (either directly or could have been raised) in earlier litigation between the same parties—Petition No. 166/MP/2012, Appeal No. 261/2013, Civil Appeal No. 1922/2023, and Review Petition No. 1997/2023—which had all concluded against MSEDCL, definitively holding that RGPPL was entitled to capacity charges under the PPA even without MSEDCL's specific consent.

Findings of Court:
The Appellate Tribunal dismissed MSEDCL's appeal, upholding the CERC's order. It held that the core issue—whether MSEDCL was liable to pay capacity charges when RGPPL declared availability based on RLNG—had been finally decided against MSEDCL in the prior litigation, which included a definitive judgment from the Supreme Court. The Tribunal found that the unilateral termination of the PPA was impermissible as the PPA was non-determinable and the grounds for termination had been specifically rejected in the earlier judicial pronouncements. Furthermore, the claims regarding the validity of the termination and the adjustment of invoices were either barred by res judicata (including constructive res judicata) or were pending adjudication before the Supreme Court in a separate civil appeal.

Issues: (i) Whether Petition No. 276/MP/2024 filed by MSEDCL before the CERC was barred by the principles of res judicata given the prior litigation on the PPA's interpretation. (ii) Whether the unilateral termination of the PPA by MSEDCL was legally valid and could form the basis for a fresh cause of action.

Ratio Decidendi: The court reasoned that the very basis of the termination letter—MSEDCL's interpretation of Articles 4.3 and 5.9 of the PPA—had been conclusively and finally decided against it by the CERC, Appellate Tribunal, and Supreme Court. Therefore, the issue was res judicata. Even if the termination was a subsequent event, MSEDCL failed to amend its earlier appeal to include it, thus attracting constructive res judicata. Furthermore, the PPA being non-determinable, its unilateral termination without valid legal grounds was itself invalid, and MSEDCL could not use its own wrongful act to avoid contractual liabilities that had been affirmed by judicial decrees. Result : Appeal dismissed. All IAs dismissed. FULL JUDGMENT: The judgment provides a detailed analysis of the law of res judicata (Section 11 CPC), the nature of determinable contracts, and the binding effect of Supreme Court orders. It distinguishes the case from I.S. Sikandar v. K. Subramani and applies the principles from K.S. Manjunath and Others. The court has provided a comprehensive headnote with paragraph references, making it a valuable precedent for cases involving re-litigation of settled issues in electricity regulatory matters. The case is a significant authority on the application of res judicata in regulatory proceedings and on the conditions under which a contract can be unilaterally terminated, particularly in the context of long-term power purchase agreements governed by the Electricity Act, 2003.

JUDGEMENT

PER HON’BLE MR. JUSTICE RAMESH RANGANATHAN, CHAIRPERSON

I. INTRODUCTION:

Appeal No. 232 of 2025 has been filed by the Maharashtra State Electricity Distribution Company Limited (“MSEDCL” for short) aggrieved by the order passed by the Central Electricity Regulatory Commission (“CERC” for short) in Petition No. 276/MP/2024 dated 12.06.2025. The reliefs sought by MSEDCL, in Appeal No. 232 of 2025, are (a) to set aside the order of the CERC in Petition No. 276/MP/2024; (b) declare that the invoices raised by the 2nd Respondent- Ratnagiri Gas and Power Private Ltd (“RGPPL” for short) against the Appellant-MSEDCL, as more specifically set out in Annexure A-29 of the Appeal, as void, non-est and illegal; (c) restrain the 2nd Respondent-RGPPL from issuing any further invoices under the terminated PPA dated 10.04.2007 and from uploading any further invoices on the PRAAPTI portal, seeking payment thereof; (d) direct the 3rd Respondent-Grid Controller of India Limited and the 4th Respondent-PFC Limited not to take any coercive actions prejudicial to the Appellant’s short term access and full GNA; and (e) restrain the Respondents from taking any coercive steps against the Appellants in furtherance of such impermissible, inapplicable, void, non-est and arbitrary invoices, including by way of regulation of GNA and open access under the framework of the LPS Rules.

Petition No. 276/MP/2024 was filed by MSEDCL before the CERC, under Section 79(1)(f) of the Electricity Act, 2003, seeking quashing of the invoices raised by the 1st Respondent-RGPPL on them as being void, illegal and non-est; seeking appropriate directions against RGPPL to withdraw the invoices uploaded on the PRAAPTI portal; to restrain them from issuing or uploading any further invoices on the said portal; and from taking any coercive action in furtherance of such invoices, including by way of seeking regulation of open access under the Electricity (Late Payment Surcharge and Related Matters) Rules, 2022.

II. IMPUGNED ORDER PASSED BY THE CERC IN PETITION NO. 276/MP/2024 DATED 12TH JUNE, 2025: ITS CONTENTS:

In its order, in Petition No. 276/MP/2024 dated 12th June, 2025, the CERC noted the background facts leading up to the filing of E.P.No.12 of 2023 before this Tribunal by RGPPL. It then noted that MSEDCL had filed IA No.1068 of 2024 in the Execution Proceedings (E.P. No.12/2023) seeking intervention of this Tribunal in respect of the PRAAPTI proceedings in the light of the approaching trigger date for the curtailment of open access of MSEDCL, due to non-payment of dues against the outstanding invoices raised by RGPPL; MSEDCL had also filed W.P. No. 24685 of 2024 before the High Court of Bombay, seeking directions to set aside the invoices raised by RGPPL, and also to restrain RGPPL from issuing fresh invoices under the allegedly terminated PPA, and from uploading any invoices in the PRAAPTI portal; the Bombay High Court, vide its order dated 8.8.2024, disposed of the said writ petition directing: (a) the Petitioner (MSEDCL) to file their Petition before the CERC by 14th August 2024 along with an application for stay. These papers and proceedings shall also be served on the Respondents by 14th August, 2024; (b) the CERC to take up the stay application of the Petitioner on 20th August, 2024; (c) in the interregnum and until 20th August, 2024, there shall be no reduction or withdrawal of access for sale and purchase of electricity as provided in Rule 7(c) of the said Rules. It was clarified that this will not affect the reduction. If any, that is already triggered and /or taken place; (d) it was clarified that the interim protection granted will be subject to the orders passed by the CERC in the proposed stay application to be filed by the Petitioner; and the CERC shall decide the Petition and the application for the interim reliefs of the Petitioner without being influenced by anything stated in this order; and, in the above background, MSEDCL had filed the present Petition

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top