SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Online)(CERC) 194

CENTRAL ELECTRICITY REGULATORY COMMISSION
Jishnu Barua, Chairperson, Ramesh Babu V., Member, Harish Dudani, Member, Ravinder Singh Dhillon, Member
Lanco Kondapalli Power Limited – Appellant
Versus
Andhra Pradesh Power Coordination Committee – Respondent
Petition No. 249/MP/2022



Advocates:
For the Appellants/Petitioners: M.G. Ramachandran, Sanjay Sen, Mandakini Ghosh, Neha M. Dabral, Saurabh Gupta, Puneet Yadav, Akshansh Gupta
For the Respondents: Swapna Seshadri, Anand K. Ganesan, Aishwarya, Harsha

Disputes concerning payment of capacity and energy charges under a power purchase agreement constitute 'tariff disputes' within the exclusive adjudicatory jurisdiction of the regulatory commission. Contractually valid declarations of commercial operation based on performance test results are binding, and capacity charges are payable from such dates.

Headnote:(A) Electricity Act, 2003 - Sections 79(1)(b) and 79(1)(f) - Power Purchase Agreement (PPA) - Tariff dispute - Adjudication jurisdiction - Central Commission has jurisdiction to adjudicate disputes between generating company and distribution licensees regarding interpretation of tariff, billing, and payment obligations - Such matters constitute 'tariff disputes' impacting consumers directly, thus falling under statutory regulatory functions rather than non-tariff disputes referable to arbitration. (Paras 26, 27, 28)

(B) Limitation Act, 1963 - Section 14(2) - Exclusion of time - Period spent in bona fide arbitration proceedings and subsequent disposal by high court must be excluded when computing limitation period for filing petition before regulatory commission. (Paras 21, 22, 23)

(C) Contract Law - Commercial Operation Date (COD) - Declaration of COD - Where PPA stipulates successful performance acceptance testing as the sole requirement for declaration of COD, it does not mandate governmental approval or prior consensus with the purchaser for such declaration; once performance standards are met, the generator is entitled to declare COD regardless of the purchaser’s subsequent grid drawal timeline. (Paras 36, 39, 43)

(D) Specific Performance - Obligation to pay capacity charges - Where PPA requires payment of capacity charges upon COD of generating units, the purchasing entity cannot unilaterally shift COD to a later date to avoid payment, and having continued to accept power under the subsisting agreement's terms, remains liable to compensate for the services rendered based on initial declared COD. (Paras 44, 45, 50, 51)

Facts of the case:
The petitioner, a power generation company, sought payment of capacity charges and interest for the period following the achievement of the commercial operation date (COD) of its project units. The respondents, distribution companies, refused payment, contesting the COD date and citing project delays. Previous legal proceedings established that the claims were not time-barred. The dispute was subsequently transferred to the Commission following statutory reorganisation.

Findings of Court:
The Commission held that the petitioner is entitled to capacity charges from the date of respective unit CODs. It rejected the respondents' attempt to unilaterally designate a later date as the project COD based on their convenience or government orders, as the contract specifically provided for the generator's right to declare COD upon passing performance tests.

Issues: Whether the claims were barred by limitation, whether the Commission or an arbitrator should adjudicate the dispute, and the criteria for determining the project COD and subsequent entitlement to capacity charges.

Ratio Decidendi: All matters significantly impacting the tariff of a generating company are 'tariff disputes' assigned to the regulatory commission's adjudicatory power. Once contractually valid test procedures are followed, the declaration of COD is a function of the generator, and capacity charge obligations commence therefrom.

Result: Petition allowed; respondents directed to pay outstanding capacity charges with interest.

Table of Content
1. overview of ppa disputes and procedural history. (Para 1 , 2 , 3 , 4)
2. parties' contentions on cod, limitation, and ppa validity. (Para 5 , 6 , 7 , 8 , 9 , 10 , 11 , 12 , 13 , 14 , 15 , 16 , 17 , 18)
3. limitation period excludes time spent in bona fide arbitration. (Para 19 , 20 , 21 , 22 , 23)
4. tariff-related disputes are within commission's adjudicatory jurisdiction. (Para 24 , 25 , 26 , 27 , 28)
5. cod is determined by performance tests, not unilateral utility acceptance. (Para 29 , 30 , 31 , 32 , 33 , 34 , 35 , 36 , 37 , 38 , 39 , 40 , 41 , 42 , 43 , 44 , 45 , 46)
6. right to claim capacity charges accrues from unit cods. (Para 47 , 48 , 49 , 50 , 51)
7. liability for unpaid charges plus late payment surcharge. (Para 52 , 53 , 54 , 55 , 56)
Parties Present:

Shri M.G. Ramachandran, Senior Advocate, LKPL

Shri Sanjay Sen, Senior Advocate, LKPL

Ms. Mandakini Ghosh, Advocate, LKPL

Ms. Neha M. Dabral, Advocate, LKPL

Shri Saurabh Gupta, Advocate, LKPL

Shri Puneet Yadav, Advocate, LKPL

Shri Akshansh Gupta, Advocate, LKPL

Ms. Swapna Seshadri, Advocate, Andhra & Telangana Discoms

Shri Anand K. Ganesan, Advocate, Andhra & Telangana Discoms

Ms. Aishwarya, Advocate, Andhra & Telangana Discoms

Shri Harsha, Advocate, Andhra & Telangana Discoms

ORDER

The Petitioner, Lanco Kondapalli Power Limited (in short ‘LKPL’), has filed this Petition under Section 79 (1)(f) of the Electricity Act, 2003 (‘the Act’), seeking the following reliefs:

(a) Allow the present Petition and direct that the pleadings in OP No. 33 of 2009 (renumbered as OP No. 27/2015) as filed before the Andhra Pradesh Electricity Regulatory Commission be taken on record by this Hon’ble Commission.

(b) Declare / hold that the Petitioner Company is entitled for Capacity Charges of Rs.76.18 Crores as per the provisions of Power Purchase Agreement dated 31.3.1997 and consequently direct the respondents 1 to 6 to pay 78.16 Crores as claimed vide Bill Nos. 3A, 4A, SA, 6A, 7A, and 8 for the period from 21.01.2000 to 01.01.2001;

(c) Declare / hold that the Petitioner Company is entitled for interest of Rs. 86,35,87,699/- for delay in payment of Capacity Charges and Energy Charges for the Bill Nos. 3A, 4A, SA, 6A, 7A, and 8 in terms of Power Purchase Agreement dated 31.3.1997 from 9.2.2001 till the date of filing of this Petition and consequently direct the respondents 1 to 6 to pay the same;

(d) Direct the Respondents to pay interest on Rs.78.16 Crores and Rs. 86,35,87,699/- at working capital interest rate from the date of this Petition till the date of realization; and

(e) Pass any other or further order/reliefs which this Hon’ble Commission may deem fit and proper in light of justice, equity and good conscience.

Background of the case

2. The Petitioner, LKPL, is a company incorporated under the Companies Act, 1956, inter alia, engaged in the generation and sale of electricity. It has set-up a 368.144 MW Combined Cycle Power Project located in the Kondapalli Industrial Development Area, Krishna District, Andhra Pradesh. It is a short-gestation power plant completed in time, out of the six projects awarded through Tariff Based International Competitive Bidding by the Government of Andhra Pradesh (GoAP)/ Andhra Pradesh State Electricity Board. LKPL executed PPA with the erstwhile APSEB (presently APTRANSCO) on 31.3.1997 for the purchase of all the available capacity, in accordance with the terms and conditions of the said PPA. LKPL implemented the project, and the first generating unit was tested from 22.6.2000 to 26.7.2000, and with the COD of the first unit declared on 26.7.2000. Similarly, the COD of the second generating unit was declared on 24.9.2000, after testing. Subsequently, LKPL demonstrated the project's total capacity as per the provisions of the PPA on 25.10.2000, in the presence of APTRANSCO and NTPC officials (deputed by APTRANSCO), and the project's COD was declared on 25.10.2000. Thereafter, vide G.O.Ms. No. 59 dated 7.6.2005, Respondent No. 1, Andhra Pradesh P

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top