CENTRAL ELECTRICITY REGULATORY COMMISSION
Jishnu Barua, Chairperson, Ramesh Babu V., Member, Harish Dudani, Member, Ravinder Singh Dhillon, Member
Lanco Kondapalli Power Limited – Appellant
Versus
Andhra Pradesh Power Coordination Committee – Respondent
Petition No. 249/MP/2022
| Table of Content |
|---|
| 1. overview of ppa disputes and procedural history. (Para 1 , 2 , 3 , 4) |
| 2. parties' contentions on cod, limitation, and ppa validity. (Para 5 , 6 , 7 , 8 , 9 , 10 , 11 , 12 , 13 , 14 , 15 , 16 , 17 , 18) |
| 3. limitation period excludes time spent in bona fide arbitration. (Para 19 , 20 , 21 , 22 , 23) |
| 4. tariff-related disputes are within commission's adjudicatory jurisdiction. (Para 24 , 25 , 26 , 27 , 28) |
| 5. cod is determined by performance tests, not unilateral utility acceptance. (Para 29 , 30 , 31 , 32 , 33 , 34 , 35 , 36 , 37 , 38 , 39 , 40 , 41 , 42 , 43 , 44 , 45 , 46) |
| 6. right to claim capacity charges accrues from unit cods. (Para 47 , 48 , 49 , 50 , 51) |
| 7. liability for unpaid charges plus late payment surcharge. (Para 52 , 53 , 54 , 55 , 56) |
Shri M.G. Ramachandran, Senior Advocate, LKPL
Shri Sanjay Sen, Senior Advocate, LKPL
Ms. Mandakini Ghosh, Advocate, LKPL
Ms. Neha M. Dabral, Advocate, LKPL
Shri Saurabh Gupta, Advocate, LKPL
Shri Puneet Yadav, Advocate, LKPL
Shri Akshansh Gupta, Advocate, LKPL
Ms. Swapna Seshadri, Advocate, Andhra & Telangana Discoms
Shri Anand K. Ganesan, Advocate, Andhra & Telangana Discoms
Ms. Aishwarya, Advocate, Andhra & Telangana Discoms
Shri Harsha, Advocate, Andhra & Telangana Discoms
ORDER
The Petitioner, Lanco Kondapalli Power Limited (in short ‘LKPL’), has filed this Petition under Section 79 (1)(f) of the Electricity Act, 2003 (‘the Act’), seeking the following reliefs:
(a) Allow the present Petition and direct that the pleadings in OP No. 33 of 2009 (renumbered as OP No. 27/2015) as filed before the Andhra Pradesh Electricity Regulatory Commission be taken on record by this Hon’ble Commission.
(b) Declare / hold that the Petitioner Company is entitled for Capacity Charges of Rs.76.18 Crores as per the provisions of Power Purchase Agreement dated 31.3.1997 and consequently direct the respondents 1 to 6 to pay 78.16 Crores as claimed vide Bill Nos. 3A, 4A, SA, 6A, 7A, and 8 for the period from 21.01.2000 to 01.01.2001;
(c) Declare / hold that the Petitioner Company is entitled for interest of Rs. 86,35,87,699/- for delay in payment of Capacity Charges and Energy Charges for the Bill Nos. 3A, 4A, SA, 6A, 7A, and 8 in terms of Power Purchase Agreement dated 31.3.1997 from 9.2.2001 till the date of filing of this Petition and consequently direct the respondents 1 to 6 to pay the same;
(d) Direct the Respondents to pay interest on Rs.78.16 Crores and Rs. 86,35,87,699/- at working capital interest rate from the date of this Petition till the date of realization; and
(e) Pass any other or further order/reliefs which this Hon’ble Commission may deem fit and proper in light of justice, equity and good conscience.
Background of the case
2. The Petitioner, LKPL, is a company incorporated under the Companies Act, 1956, inter alia, engaged in the generation and sale of electricity. It has set-up a 368.144 MW Combined Cycle Power Project located in the Kondapalli Industrial Development Area, Krishna District, Andhra Pradesh. It is a short-gestation power plant completed in time, out of the six projects awarded through Tariff Based International Competitive Bidding by the Government of Andhra Pradesh (GoAP)/ Andhra Pradesh State Electricity Board. LKPL executed PPA with the erstwhile APSEB (presently APTRANSCO) on 31.3.1997 for the purchase of all the available capacity, in accordance with the terms and conditions of the said PPA. LKPL implemented the project, and the first generating unit was tested from 22.6.2000 to 26.7.2000, and with the COD of the first unit declared on 26.7.2000. Similarly, the COD of the second generating unit was declared on 24.9.2000, after testing. Subsequently, LKPL demonstrated the project's total capacity as per the provisions of the PPA on 25.10.2000, in the presence of APTRANSCO and NTPC officials (deputed by APTRANSCO), and the project's COD was declared on 25.10.2000. Thereafter, vide G.O.Ms. No. 59 dated 7.6.2005, Respondent No. 1, Andhra Pradesh P
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.