IN THE HIGH COURT OF DELHI AT NEW DELHI
AVNEESH JHINGAN, J.
Pandrol Rahee Technologies Pvt Ltd., Through Authorized Representative Varun Bhojak – Petitioner
Versus
IRCON International Ltd, Through Its Chairman Mr. Sunil Kumar Chaudhury – Respondent
O.M.P. (COMM) 414 of 2023
Decided On : 20-05-2026
| Table of Content |
|---|
| 1. factual background of the arbitration dispute over tender quantities and payments. (Para 1 , 2) |
| 2. conflicting contentions regarding contract interpretation and scope of section 34 interference. (Para 3 , 4) |
| 3. determination that the contract was for a fixed-price supply and variation clauses did not trigger additional payments. (Para 5 , 6 , 7 , 8 , 9 , 10 , 11 , 12 , 13 , 14 , 15 , 16 , 18) |
| 4. limited scope of judicial review under section 34 of the arbitration and conciliation act. (Para 17) |
| 5. final outcome dismissing the section 34 petition and upholding the arbitral award. (Para 19) |
JUDGMENT :
AVNEESH JHINGAN, J.
1. The present petition is filed under Section 34 of the Arbitration and Conciliation Act, 1996 (for short 'the Act') against the arbitral award dated 15.05.2023 (for brevity 'the award').
2. The facts shorn of unnecessary detail are that the respondent on 21.04.2015, issued Notice Inviting Tender (for short 'NIT') for design, manufacture, supply, transportation and delivery of Ballastless Track Fastening for standard gauge railway track (1435 mm) with 60 kg 1080 grade rail for installation of ballastless track in elevated and underground sections of Mukundpur–Lajpat Nagar (excluding Line-7) of Delhi MRTS Project Phase-III.
2.1 The petitioner was the successful bidder and the Letter of Acceptance (LOA) dated 21.05.2015 was issued. On 09.10.2015, the parties executed Contract CT-1A (for brevity 'the contract'). The respondent by communication dated 04.08.2016 (hereinafter referred to as 'variation order') varied the quantity of the ballastless track fastening sets (for short 'sets') to be supplied under each of the categories and the total quantity increased from 1,86,500 sets to 1,98,715 sets. The details of the change in quantities of sets pursuant to the variation order are tabulated below:
| Item No | Description of Item | Unit | BOQ Qty. | Variation Qty. | Total Qty. after variation | Percentage Change % |
|---|---|---|---|---|---|---|
| 1 | Supply of BLT fittings | |||||
| 1.1 | Supply track & curve track up to 1750m | Sets | 1,60,000 | (-) 56,751 | 1,03,249 | (-) 35.46% |
| 1.2 | For curved track | |||||
| a | Radius 1750-1000m | Sets | 1,500 | (+) 13,522 | 15,022 | (+) 901.46% |
| b | Radius 1000m 500m | Sets | 4,500 | (+) 20,558 | 25,058 | (+) 456.84% |
| c | Radius 500-300m | Sets | 19,000 | (+) 28,804 | 47,804 | (+) 151.60% |
| d | Radius <300m | Sets | 1500 | (+) 6,082 | 7,582 | (+) 405.46% |
| Total | 1,86,500 | 1,98,715 |
2.2 The dispute arose as according to the petitioner, the revised quantities required supply of a 4-bolt fastening system in place of the 2-bolt fastening system for curved tracks above 500 metres. The petitioner had to procure and supply additional components including anchor, nut bolts, eccentric bush, collared washer and compression springs for varied order and thereby the cost of execution increased.
2.3 The petitioner completed the supplies and completion certificate dated 11.05.2017 was issued. The payment for the sets supplied was released by the respondent. The claim of the petitioner for payment over and above agreed price towards the additional components supplied was denied by the respondent.
2.4 The petitioner on 23.08.2019, invoked arbitration by issuing notice under Section 21 of the Act. Vide court order dated 25.10.2021, the sole arbitrator was appointed and the proceedings culminated in the impugned award dated 15.05.2023. The claims of the petitioner were rejected and hence, the present petition.
3. Learned senior counsel for the petitioner submits that the sets were accepted by the respondent and the contract was fully executed. The petitioner had to supply 4-bolt system instead of the 2-bolt system for the curved tracks above 500 metres. The contention is that the arbitrator failed to appreciate that the cost of supplies increased due to the variation order.
3.1 Reliance is on the decisions of the Supreme Court in Patel Engineering Ltd. v. North Eastern Electric Power Corporation Ltd. , (2020) 7 SCC 167, Associate Builders v. Delhi Development Authority , (2015) 3 SCC 49, Dyna Technologies Pvt. Ltd. v. Crompton Greaves Ltd. , (2019) 20 SCC 1 and Ssangyong E
Patel Engineering Ltd. v. North Eastern Electric Power Corporation Ltd.
Associate Builders v. Delhi Development Authority
Dyna Technologies Pvt. Ltd. v. Crompton Greaves Ltd.
Ssangyong Engineering & Construction Co. Ltd. v. National Highways Authority of India
Prakash Atlanta (JV) v. National Highways Authority of India
Ramesh Kumar Jain v. Bharat Aluminium Company Limited (BALCO)
Consolidated Construction Consortium Limited v. Software Technology Parks of India
Sepco Electric Power Construction Corporation v. GMR Kamalanga Energy Ltd.
Parsa Kente Collieries Limited. v. Rajasthan Rajya Vidyut Utpadan Nigam Limited
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.