IN THE HIGH COURT OF DELHI AT NEW DELHI
JASMEET SINGH, J.
Atlanta Infra Assets Limited - Petitioner
Versus
National Highway Authority of India - Respondent
O.M.P. (COMM) No. 152 of 2022, O.M.P. (COMM) No. 243 of 2022
Decided On : 26-05-2026
| Table of Content |
|---|
| 1. procedural background and factual history of the arbitral dispute. (Para 1 , 2 , 3 , 4 , 5 , 6 , 7 , 8 , 9 , 10 , 11 , 12 , 13 , 14 , 15 , 16 , 17 , 18) |
| 2. determination of reasonable time for contractual performance when the contract is silent. (Para 19 , 20 , 21 , 22 , 23 , 24 , 25 , 36 , 37 , 38 , 39 , 51 , 52 , 53 , 54 , 55 , 56 , 57 , 58 , 59 , 60 , 61) |
| 3. arbitral tribunal's discretionary power in fixing pendente lite interest and costs. (Para 26 , 27 , 28 , 40 , 41 , 62 , 63 , 64 , 65 , 66 , 67 , 68 , 69 , 70 , 71) |
| 4. requirement of proving actual loss before awarding liquidated damages under section 74. (Para 29 , 30 , 31 , 32 , 33 , 34 , 42 , 43 , 44 , 45 , 46 , 72 , 73 , 74 , 75 , 76 , 77 , 78 , 79 , 80 , 81 , 82 , 83 , 84 , 85 , 86) |
| 5. minimal judicial interference in arbitral awards under section 34 of the arbitration act. (Para 47 , 48 , 49 , 50 , 87 , 88) |
JUDGMENT :
1. These are cross petitions filed under section 34 of the Arbitration and Conciliation Act, 1996 (“the Act”) seeking to challenge the Arbitral Award dated 16.11.2021 (“impugned Award”)-majority view, passed by the learned Arbitral Tribunal (“AT”), in the matter of Arbitration between M/s Atlanta Infra Assets ltd. v. National Highway Authority of India.
2. Both the parties have preferred their respective petitions to challenge the impugned Award, to the extent they are aggrieved by it.
3. Atlanta Infra Assets Limited (“Atlanta”) was the Claimant in the Arbitral proceedings and National Highway Authority of India (“NHAI”) was the respondent therein.
4. Atlanta and NHAI, both have approached this Court against the impugned Award by way of filing O.M.P. (COMM) 152/2022 and O.M.P. (COMM) 243/2022 respectively.
FACTUAL BACKGROUND
5. NHAI, is a statutory body established under Section 3 of the National Highways Authority of India Act, 1988, and operating under the aegis of the Ministry of Road Transport & Highways, responsible for development, maintenance and management of national highways.
6. NHAI invited bids vide letter No. NHAI/BOT/NH-24035/42/2003 dated 09.06.2004 for the award of several projects including “Improvement, Operation and Maintenance including Strengthening and Widening of existing 2 lane road to 4 lane dual carriageway from Km.9.200 to Km.50.000 of NH-6 (Nagpur - Kondhali Section) in the State of Maharashtra on Build Operate and Transfer (BOT)” (“Project”).
7. The bid submitted by a consortium of M/s Atlanta Ltd. (Lead technical member) and SREI Infrastructure Finance Ltd. (Lead financial member) was accepted vide a letter of award dated 22.09.2005.
8. The tender document contemplated setting up of a special purpose vehicle (“SPV”) to execute and implement the project and hence a SPV namely, Balaji Tollways Ltd. was incorporated. Subsequently, the name of the SPV was changed to Atlanta Infra Assets Limited., i.e. the petitioner in O.M.P. (COMM) 152/2022 and respondent in O.M.P. (COMM) 243/2022.
9. Thereafter, a concession agreement (“CA”) dated 09.12.2005 was executed between the SPV and NHAI for twenty years.
10. Disputes arose between parties during the execution of works till the issuance of provisional commercial certificate (“PCC”) dated 22.09.2011 by the Independent consultant (“IC”) namely, M/s Aarvee Associates, Hyderabad. With respect to these disputes concerning breaches before 22.09.2011, the respondent invoked Arbitration mechanism under Clause No. 39.2 of the CA.
11. The arbitral proceedings with respect to pre-PCC disputes culminated in Atlanta’s partial claim being allowed vide arbitral Award dated 29.09.2016, passed by the learned AT comprising of Mr Justice (Retd.) D P Wadhwa, Mr. Justice (Retd.) V N Khare, Mr. G G Shivdasani.
12. As the works under the Project could not be completed, NHAI and Atlanta entered into a supplementary agreement (“SA”) dated 22.09.2011, to complete the remaining work within 120 days of land being made available.
13. Several disputes arose between the parties post-PCC i.e., after 22.09.2011, wh
PSA Sical Terminals (P) Ltd. v. V.O. Chidambaranar Port Trust, Tuticorin & Ors.
Ssangyong Engg. & Construction Co. Ltd. v. NHAI
Indian Hume Pipe Co. Ltd. v. State of Rajasthan
Hungerford Investment Trust Ltd. v. Haridas Mundhra
Consolidated Construction Consortium Ltd. v. Software Technology Parks of India
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.