IN THE HIGH COURT OF KERALA AT ERNAKULAM
ZIYAD RAHMAN A.A., J.
The Army Welfare Housing Organisation (Awho) Represented By Its Authorised Signatory - Appellant
Vs.
Union Of India - Respondent
WP(C) No. 6169 of 2026
Decided On : 20-02-2026
| Table of Content |
|---|
| 1. overview of writ petitions filed by awho (Para 1) |
| 2. challenge to jurisdiction of k-rera orders (Para 2 , 3) |
| 3. counterarguments regarding jurisdiction and interim orders (Para 4 , 5) |
| 4. court's review of authority decisions (Para 6 , 7 , 8) |
| 5. necessity of registration for ongoing projects under rera (Para 9 , 10) |
| 6. establishment of jurisdiction based on occupancy certificate issuance (Para 11) |
| 7. rights of allottees and registration requirement under the act (Para 12) |
| 8. dismissal of writ petitions due to availability of alternate remedy (Para 13) |
JUDGMENT :
ZIYAD RAHMAN A.A., J.
[WP(C) Nos.6169/2026, 5821/2026, 5846/2026, 6003/2026, 6069/2026, 6103/2026, 6121/2026, 6129/2026]
All these writ petitions were filed by the Army Welfare Housing Organisation (hereinafter referred to as the “AWHO”) challenging the various orders passed by the adjudicating officer of K-RERA in various complaints submitted by the occupants of the apartments constructed by the petitioners. All those orders are produced as Ext.P7 in these writ petitions.
2. Sri.M.Ramesh Chander, the learned Senior counsel appearing for the petitioners mainly challenges Ext.P7 orders by way of writ petition, instead of invoking the statutory remedy contemplated under Section 43 (5) of the Real Estate (Regulation and Development) Act (hereinafter referred to as the Act) on the ground that, the K-RERA does not have the jurisdiction to entertain the complaints in which these impugned orders are passed. The reason, according to the learned Senior Counsel, that makes the complaint without any jurisdiction is that, the project, which is the subject matter in these writ petitions, is not liable to be registered under the provisions of the Act, in view of the fact that, the project was not an ongoing project.
3. This contention was raised, mainly on the ground that, the occupancy certificate for the building completion was received on 21.02.2018 and Kerala Real Estate (Regulation and Development) Rules, 2018 came into force only on 14.06.2018 and thus, it was not possible for any real estate project to get registration before the date on which the Rules came into force. Therefore, it was pointed out that, it was not an ongoing project which requires registration as contemplated under proviso to Section 3 (1) of the Kerala Real Estate (Regulation and Development) Act.
4. However, the contention raised by the petitioners was opposed by Adv.K. Shaj, the learned Counsel appearing for the party respondents in these cases, Sri.Saji Thomas, the 2nd respondent in W.P(C) No.5846/2026, who appeared in person, Adv.P.Anirudhan, learned Central Government Counsel appearing for the 1st respondent in W.P(C) No.6103/2026 and Adv.Mahadev M.J., learned Central Government Counsel appearing for the 1st respondent in the remaining writ petitions.
5. It was pointed out by the said respondents that, the question regarding the jurisdiction was considered by the RERA and passed an interim order on 03.10.2024, rejecting the very same contentions raised by the petitioners herein. It was held that, since the occupancy certificate was obtained after the Act came into force on 01.05.2017, it is required to be registered and therefore, a direction was issued to the petitioners herein, to register the project within thirty days from the date of receipt of the said order.
6. The sequence of events after issuance of the said order indicates that, the complaints in which the order dated 03.10.2024 was passed, were happened to be rejected by the K-RERA taking note of the judgment rendered by this Court in W.P(C) No.40178/2023, a copy of which is produced as Ext.P2, wherein, this Court directed the demolition of two towers in the apartment complex that form part of the project in question, by directing the District Collector to constitute a committee to do the same. The said judgment was rendered by this Court, taking note of the serious structural defects that were found in the said towers and also taking in
IFCI Infrastructure Development Limited v. Kerala Real Estate Regulatory Authority
All real estate projects with occupancy certificates issued after 01.05.2017 are considered ongoing and shall be registered under the Real Estate (Regulation and Development) Act, entitling allottees....
The court affirmed that ongoing real estate projects must be registered under RERA to protect allottee interests, regardless of title transfer.
The Real Estate (Regulation and Development) Act mandates registration for ongoing projects, where completion certificates are absent, emphasizing consumer protection in real estate transactions.
Determination of K-RERA's jurisdiction over registration requirements under the Real Estate Act.
The High Court upheld that jurisdiction for RERA to adjudicate complaints exists even if the promoter lacks registration, emphasizing the rights of aggrieved parties under the Act.
The distinction between occupancy certificate and completion certificate is crucial in determining the applicability of the Real Estate (Regulation and Development) Act, 2016, and the requirement for....
Section 35 deals with powers of authority to call for information and conduct investigation.
The court clarified that the Completion Certificate's issuance date is crucial in determining a project's ongoing status under RERA, emphasizing the conjunctive reading of statutory provisions.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.