SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Mad) 2132

IN THE HIGH COURT OF JUDICATURE AT MADRAS
P.T. Asha, J.
M. Selvaraj, S/o. Marappagounder - Petitioner
Versus
The State Represented By., Principles Secretary to Government, Department of Energy – Respondent
WP No. 2438 of 2026 and WMP Nos.2685 and 2687 of 2026
Decided On : 24-02-2026

Advocates Appeared:
For the Petitioner: Mr.N.U.Pressanna
For the Respondent:Mr.P.S.Raman, Advocate General, Assisted by Mr.D.R.Arun Kumar

Statutory authorities can erect high-tension electricity towers on private land without prior consent, provided they ensure minimal damage and compensate affected parties, in adherence to public interest principles.

Headnote:(A) Electricity Act, 2003 - Sections 10, 15, 16, 68, 164 - Indian Telegraph Act, 1885 - Electricity transmission rights on private land - Petitioners, joint owners of agricultural land, opposed high tension towers without due process and notice, claiming hardship in agriculture - Respondents argued statutory rights to erect towers, citing public interest and no requirement for prior owner permission - Court reiterated that such actions do not amount to land acquisition and compensation may be claimed per statutory provisions. (Paras 3, 11, 12, 13)

(B) Duty of public authority - Public interest versus private rights - The authority must follow procedures under the Act but does have powers to proceed without consent in public interest, ensuring damages are compensated. (Paras 8, 9, 10)

Facts of the case:
The petitioners claimed ownership of ancestral agricultural land affected by the erection of high tension electricity towers, which they argued would obstruct their farming activities. They alleged no prior notice was given before construction began, impacting their livelihoods and prior loans.

Findings of Court:
The court found that the respondents acted within their statutory powers and did not violate any due process, emphasizing the public interest in electricity transmission. As such, the petitioners were reminded of their right to claim compensation for any actual damages incurred.

Issues: The court addressed whether the respondents required prior permission to erect towers and whether the erection impinges on the petitioners' property rights or agricultural activities.

Ratio Decidendi: The court ruled that the respondents possess statutory authority under the Electricity Act and the Indian Telegraph Act to place towers without prior owner consent, provided they minimize damage and offer compensation.

Result: Writ petition dismissed.

Table of Content
1. petitioners' claims of land ownership and hardship due to tower erection. (Para 1 , 2)
2. court's legal analysis on statutory authority and rights. (Para 4 , 5 , 6 , 7 , 8)
3. legal interpretations of the electricity act and telegraph act. (Para 9 , 10 , 11 , 12)
4. petition dismissed; petitioners can seek compensation. (Para 13)

ORDER :

P.T. Asha, J.

The above writ petition is filed for a mandamus directing the second respondent to consider the petitioners’ objections dated 18.09.2025 and consequently to forbear the respondents 1 to 4 from erecting High Tension Electricity Tower in the petitioners’ agricultural land situated in Survey Field No.573, in patta No.1198, Emmampatti Village, Nambiyur Taluk, Erode District.

2.The petitioners would submit that the lands in question are their ancestral properties and the petitioners who are brothers are joint owners of the said land and they have been cultivating crops thereon and they have been in continuous possession of the same. Their livelihood is dependant on these lands. In the year 1981, two high tension electric towers were erected in their lands by the respondents’ board for carrying 250 KW of power and the cable is passing right in the middle of the land from East to West. This has caused excess hardship to the petitioner for cultivating crops and in carrying out their agricultural activities and since the overhead lines are running through their land, their agricultural activities are restricted.

2.1.While so, without any prior notice, the respondents board officials unauthorisedly entered their lands and started measuring it and when questions were raised, they were informed that such measurements were part of the process of constructing a new 110 KW high tension electricity tower and line once again through their property. The petitioners would submit that the construction of these towers would ring a death knell to their agricultural operations and they would be forced to stop their agricultural activities and if their agricultural activities are stopped, they would be declared as defaulters as they have taken loans from banks to carry on their agricultural operations.

2.2.The petitioners would submit that to add to their hardship, two acres had been acquired by the Government for the purpose of establishing Athikadavu-Avinashi Water Supply Project and it was only the remaining lands that is in the enjoyment of the petitioners. The petitioners would further submit that as per the original plan, the tower was not intended to pass through their land, but only through the government lands that is adjacent to their property and it is well open to the respondent to stick to the original plan. Further, the respondents board had not followed due process by issuing proper notice prior to approving or commencing the project. If they had issued notice, the petitioner would have submitted their objections. Therefore, the action of the respondents board is arbitrary.

2.3.The petitioners had therefore, made an objection by way of representation dated 13.08.2025 to the second respondent. Till date, there is no response for the same and the respondents are continuing with their work to erect the high tension towers as per the schedule. This prompted the petitioners to sent yet another objection on 18.09.2025 to the fourth respondent. Despite receiving the objections / representation, the fourth respondent did not respond to the same. Therefore, the petitioner is constrained to approach this Court. 3.The fourth respondent has filed a counter affidavit inter alia contending that the Government of Tamil Nadu had permitted the fourth respondent as per Section 68 and 164 of the Electricity Act, 2003, for executing 11 schemes throughout the State and one of the schemes is the erection of 110 KV DC line on DC tower for making LILO of the existing Karuvallur – Nambiyur feeder at Malayampalayam 110/33-11 kV Substation. They would contend that they are the deemed transmission lincensee

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top