HIGH COURT OF JUDICATURE FOR RAJASTHAN, BENCH AT JAIPUR
SANJEEV PRAKASH SHARMA, ACJ., BIPIN GUPTA, J.
M/s Shalimar Electrical, Through Satatwdhari Shri Satynarayan, S/o. Late Shri Ramchandra Ajmera - Appellant
Versus
M/s Kanchan India Limited, Through Managing Director – Respondent
D.B. Civil First Appeal No. 318 of 2020
Decided On : 21-05-2026
| Table of Content |
|---|
| 1. summary of facts and trial court findings regarding payment dispute. (Para 1 , 2 , 3) |
| 2. appellant's arguments regarding the commencement date for interest calculation. (Para 4 , 5) |
| 3. respondent's counterarguments on contractual disputes and interest discretion. (Para 6) |
| 4. doctrine of laches: courts may deny pre-notice interest for periods of claimant inactivity. (Para 7 , 8 , 9 , 10 , 11 , 12 , 13 , 14 , 15 , 16) |
JUDGMENT :
Bipin Gupta, J.
1. The present Civil First Appeal has been preferred by the plaintiff-appellant assailing the judgment dated 23.10.2019, passed by learned Commercial Court, Ajmer, in Civil Suit No. 189/2018 (124/2014) CIS No. 123/2018, whereby the suit instituted by the plaintiff-appellant for recovery of amount has been partly decreed in its favour.
2. The controversy, in a narrow compass, is that a suit came to be filed by the plaintiff-appellant against the defendant- respondent for recovery of amount to the tune of Rs.10,24,017/-, contending therein that on 18.03.2008, the plaintiff-appellant, who was a dealer of M/s. Schneider Electric India Pvt. Ltd., received a purchase order from the defendant-respondent for supply of electric switchgear worth Rs. 60,43,356/-. The supplies were effected from 22.04.2008 till 19.05.2008. However, the defendant-respondent did not take delivery of the goods and, therefore, the plaintiff-appellant was compelled to store the goods at its premises/godown. Upon being asked the reason for not taking delivery of the goods, the defendant-respondent replied that the requirements had changed and, therefore, a fresh purchase order would be placed according to the new requirements.
2.1 On 13.08.2008, a fresh purchase order was issued for material amounting to Rs.44,51,000/-. In compliance with the fresh purchase order, material worth Rs.44,00,000/- was supplied from 20.08.2008 to 10.12.2008. However, the defendant- respondent paid only an amount of Rs.40,00,000/-. Thus, a remaining amount of Rs. 4,00,000/- was due and payable.
2.2 The plaintiff-appellant, in his plaint, claimed that in its books of account, against the said purchase order, a principal amount along with agreed interest amounting to Rs.8,30,774/- was outstanding. It was also pleaded that, against the purchase order dated 18.03.2008, since the material was not taken by the defendant-respondent, the plaintiff-appellant had to pay a penalty to M/s. Schneider Electric India Pvt. Ltd., amounting to Rs.1,93,243/-. Thus, a suit was filed for recovery of total amount of Rs.10,24,017/-.
2.3 The defendant-respondent filed a detailed written statement admitting the fact of the purchase order for supply of switchgear worth Rs.60,43,356/-. It was further contended that the material supplied pursuant to the subsequent purchase order was not of standard quality and, therefore, a debit note of Rs.4,00,000/- was issued to the plaintiff-appellant. It was also contended that the penalty allegedly paid by the plaintiff-appellant to M/s. Schneider Electric India Pvt. Ltd., amounting to Rs.1,93,243/-, could not be recovered from the defendant-appellant, in absence of any privity of contract. On the aforesaid grounds, dismissal of the suit was prayed for by the defendant-respondent.
3. On the basis of the pleadings of the parties, the learned Commercial Court framed as many as eleven issues which reads as under:


3.1 In support of its pleadings, the plaintiff-appellant examined two witnesses and produced various documents in evidence. On the other hand, the defendant-respondent examined only one witness in support of his case.
3.2 Issue Nos.1 and 3 were decided in favour of the plaintiff. Issue No.2 was decided against the plaintiff. Issue No. 4 was partly allowed in favour of the plaintiff wherein the it was held entitled to receive the outstanding amount of Rs.4,00,000/- along with agreed interest @ 24% from the date of service of notice i.e. 01.12.2011. Issue No. 5 was decided against defendant. Issue No. 6 was partly allowed i
The main legal point established in the judgment is that the Interest on Delayed Payment to Small Scale and Ancillary Industrial Undertakings Act, 1993 does not apply to transactions prior to its enf....
The court has discretion to award pendente lite and post decree interest even in the absence of a contractual provision, considering the conduct of the parties involved.
Court upheld contractual interest of 18% from pre-suit period while awarding 9% future interest post-decree, reflecting equitable considerations of a commercial transaction.
Under the Indian Law neither consideration nor an agreement would be necessary to constitute waiver. Therefore, a written agreement discharging liability is not a mandate of law.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.