SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Online)(Tel) 41913

IN THE HIGH COURT FOR THE STATE OF TELANGANA AT HYDERABAD
Abhinand Kumar Shavili, Vakiti Ramakrishna Reddy, JJ
Md Ameeraap Khan – Appellant
Versus
Competent Authority Cum RDO – Respondent
Civil Revision Petition No.341 of 2019



Advocates:
For the Appellants/Petitioners: Sri J. Suresh Babu
For the Respondents: Sri Madishetty Ramu

The period of limitation for challenging an arbitral award under Section 34(3) of the Arbitration and Conciliation Act, 1996, commences only upon the delivery of a signed copy of the award to the party himself, as mandated by Section 31(5), and not to the counsel.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 31(5) and 34(3) - Limitation - Commencement of limitation period for challenging arbitral award - Period of limitation under Section 34(3) commences only upon delivery of a signed copy of the arbitral award to the party himself, not merely to the advocate - Service upon counsel is not a substitute for the mandatory requirement of delivery to the party.

(B) Limitation - Condonation of delay - The power conferred under Section 5 of the Limitation Act, 1963, to condone delay must be exercised in a justice-oriented manner - Minor, bonafide delays that fall within the permissible grace period should be condoned to ensure that matters are decided on merits.

Facts of the case:
The petitioners sought the acquisition of compensation for land acquired for highway widening, which was marginally enhanced by the Arbitrator. The petitioners alleged that they did not receive a signed copy of the award until 04.05.2016. Consequently, they filed a petition under Section 34 of the Act with a delay of 27 days, which was rejected by the Trial Court on the ground that the award had been dispatched to their counsel in May 2015. Findings of the Court: The Court held that the service on counsel did not satisfy Section 31(5) of the Act. Limitation only began when the signed award was delivered to the petitioners on 04.05.2016. The delay of 27 days was within the permitted grace period and was sufficiently explained, necessitating a justice-oriented approach.

Issues: Whether limitation under Section 34(3) commences from service upon the party or the advocate, and whether the 27-day delay should be condoned.

Ratio Decidendi: The provision of Section 31(5) is mandatory and substantive; the period of limitation under Section 34(3) begins only upon service of the signed award to the party personally. Technicalities should not prevail over substantial justice when a delay is marginal and bonafide.

Result: Civil Revision Petition allowed; the order of the Trial Court set aside; delay condoned.

Table of Content
1. introduction and background facts of the delay in filing section 34 application. (Para 1 , 2 , 3)
2. rival contentions regarding service of award and scope of limitation. (Para 4 , 5 , 6)
3. judicial precedents establishing that limitation runs from personal service on the party. (Para 7 , 8 , 9 , 10 , 11 , 12 , 13)
4. analysis confirming section 31(5) requires direct delivery of signed copy to the party. (Para 14 , 15 , 16 , 17 , 18 , 19 , 20 , 21 , 22 , 23 , 24 , 25 , 26)
5. discretion to condone delay when substantial justice requires it. (Para 27 , 28 , 29 , 30 , 31 , 32 , 33 , 34 , 35 , 36 , 37)
6. summary of findings and final order allowing the petition. (Para 38 , 39 , 40 , 41)

GIST :

HEAD NOTE :

Cases referred :

1. (2011) 4 SCC 616

2. (2012) 9 SCC 496

3. (2011) 4 SCC 616

4. (2005) 4 Supreme Court Cases 239

5. (2021) 7 Supreme Court Cases 657

6. AIR 2015 Supreme Court 3411

7. (2012) 6 SCC 384

8. AIR 2015 SC 3411

9. (2001) 8 SCC 470

10. (2019) 2 SCC 455

11. (2020) 10 SCC 654

12. (1987) 2 SCC 107

13. 2023 LiveLaw (SC) 572

ORDER: (Per Hon’ble Sri Justice Vakiti Ramakrishna Reddy)

1. This Civil Revision Petition is preferred by the petitioners aggrieved by the order dated 05.02.2018 (hereinafter referred to as the “Impugned Order”) passed by the learned Principal District Judge, Nalgonda, in I.A. No.1146 of 2016 in O.P.S.R. No.3456 of 2016. By the Impugned Order, the Trial Court dismissed the petitioners’ application filed under Section 34(3) of the Arbitration and Conciliation Act, 1996 (in short “the Act”), wherein they had sought condonation of delay of twenty-seven (27) days in filing a petition under Section 34 of the Act, for setting aside the arbitral award passed under the National Highways Act, 1956.

2. This case raises questions concerning the commencement of limitation under Section 34(3) of the Act, the scope of delivery of signed copy of the award under Section 31(5) of the Act, and the approach to be adopted by Courts while considering applications for condonation of delay in challenging arbitral awards.

I. BRIEF FACTS

3. The factual backdrop to the present revision is as follows:

(a) The petitioners’ agricultural lands were acquired for widening of National Highway No.65 (earlier No.9) at Suryapet.

(b) Pursuant thereto, an award dated 03.06.2010 in Case No.C/3125/2009 was passed, awarding compensation which, according to the petitioners, was grossly inadequate.

(c) Being dissatisfied, the petitioners sought reference, whereupon the Arbitrator (respondent No.3) passed Award No. G2/6452/2010 dated 27.04.2015, marginally enhancing the compensation.

(d) The petitioners contend that despite the award having been passed in April 2015, they were never served a signed copy until 04.05.2016.

(e) On receipt of the signed copy, the petitioners filed O.P.S.R. No.3456 of 2016 under Section 34 of the Act, on 30.08.2016, accompanied by I.A. No.1146 of 2016 for condonation of 27 days’ delay in filing the petition under Section 34 of the Act.

(f) The Trial Court, however, dismissed the condonation application, holding that since the award had been dispatched to the petitioners’ advocate in May 2015, limitation commenced from that date. On that basis and by presumption of service, the Trial Court concluded that the petition was hopelessly time-barred.

(g) Aggrieved by the impugned order passed by the Trial Court, the petitioners have approached this Court in the present Revision.

II. SUBMISSIONS OF THE PARTIES:

a) Submissions on behalf of the petitioners:

4. The following arguments have been advanced on behalf of the petitioners:

i) The petitioners emphasize that limitation under Section 34(3) of the Act is triggered only upon delivery of a signed copy of the Award to the party himself, as mandated by Section 31(5) of the Act. Further, service upon counsel does not satisfy this statutory requirement.

ii) The petitioners assert that they received the signed copy of the Award only on 04.05.2016. Thus, the peti

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top