(B) Burden of Proof - The party asserting a claim must prove the facts alleged - The Court emphasized that the burden lies on the party making the claim to establish their case on a balance of probabilities. (Paras 30, 31, 161)
(C) Quantum Meruit - The Court recognized that a claim for quantum meruit can be established if the work was done lawfully for the benefit of another and not intended to be gratuitous. (Paras 56, 252)
Facts of the case:
The Plaintiffs provided construction services to the Defendant, who terminated the contract citing delays and overclaims. The Plaintiffs claimed outstanding payments, while the Defendant counterclaimed for overpayments and damages. (Paras 2, 4, 26)
Findings of Court:
The Court found that the Plaintiffs had partially completed the works and were entitled to payment based on the value of the work done, but the counterclaims for overpayment and damages were dismissed. (Paras 81, 140, 252)
Issues: The main issues included whether the Defendant was liable to pay for the outstanding sums claimed by the Plaintiffs and whether the Defendant's counterclaims were valid. (Paras 26, 111)
Ratio Decidendi: The Court ruled that the Plaintiffs had established a contractual relationship through accepted quotations and invoices, and the claims were to be assessed based on the actual work completed. The counterclaims were dismissed due to lack of evidence linking the alleged damages to the Plaintiffs' actions. (Paras 252, 272)
Result: The Plaintiffs' claims were partly allowed, and the Defendant's counterclaims were dismissed. (Paras 81, 140, 272)
JUDGMENT
Introduction
[1] When parties enter into dealings, it is always best that proper documentation is drawn up and kept to regulate their transactions/dealings. If they are not and parties deal in a very informal manner without proper documentation, issues will then arise which may inevitably lead to Court proceedings. This is one such situation/case.
[2] The three separate Plaintiffs abovenamed and the common Defendant have had business dealings whereby the Defendant had engaged the various Plaintiffs to provide their respective services on a piece of land and hereditament owned by the Defendant known as Lot No PT13, Mukim 1, Daerah Seberang Perai Tengah, Negeri Pulau Pinang held under Geran No H.S.(D) 43162 together with an existing warehouse and office erected thereon bearing address No 972, Solok Perusahaan 3, Kawasan Perusahaan Perai, 13600 Perai (hereinafter referred to as "the site"). Their services were ultimately terminated on 4 April 2022. Disputes have now arisen which led the Plaintiffs to commence these three separate proceedings seeking payments from the Defendant for works done on the site.
[3] The above three suits originated in the Subordinate Courts vide PA- A52NCC-59-08/2022; PA-A52NCC-97-11/2022 and PA-A52NCC- 98-11/2022 respectively. However, in light of counterclaims by the Defendant being in excess of RM1 million, the High Court had subsequently vide Originating Summons No. PA-24NCVC-151- 02/2023 ordered these suits to be transferred to the High Court and be consolidated and heard together.
[4] The Court will hereinbelow set out the salient background facts of each case, the parties' respective contentions and the Court 's analysis with a view of determining if the parties have discharged the burden of proving their respective claims/counterclaims
[5] Although consolidated and heard together, for the sake of convenience and clarity, the Court will deal with each of these three cases separately.
Suit No. Pa-22NCC-32-05/2023 (Hereinafter Referred To As "Suit 32")
Salient Background Facts
[6] The salient background facts are derived from the pleadings and the common agreed facts as well as the chronology of events and are summarised as follows.
[7] The Plaintiff (hereinafter referred to as "QTMY") is in the business of supply and installation of building materials and conducting electrical and machinery works.
[8] The Defendant (hereinafter referred to as "Nbrand") is the registered owner of the site where works were carried out.
[9] Sometime in early 2021, Nbrand approached the representative of QTMY, Mr Goh Tiong Hum (hereinafter referred to as "Kenny Goh") to procure QTMY's services for the work of construction and refurbishment at the site (hereinafter referred to as "construction and refurbishment works").
[10] QTMY pleads that they issued a total of 8 quotations to Nbrand between 20 March 2021 and 23 March 2022 for various services to be rendered. However, Nbrand pleads and contends that they only received and accepted 5 quotations. They deny receiving or verbally accepting the other 3 quotations.
[11] However, it is not disputed that Nbrand then made several advance payments totalling RM298,000.00 to QTMY for the construction and refurbishment works as follows:
[12] QTMY pleads that pending the completion of their services, the Government had imposed multiple Movement Control Orders (MCO) to curb the outbreak of COVID-19. Nevertheless, QTMY immediately continued to rush the completion of their services at the site once they were allowed to operate by MITI and/ or the MCO was uplifted.
[13] Prior to the termination of QTMY's services on 4 April 2022, QTMY pleads that they have completed part of their services at the site amounting to a sum of RM346,810.80 wherein QTMY has issued the following invoices for the previous 8 quotations:
[14] Around the end of March 2022, Nbrand communicated its intention to terminate the services of QTMY and their workers and agents were also denied access to