COURT OF APPEAL PUTRAJAYA
SAYCON CONSTRUCTION SDN BHD – Appellant
Versus
ROSADO TRADELINE SDN BHD – Respondent
| Table of Content |
|---|
| 1. contractor-plaintiff's claims against subcontractor-defendant. (Para 1) |
| 2. negligence in performance of contract. (Para 2 , 3 , 5 , 6) |
| 3. court's confirmation of delay due to subcontractor's negligence. (Para 12 , 13 , 18) |
| 4. arguments regarding damages and payment under threat. (Para 20 , 25) |
| 5. burden of proof rests on the claimant for damages. (Para 30 , 31 , 32 , 35 , 36) |
| 6. court's interpretation of evidence supporting claims. (Para 44) |
[1] This is the appellant/defendant's appeal against the decision of the High Court at Penang which entered judgment for the respondent/plaintiff. For ease of reference, in this judgment, parties will be referred to as they were in the High Court.
Background
[2] The plaintiff was appointed as the main contractor by Ann Joo Integrated Steel Sdn Bhd ("the employer") for the construction of Ore Bunker and Hot Stove at Prai Industrial Park ("the project") at an accepted tender price of RM3,000,000.00. The liquidated and ascertained damages payable by the plaintiff to the employer in the event of delay in the completion of the project was RM6,000.00 per day.
[3] By a letter dated 25 June 2008, the plaintiff appointed the defendant as its s
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.