COURT OF APPEAL PUTRAJAYA
KINU SDN BHD – Appellant
Versus
KERAJAAN MALAYSIA (JABATAN KERJA RAYA MALAYSIA) – Respondent
[Civil Appeal No: W-01(C)(A)-523-08/2024]
The grounds of appeal are based on the interpretation of the statutory obligation of the principal under the relevant legislation, specifically focusing on whether the principal's recognition or acknowledgment of the subcontractor affects their obligation to make direct payment. The appellant contends that the obligation to pay arises solely from the existence of a valid adjudication decision and evidence that funds are "due or payable" from the principal to the main contractor at the time of the request (!) (!) .
Furthermore, it is argued that the absence of written recognition or consent by the principal does not negate their statutory obligation to make payment, as the framework is designed to facilitate prompt payments regardless of contractual recognition. The appellant emphasizes that the factual determination of whether money is "due or payable" is central, and that the burden of proof rests on the principal to demonstrate otherwise. The failure to produce sufficient evidence to establish that no such funds are owing forms the basis for the appeal (!) (!) .
In addition, the appellant asserts that the court's interpretation aligns with the legislative intent to ensure timely and effective payment mechanisms within the construction industry chain, and that the obligation to pay is triggered by the adjudication outcome and the existence of credible evidence, not by the principal's recognition or approval of the subcontractor's appointment (!) .
Overall, the appeal challenges the notion that the principal's recognition or consent is a prerequisite for their statutory obligation to make direct payment, emphasizing that the key determinants are the adjudication decision and the evidence of funds "due or payable" at the relevant time (!) (!) .
[1] This is an appeal from a decision of the High Court that had dismissed a s 30 of the Construction Industry Payment and Adjudication Act 2012 ("CIPAA") application by the successful claimant (subcontractor) in an adjudication decision for an order to compel the principal (employer) to make direct payment to it on account of money "due or payable" by the principal to the unsuccessful respondent in the adjudication who is the main contractor.
[2] The issues raised in this appeal were whether retention sum retained by the principal from certified amounts due to the main contractor was money "due or payable" to the main contractor from the principal and whether on the balance of probabilities the subcontractor had proved that there was money "due or payable" from the principal to the main contractor when the request for payment was served on the principal under s 30(1) of the CIPAA.
[3] It was also argued by the principal who is the Government of Malaysia ("GOM") and more particularly Jabatan Kerja Raya ("JKR") that since it did not recognise nor consent to the main contractor appointing the subcontractor, it was not bound to make any payments under s 30 of the CIPAA.
In the High Court Below
[4] The subcontractor KSB was the plaintiff in the High Court below and the appellant here. The GOM/JKR was the defendant below and the respondent here.
[5] The High Court held that the liability of the principal to pay if there is a debt due or payable from it to the main contractor is irrespective of whether the subcontractor is recognised or approved by the principal as this is not a requirement under s 30 of the CIPAA.
[6] The High Court was satisfied that there was no money "due or payable" from the principal to the main contractor, the losing party in the adjudication as the last Interim Payment Certificate ("IPC") in IPC No 84 showed a negative sum of RM1,788,581.24 as the recommended amount for payment by the GOM to NSB, the main contractor.
[7] The High Court had further held that there was an issue as to whether there was a debt due or payable from the principal to the main contractor in that there was a dispute as to whether the percentage of works completed at the point of termination of the contract by the principal of the main contractor was physical or financial completion. The High Court held that such a dispute was essentially to be resolved between JKR and its main contractor NSB.
[8] The High Court had thus dismissed the plaintiff's/subcontractor's application under s 30 of the CIPAA. The plaintiff had appealed to the Court of Appeal.
Before the Court of Appeal
[9] The plaintiff appealed to the Court of Appeal on the ground that the plaintiff had proved on the balance of probabilities that there was money "due or payable" from JKR to the main contractor NSB which money was more than enough to satisfy the adjudicated amount that the plaintiff had obtained and enforced against the main contractor.
[10] The plaintiff argued that the High Court had erred when it failed to consider that the Performance Guarantee sum carved out from the IPCs due from JKR to its main contractor to the sum of 5% of contract sum of the Project was money "payable" within the meaning of s 30(5) CIPAA.
[11] The plaintiff further contended that the difference between the progress of the works under the last IPC which was IPC No 84 dated 24 June 2022 and that stated as 99.86% in the Notice of Termination dated 14 July 2022, represented money due or payable from JKR to the main contractor and that this was not a matter that could only be resolved in a dispute between JKR and NSB but rather it was to be resolved based on the evidence adduced under a s 30 CIPAA application on the balance of probabilities.
Whether the Principal May Refuse Payment Under a s 30 CIPAA Application on Ground That It Had Not Given Its Written Consent to the Main Contractor Appointing the Subcontractor
[12] The principal had referred to the fact that its main contractor NSB had appoi
Aspen Glove Sdn Bhd v. Tialoc Malaysia Sdn Bhd
Foo Loke Ying & Anor v. Television Broadcasts Ltd & Ors
Krishnadas Achutan Nair & Ors v. Maniyam Samykano
Kasugi Prima Sdn Bhd v. Cobrain Holdings Sdn Bhd
Murni Environmental Engineering Sdn Bhd v. Eminent Ventures Sdn Bhd & Anor
HSL Ground Engineering Sdn Bhd v. Civil Tech Resources Sdn Bhd
Cubic Electronics Sdn Bhd v. Mars Telecommunications Sdn Bhd
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.