SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2010 MarsdenLR 2399

HIGH COURT MALAYA KUALA LUMPUR
LAFARGE CONCRETE (MALAYSIA) SDN BHD – Appellant
Versus
HASRAT USAHA SDN BHD & ANOR – Respondent
[Suit No: D10-22-1484-2005]



In contract disputes involving multiple parties, prior conduct and joint arrangements may establish liability despite strict adherence to written agreements.

Headnote:(A) Sale of Goods Act 1957 - Section 31 - Rules of the High Court 1980 - Order 35 rule 4(5)(c) - Liability in contract dispute between main contractor and subcontractor for unpaid concrete supply - Court found that the first Defendant is liable for payment as per the agreed terms - Doctrine of estoppel invoked against the first Defendant due to prior conduct of honoring payments for similar arrangements - Claim against the second Defendant dismissed. (Paras 26, 27)

(B) No case submission - Court emphasizes that a case should be tried in its entirety and that all evidence must be considered before rendering a decision - A submission of no case does not eliminate a party's right to cross-examine witnesses when evidence is adduced by others. (Paras 5, 26)

Facts of the case:
The Plaintiff, a concrete supplier, entered into an agreement with the first Defendant for the supply of concrete, with deliveries handled through the second Defendant, its subcontractor. The first Defendant failed to pay for specific unpaid invoices, while both Defendants contended that the other was liable.

Findings of Court:
The court ruled that the first Defendant has established liability to the Plaintiff due to the consistent payment behavior and the collaborative nature of the two Defendants in executing the project. The second Defendant was acting as the authorized agent of the first Defendant.

Issues: The court addressed the main question of liability between the two Defendants for the unpaid concrete supplied to the project. It questioned whether the first Defendant could submit a no case argument when it did not present evidence.

Ratio Decidendi: A clear mutual understanding regarding obligations was found between the parties, thus allowing the Plaintiff's substantial claim to prevail. The failure to contest documentation did not absolve inadequacy in payment fulfillment. The established agreement mandated payment from the first Defendant.

Result: The first Defendant ordered to pay Plaintiff RM607,134.37 with interest; claim against the second Defendant dismissed with costs.

Table of Content
1. disputes over liability for concrete payments. (Para 1 , 2 , 3)
2. rights to cross-examine and procedural implications. (Para 4 , 5 , 6 , 7 , 8)
3. plaintiff's entitlement to payment and evidence. (Para 9 , 10 , 11 , 12 , 13)
4. defendants' obligations and clarity of agreements. (Para 14 , 15 , 16 , 17)
5. evaluation of claims and evidence. (Para 18 , 19)
6. understanding the terms of the agreement. (Para 20 , 21 , 22 , 23 , 24 , 25 , 26)
Mary Lim Thiam Suan J:

Background Facts

1. The 1st Defendant was the main contractor in a project known as the "Proposed construction and completion of Light Rail Transit (LRT) Infrastructure Works and Boulevard Packages at Precinct 3 & 4 for the Putrajaya Core Island Development Packages LRT-BLVD 103 & 104" [the project]. The 2nd Defendant was its subcontractor. By letter dated 2 April 2002, the Plaintiff agreed to supply ready-mixed concrete to the 1st Defendant on the terms and conditions as set out in the letter [the said agreement]. The Plaintiff duly supplied the concrete to the project site. All the delivery orders, invoices and statements of accounts issued by the Plaintiff bore the stamp and signatures of the 2nd Defendant. All payments were made by the 1st Defendant save for the amounts which are now the subject of the instant claim. The Plaintiff claimed from both Defendants the outstanding amounts but both of them refused to pay, with each Defendant contending that the other was liable.

2. At the outset of the trial, it was agreed that the case be determined by the single issue of who then was liable to pay for the concrete sold and delivered, is it the 1st Defendant or the 2nd Defendant, or both. This question was relooked just before trial commenced and the parties agreed that the issue rightly should be which of the two Defendants is liable to pay the Plaintiff.

3. The Plaintiff called two witnesses and then closed its case, at which point the 1st Defendant submitted that there was no case for it to answer and elected not to call evidence. The 2nd Defendant on the other hand, chose to adduce evidence. Consequently, the question was having made that election, did the 1st Defendant still have a right to cross-examine the 2nd Defendant's witnesses. Whether by making such a submission, the 1st Defendant not only lost the right to call evidence but the right to participate further in the proceedings. After hearing counsel, I ruled that the 1st Defendant's right to cross-examine the 2nd Defendant's witnesses was preserved, subject to there being no indirect effect of adducing evidence. I gave my reasons for my ruling but in view of the significance of this related issue, I felt it best to set out my reasons in full.

Submission Of No Case By One Of Two Defendants

4. Order 35 rule 4(5)(c) of the Rules of the High 1980 provides for the order of speeches where there are several Defendants and where one of them opts to adduce evidence while the other proceeds to adduce evidence. It does not however, deal with the matter of the right to cross-examine witnesses in such circumstances. For this, one must bear in mind the significance of the election when a Defendant submits there is no case to answer, be it because the plaintiff has not established its case or that the burden of proof has not been discharged. This becomes trickier when there are several Defendants involved, each taking a strategic judgmental call in order to advance their diametrically opposing interests, each seeking to exculpate and establish blame on any other save on itself. The election must be made; otherwise an unsuccessful Defendant whose submission of no case to answer has been rejected by the Court may then call evidence. Generally, a Court should try cases in its entirety, taking all evidence and hearing all the parties before making a determination. In a situation where there are multiple Defendants, that would include the evidence to be offered by the Defendants who have opted to adduce evidence. Otherwise

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top