SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 MarsdenLR 2263

HIGH COURT MALAYA SHAH ALAM
X DIMENSION SDN BHD – Appellant
Versus
DATUK CHIANG HENG KIENG & ANOR – Respondent
[Civil Appeal No: BA-12BC-8-05/2024]



Petitioner Advocates:Edmund Bon Tai Soon,Khor Xiou Shan,Lee Yee Woei ,Respondent Advocate: Edmond Teh,Wong Kar Chun,Wong Yi Ying

The contracts involving design services are void when the provider lacks mandatory registration, preventing them from recovering fees, while clients can still claim damages for defects regardless of contract illegality.

Headnote:(A) Architects Act 1967 - Sections 27A and 27E - Contracts Act 1950 - Section 25 - Contractual obligations - The Defendant engaged as an interior designer was not registered under the Act, leading to the contracts being ruled void ab initio and the counterclaim dismissed - The Defendant's failure to rectify defects resulted in the Plaintiffs being entitled to special damages despite the contracts' illegality. (Paras 43, 44, 55)

(B) Legal obligations - The requirement for an interior designer to be registered is mandatory, and non-compliance renders contracts illegal. (Paras 30, 33, 37)

(C) Judicial appreciation - Judicial assessments must be based on the evidence presented, and total adoption of submissions without appreciation is insufficient. (Paras 26, 27)

Facts of the case:
The Plaintiffs entered into three contracts for renovations with the Defendant, who failed to complete the works satisfactorily, leading to claims for damages. (Paras 6-13)

Findings of Court:
The contracts entered into were declared illegal due to the Defendant's lack of registration, but the Plaintiffs were entitled to special damages for unrectified defects. (Paras 44, 56)

Issues: The key issues were the legality of the Defendant’s role as an unregistered designer, entitlement to counterclaims, and the right of the Plaintiffs to claim damages for defects. (Paras 28)

Ratio Decidendi: The contracts were void ab initio due to the Defendant's unregistered status as an interior designer, and the Plaintiffs, as the weaker party, are entitled to damages for rectifying defects caused by the Defendant's inadequate work. (Paras 43, 55)

Result: The Defendant's appeal is dismissed, and the Plaintiffs' claim for special damages granted.

Table of Content
1. engagement of defendant for renovation services (Para 3 , 4 , 5 , 6 , 7 , 8 , 9 , 10 , 11 , 12 , 13 , 14)
2. plaintiffs allege defects and illegality (Para 15 , 16 , 17)
3. defendant's position and claim for balance payment (Para 18 , 19 , 20 , 21 , 22 , 23 , 24)
4. sessions court findings reviewed (Para 25 , 26 , 27)
5. legality of contracts and registration necessity (Para 29 , 30 , 31 , 32 , 33 , 34 , 35 , 36 , 37 , 38 , 39 , 40 , 41 , 42 , 43)
6. contracts deemed void due to illegality (Para 44 , 45 , 46)
7. entitlement of plaintiffs to their claim despite illegality (Para 48 , 49 , 50 , 51 , 52 , 53 , 54 , 55 , 56)
8. conclusion and dismissal decisions (Para 57)
Sumathi Murugiah JC:

A. Introduction

[1] For ease of reference, parties will be referred to as they were in the Sessions Court. The Appellant was the Defendant, whereas the Respondent was the Plaintiffs.

[2] This appeal was filed by the Defendant against part of the decision of the Sessions Court dated 29 April 2024 in the Civil Suit No: BA-A52C-35- 10/2020.

B. Brief Background

[3] On 31 May 2018, the Plaintiffs had approached the Defendant for interior design and renovation services for a project located at No 30, Jalan DU 6/5, Ambrosia@Kinrara Residensi, Taman Damai, Utama, 47180 Puchong, Selangor Darul Ehsan (the Property).

[4] Defendant submitted a quotation along with the terms and conditions for interior design consultancy services for the Property through a letter dated 18 July 2018 (ID Contract). Plaintiffs, through the 1st Plaintiff, agreed to, accepted, and signed the ID Contract on 16 October 2018.

[5] In or around September 2018, the Defendant was requested to submit a quotation along with terms and conditions for construction works related to the extension of the Property. The Defendant submitted a revised quotation along with the terms and conditions for the construction works related to the extension of the Property through a letter dated 26 September 2018 (Extension Works Contract). Plaintiffs, through the 1st Plaintiff, agreed to, accepted, and signed the Extension Works Contract on 16 October 2018.

[6] In or around December 2018, The Defendant was requested to submit a quotation along with terms and conditions for interior fit-out works of the Property. The Defendant submitted a revised quotation along with the terms and conditions for the interior fit-out works of the Property through a letter dated 19 December 2018 (Interior Fit-Out Contract). Plaintiffs, through the 2nd Plaintiff, agreed to, accepted, and signed the Interior Fit-Out Contract on 20 December 2018.

[7] Altogether, the Defendant was engaged by the Plaintiffs to carry out 3 contracts (collectively known as "the project"):

i. ID Contract - contract sum of RM55,000.00

ii. Extension Works Contract - contract sum of RM520,000.00

iii. Interior Fit-Out Contract - contract sum of RM588,750.00

[8] However, the contract sum for the Extension Works Contract and the Interior Fit-Our Contract were subsequently reduced to RM416,160.00 and RM506,110.00 respectively as the scope of works were reduced in these contracts.

[9] Apart from these 3 contracts, the Defendant had also requested the Plaintiffs to pay an additional sum of RM42,000.00 for the Architect's and Engineer's services which included but not limited to the application for the procurement of CCC from the local authorities.

[10] Additionally, there were 10 variation order (VO) claims by the Defendant for this Project. The preliminary works were carried out by the Defendant on or around September 2018 and the understanding between parties was for the completion of the project to be before the Chinese New Year 2019 which was celebrated on 5 February 2019.

[11] The Defendant did not complete the project by 5 February 2019, however, the Plaintiffs had nevertheless moved in to the Property just before Chinese New Year 2019. The Defendant had resumed work at around end of February 2019. The extension works commenced on 26 February 2019 and was t

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top