SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 MarsdenLR 4106

HIGH COURT MALAYA KLANG
PERRESIA RESOURCES (M) SDN BHD – Appellant
Versus
PERSPEKTIF MASA SDN BHD & ANOTHER CASE – Respondent
[Civil Suit No: BL-22NCvC-21-06/2023 & BL-22NCVC-22-06/2023]



A party acting as an agent lacks standing to claim liquidated damages when the relevant agreements are superseded by a Deed, which determines rights and obligations contrary to the claims.

Headnote:(A) Contracts Act 1950 - Section 183 - Evidence Act 1950 - Section 58 - The Plaintiff, acting as a nominee for another party, lacked locus standi to sue the Defendant for liquidated damages due to late delivery of properties as the SPAs were superseded by a Deed of Settlement. The Deed established that the rights of the Plaintiff to claim damages were not retained, nor were they a rightful party under the agreements. (Paras 7, 11, 25)

(B) Laches - The Plaintiff’s delay in claiming the LAD was inordinate and unjustifiable as complaint was not made for over 12 years since the signing of the SPAs. The court emphasized that parties should not delay in asserting their rights. (Paras 23, 24)

(C) Exemptions Due To COVID-19 - The Plaintiff's claims for LAD failed to account for relevant time exemptions calculated under the applicable legislation due to the pandemic period. (Paras 20, 21)

Facts of the case:
The Plaintiff took legal action against the Defendant, a developer, for failure to deliver vacant possession of condominium units within the agreed period. The basis of the purchase was linked to a Deed of Settlement that discharged obligations due to debt settlement arrangements. The properties were transferred to the Plaintiff as a contra settlement and not through a standard sale. (Paras 1-5)

Findings of Court:
The court ruled that the Plaintiff had no standing to claim damages as they were acting merely as an agent for another party; the rights to claim for damages were extinguished by the Deed of Settlement, and the claim for LAD was barred by laches. (Paras 25)

Issues: The court addressed the Plaintiff's standing to sue, the applicability of the Deed of Settlement over the SPA, the acknowledgment of late delivery, the potential entitlement to LAD, and the impact of delays in filing claims. (Paras 6-9, 20-22)

Ratio Decidendi: The court clarified that parties must adhere to the terms of binding agreements and cannot claim damages against the intention expressed in legally executed Deeds. Laches and inordinate delays in asserting rights may bar claims despite prima facie entitlements. (Paras 25)

Result: Claims dismissed with costs, requiring the Plaintiff to pay RM25,000.00 to the Defendant in each suit.

Table of Content
1. background facts about property purchase and agreements. (Para 1 , 2 , 3 , 4 , 5)
2. argument on plaintiff's locus standi. (Para 6 , 7 , 8 , 9 , 10 , 11)
3. debate regarding the deed's exclusion of claims. (Para 12 , 13 , 14 , 15 , 16 , 17)
4. late delivery and calculation of damages. (Para 18 , 19 , 20 , 21)
5. claim barred by laches and delay. (Para 22 , 23 , 24)
JUDGMENT

Norliza Othman J:

[Full Trial]

A. Background Facts

[1] Suit No.: BL-22NCVC-21-06/2023 (known as Suit 21) and Suit No.: BL-22NCvC-22-06/2023 (known as Suit 22) will be decided together since both are tried together. The documents are common for both suits

The Plaintiff were purchasers of two (2) units of condominium under the D'Rapport Festa, Ampang ("Project") developed by the Defendant.

[2] Parties then entered into two (2) Sale and Purchase Agreement, both dated 22 February 2011 ("SPA") with the purchase price of RM1,060,200.00 and RM1,056,700.00 respectively ("Properties"). Plaintiff claims that the purchase price were paid by 3rd party consideration, which was the debt owed by the Defendant to one Juruukur Bahan FPPS Sdn Bhd ("FPS") to which a Deed of Settlement dated 29 August 2013 was entered between FPS and the Defendant ("Deed").

[3] The Defendant ought to have delivered the vacant possession of the properties on or by 21 February 2014 which is within 36 months from the date of the SPA as stated in cl 25(1) of the SPA. However, the Defendant only issued and/or delivered the vacant possession of the properties on 21 February 2023 ie 14 days after issuance of Notice of Delivery of Vacant Possession. Plaintiff then filed this suit claiming liquidated ascertained damages against the Defendant pertaining to the late delivery of the said properties.

[4] The Defendant's version is:

i. The Defendant is a developer of a plot of land ("Land"). By way of Letter of Appointment dated 7 April 2010, the Defendant appointed FPS as the Quantity Surveyor for the said project;

ii. FPS and the Defendant agreed to settle part of the remaining professional consultant fees owing to FPS for the project by way of contra properties. FPS agreed to accept 2 condominium units and 1 apartment unit known as D' Rapport Condominium Unit E-21-02 and Unit E-22-02 ("condominium units") and Palm Garden Apartment A-8-13A worth a total sum of RM 2,182,000.00 as full and final settlement sum of the services rendered by FPS.

iii. By way of a letter from FPS to the Defendant dated 11 November 2010 and a letter from the Defendant to FPS dated 10 May 2013, FPS agreed to name the above properties in the name of the Plaintiff as FPS nominee. Plaintiff and the Defendant then entered into 2 SPA for the properties which were dated 22 February 2011. The Defendant and FPS then subsequently entered into a Deed of Settlement dated 29 August 2013 and by way of a Letter of Release dated 17 September 2013, FPS was fully discharged as the Consultant Quantity Surveyors for the project.

[5] The trial took 1 day on 25 November 2024 and the Plaintiff called 2 witnesses and the Defendant called only 1 witness.

B. Decision Of The Court

[6] Parties have filed Issues to Be Tried and the decision of this Court is based on these issues.

I. Whether The Plaintiff Has Locus Standi To File The Suits?

[7] The Plaintiff submits that they have locus standi to file this suit because the SPA was entered between the Plaintiff and the Defendant. The Notice of Delivery of Vacant Possession was issued by the Defendant to the Plaintiff and no one else. At all material times, before the notice of demand being issued by the Plaintiff, there was no evidence whatsoever by the Defendant to suggest that the Plaintiff was not the purchaser of the said properties. By virtue of the said SPA, Plaintiff is the rightful owner of the said 2 properties.

[8] It is not disputed by parties as per para 5 of the Statement of Agreed Facts that Plaintiff was acting as a nominee or agent for FPS in signing the two SPAs.

"5. By way of a letter from JBFPS

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top