2009(8) Supreme 159
SUPREME COURT OF INDIA
Markandey Katju and Asok Kumar Ganguly, JJ.
M/s. Madnani Construction Corporation (P) Ltd. — Appellant
versus
Union of India & Others — Respondents
Civil Appeal No. 8385 of 2004
Decided on : 7-12-2009
Arbitration Act, 1940 – Interest Act, 1978 – Grant of interest – Validity of – Agreement entered into between appellant and North Eastern Railway for the construction of bridge island nos. 13 and 14 over Kosi river – Disputes arose between parties – Application filed by appellant for appointment of an arbitrator to settle disputes – Arbitrator gave his award holding that Railways should pay an amount of Rs.4,48,873.22 along with compoundable bank interest prevalent at that time from 16.11.1983 to 21.3.1992 – Award was made rule of court – Appeal – Partly allowed by High Court holding that Clause 16(2) of the GCC contains a provision against grant of interest. – High Court also relied on Clause 30 of SCC and Clause 52 of the GCC to hold that payment of interest had been barred – In the instant case relevant clauses, Clause 16(2) of GCC and Clause 30 of SCC not contained any prohibition on the arbitrator to grant interest- Hence, High Court was not right in interfering with the arbitrator’s award on matter of interest on basis of said clauses – On a strict construction of said clauses held that said clauses did not impose any bar on the arbitrator in granting interest – No interference called for with award passed by arbitrator – Impugned judgment of High Court set aside and award upheld – Appeal allowed. (Paras 53 to 59)
Facts of the Case :
An Agreement was entered into between appellant and North Eastern Railway for the construction of bridge island nos. 13 and 14 over Kosi river . Disputes arose between parties .An Application was filed by appellant for appointment of an arbitrator to settle disputes. General Manager of respondent Railways rejected appellant’s prayer for appointment of an arbitrator on the ground that the disputes were not arbitrable, as they fell under ‘expected matter’ in the contract.On application by appellant an arbitrator was appointed . Arbitrator gave his award holding that Railways should pay an amount of Rs.4,48,873.22 along with compoundable bank interest prevalent at that time from 16.11.1983 to 21.3.1992.Award was made rule of court. Appeal thereagainst was Partly allowed by High Court holding that Item Nos. 1 to 3 and 5 to 8 were excepted matters and were non-arbitrable and Arbitrator committed an illegality in allowing them.
2. Present appeal has been filed against said order of High Court.
Findings of the Court :
The arbitrator in his award after perusal of level Book No.1, Graph-Sheets, Logbook No. 1A and Logbook No.4 came to a clear finding that there were manipulations/alterations/over writings by railways and as a result of which volume of work done by the contactor had been reduced. Arbitrator is the master of facts. When the arbitrator on the basis of record and materials which were placed before him by railways came to such specific findings and which had not been stigmatized as perverse by High Court, High Court in reaching its conclusions could not ignore those findings. But in the instant case, High Court had come to said finding that items were excepted matters and non-arbitrable by completely ignoring the factual finding by arbitrator and without holding that those findings were perverse. In order to deny the claims of the contractor as covered under excepted matters, the procedure prescribed for bringing those claims under excepted matters must be scrupulously followed. The clear finding of arbitrator was that it had not been followed and High Court had not expressed any dis-agreement on that .Hence , the finding of High Court that those items were non-arbitrable could not be sustained.
JUDGMENT
Ganguly, J. —
1. The subject matter of challenge in this appeal is the judgment and order dated 29.04.2003 passed by the High Court of judicature at Allahabad in F.A.F.O. No. 40 of 1993, in a matter arising from the order dated 1.12.1992 of the learned Senior Civil Judge, making the Award a Rule of the Court, and whereby the High Court had partly allowed the Appeal filed by the respondent.
2. The appellant, a private limited company, is carrying on, inter alia, various construction works for both the State and Central Government and their undertakings. The appellant’s case is that an agreement dated 03.11.1981 was entered between the appellant and the North Eastern Railway for the construction of bridge island nos. 13 and 14 over the Kosi river. There were certain special conditions of the contract (hereinafter, SCC) and they stipulate that the General Conditions of Contract (hereinafter, GCC) and standard specifications of the North Eastern Railways shall form part of the aforesaid contract. In terms of the contract, the construction was to be completed by 15.02.1982. Certain payments were made to the appellant after completion of the contract but they were received by them “under protest”. Thus, disputes cropped-up between the parties. The appellant is said to have served a notice dated 16.11.1983 for the appointment of an arbitrator to settle the disputes. The General Manager of the respondent- Railways by an order dated 24.03.1986 rejected the appellant’s prayer for appointment of an arbitrator on the ground that the disputes were not arbitrable, as they fell under `expected matter’ in the contract.
3. On or about 18.08.1987, the appellant filed an application under Section 20 of the Arbitration Act, 1940 (hereinafter, the Act) before the Court of Addl. Civil Judge, Gorakhpur for appointment of an arbitrator which was transferred on 21st February, 1990, to the Court of Judge of Small Causes /Additional Civil Judge (hereinafter, the Court below). The Court below passed an order on 2.3.1990 that ‘file received, put up on the date fixed’. Then by an order dated 31.05.1991 the learned Civil Judge appointed one Mr. B. N. Shukla, the Sole Arbitrator, to adjudicate the disputes arising out of the agreement dated 03.11.1981. Against the order of appointment of arbitrator the responder approached the High Court by filing F.A.F.O. No. 534 of 1991 (the earlier F.A.F.O.), but the same was dismissed vide order dated 27.08.1991.
4. The learned Arbitrator gave his award on 13.4.1992 holding that the Railways should pay an amount of Rs.4,48,873.22 along with compoundable bank interest prevalent at that time from 16.11.1983 to 21.3.1992. In passing the award the Arbitrator relied on the Level book No. I, the Graph Sheets, the Log Book No. IA and the Log Book No. 4. The Arbitrator found that there were subsequent alterations and over writing in the entries made in the Log Book No.IA and the same were without any initials by the concerned authority on behalf of the respondent Railways. From such materials the Arbitrator held that all the manipulations/alterations/overwritings had resulted in reducing the quantities of the work done by the appellant. It was further observed that clause 21 (iv) of the special conditions was not followed by the respondent Railways at all. Moreover in utter violation of the Railway rules and orders on the subject, the measurements were hardly entered in the measurement book directly and mostly entries in the measurement books were copied down from subsidiary records or note books. After recording such findings, the Arbitrator gave the aforesaid award.
5. Thereafter on 08.05.1992 the appellant filed an application under Section 17 of the Act for pronouncing judgment and making decree according to the award.
6. On 20.5.1992 the respondent Railways filed application under Section 30 read with Section 33 (Section 30/33) of the Act before the Civil Judge for setting aside the award. Then on 24.08.1992 they
Executive Engineer (Irrigation), Balimela and Others Vs. Abhaduta Jena and Others [1988 (1) SCC 418]
Secretary, Irrigation Department, Government of Orissa and Others Vs. G.C. Roy, [1992 (1) SCC 508]
Hindustan Construction Company Limited vs. State of Jammu and Kashmir - (1992) 4 SCC 217
State of Orissa v. B.N. Agarwalla - (1997) 2 SCC 469
State of U.P. v. Harish Chandra and Company - (1999) 1 SCC 63
Board of Trustees for the Port of Calcutta v. Engineers-De-Space-Age, (1996) 1 SCC 516
Union of India v. Saraswat Trading Agency & others, JT 2009 (9) SC 648
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.