2010 Supreme(SC) 286

R.V.RAVEENDRAN, R.M.LODHA
State of Maharashtra – Appellant
Versus
Hindustan Construction Company Ltd. – Respondent


JUDGEMENT

R.M. Lodha, J.

Leave granted.

2. The question presented in this appeal by special leave is : whether in an appeal under Section 37 of the Arbitration and Conciliation Act, 1996 (for short ‘1996 Act’) from an order refusing to set aside the award, an amendment in the memorandum of appeal to raise additional/new grounds can be permitted.

3. M/s. Hindustan Construction Company Limited (respondent) and the State of Maharashtra (Irrigation Department, the Executive Engineer - appellant) entered into a contract on March 14, 1992 being ICB Contract No. II/1992 for the construction of civil work of Pressure Shafts and Power House Complex at Koyana Hydro Electric Project, Stage-IV. The contract work was completed by respondent within the extended period i.e., by March 31, 2000. However, it appears that disputes arose between the parties in respect of the work carried out by respondent in relation to (a) revision of percentages for hidden expenses, over breaks and profit for further additional cases of extract items/rate revision; (b) claim for extended stay at site; (c) revision of rate for Pressure Shaft excavation; (d) fixation of new rate on account of variation in the item














































Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon telegram-icon
whatsapp-icon Back to top