SUPREME COURT OF INDIA
T.S. THAKUR, CJI., R. BANUMATHI, J.
STATE OF JHARKHAND & ORS. – Appellants
Versus
M/S CWE-SOMA CONSORTIUM – Respondent
CIVIL APPEAL NO. 6125 OF 2016 (Arising out of SLP (C) No.19285 of 2015)
Decided On : 12-07-2016
(b) Government contract – Tender – Instant tender containing unapproved departures in clauses 4.5 (A) (b) and 4.5 (A) (c) from the clauses of the SBD – Resultantly only three bidders out of ten submitting bids – Even out of the three only respondent’s bid found responsive – Even then Tender Committee deciding to cancel the tender and go for fresh tender – Authority issuing tender not obliged to accept any tender, even the lowest one – Tendering authority will be within its rights to reject the tender without assigning any reason – Instantly Government assigning reasons for cancelling the tender – Point missed by High Court. (Para 9, 10, 12, 13)
(2007) 1 SCC 477; (2013) 5 SCC 182; (1996) 4 SCC 208 – Relied upon
(c) Government contract – Article 298, Constitution of India – Decision to enter into a contract or not – Subject only to the requirement of reasonableness under Article 14 – Instantly tender cancelled due to lack of real competition – There being only one responsive bid decision to cancel the tender and issue fresh tender not arbitrary or unreasonable. (Para 14)
(d) Government contract – High value Tender – CVC guidelines – Clause 4.17 and 4.18 r/w clause 4.5(A) (a) and clause 4.5 (A)(c) of NIT – NIT clauses found stringent – Bidding lacked competition – No error in decision of tender committee to cancel and re-invite tenders in the light of SBD norms. (Para 17, 18)
(e) Administration of justice – Judicial review – Court’s primary concern is to see whether there is any infirmity in the decision-making process or whether it is vitiated by mala fide, unreasonableness or arbitrariness – It is not appellate jurisdiction. (Para 18, 19)
(1994) 6 SCC 651 – Relied upon
(f) Government contract – Government must have freedom of contract – In absence of ant pleading of mala fide High Court could not sit in appeal over decision of the Tender Committee – Also, High Court ought not have deliberated on financial implications of fresh tender. (Para 20, 21)
(2005) 6 SCC 138; (1996) 4 SCC 208 – Relied upon
(g) Right to Fair Compensation and Transparency in Land Acquisition Rehabilitation and Resettlement Act, 2013 – Section 41 – Acquisition of land in scheduled areas to be made only as last resort – Proposed Icha-Kharkai Dam requiring acquisition of 20,421.43 acre of land in scheduled area – Tribal Advisory Council opining against such acquisition – Judgment of High Court directing (Para 22)
Facts of the case:
The proposed project, Kharkai Dam at Icha is a part of Subernarekha Multipurpose Project.
Government of Jharkhand, issued a Notice Inviting Tender (NIT) for the construction of the Dam as per the Standard Bidding Documents (SBD) dated 28.02.2014.
In the pre-bidding meeting ten tenderers participated wherein it was observed that in the clauses of the NIT, there were certain departures from the SBD.
After the pre-bid meeting only three bidders namely, M/s CWE-SOMA Consortium, Hyderabad (respondent herein), M/s. IL & FS Engineering and Construction Co. Ltd., Hyderabad and M/s. Navyuga Engineering Co. Ltd., Hyderabad submitted their bids.
Out of the three bidders, only the respondent was found responsive and other two bidders were found unresponsive. Therefore the tender committee took a decision under clause 4.18(d) of the Central Vigilance Commission Guidelines (‘CVC Guidelines’) to cancel the tender and go for retender to make the tender process more competitive.
The respondent made a representation against this decision which was forwarded by the Chief Minister to the Tender Committee. Aggrieved thereof, respondent filed a writ petition before the High Court.
The Single Judge allowed the writ petition, holding the action of the appellants as arbitrary and against public interest.
The Division Bench concurred with the conclusion of the Single Judge.
Finding of the Court:
Impugned judgment is liable to be set aside.
Result: Appeal allowed.
JUDGMENT
R. BANUMATHI, J.
Leave granted.
2. This appeal has been filed assailing the judgment dated 13.03.2015 of the High Court of Jharkhand dismissing the appellant’s Letters Patent Appeal No.309 of 2014, in and by which, the Division Bench affirmed the order of Single Judge directing opening of technical and financial bid of the respondent.
3. The matter in dispute relates to construction of a dam in the State of Jharkhand. The facts leading to filing of this appeal are as follows: The proposed project, Kharkai Dam at Icha is a part of Subernarekha Multipurpose Project, a Central Government Aided Scheme funded through the Accelerated Irrigation Benefits Programme (AIBP). Subernarekha Multipurpose Project is an Inter State project that was sanctioned in the year 1978 with the objective of providing irrigation in Jharkhand, Orissa and West Bengal. It will also provide water for drinking and industrial purpose as also for production of hydel power. The Water Resources Department, Government of Jharkhand, through its Executive Engineer issued a Notice Inviting Tender (NIT) for the construction of the Dam as per the Standard Bidding Documents (SBD) dated 28.02.2014. On 24.03.2014, a pre-bid meeting was held where ten tenderers participated and during its course, it was observed that in the clauses of the NIT, there were certain departures from the SBD. After the pre-bid meeting, in total, only three bidders namely, M/s CWE-SOMA Consortium, Hyderabad (respondent herein), M/s. IL & FS Engineering and Construction Co. Ltd., Hyderabad and M/s. Navyuga Engineering Co. Ltd., Hyderabad participated in the tender process and submitted their bids. In meetings of the Departmental Tender Committee held on 02.06.2014 and 06.06.2014, it was found that among the three tenderers, only the respondent was found responsive and other two bidders were found unresponsive. Therefore the tender committee took a decision under clause 4.18(d) of the Central Vigilance Commission Guidelines (‘CVC Guidelines’) to cancel the tender and go for retender to make the tender process more competitive. The tender committee re-affirmed this decision in a meeting held on 09.07.2014 after the Chief Minister referred an application of the respondent to them. Aggrieved thereof, respondent filed a writ petition before the High Court.
4. The learned Single Judge after examining clauses 4.17 and 4.18 of the CVC Guidelines which provide for procedure in case of a single quote/single valid acceptable quote and in case of lack of competition due to restrictive specifications respectively, came to the conclusion that in the absence of the decision of the tender committee that the specifications were stringent, clause 4.18 could not have been resorted to and tender committee should have resorted to clause 4.17. The Single Judge allowed the writ petition, holding the action of the appellants as arbitrary and against public interest. The matter was then carried in appeal filed by the appellants before the Division Bench by way of Letters Patent Appeal. The Division Bench upon perusal of the rationale for the decision of the tender committee, was of the view that there indeed existed competition as three companies, including the respondent had participated and respondent turned out to be the single bidder.
Thus, the Division Bench concurred with the conclusion of the Single Judge that only clause 4.17 should have been invoked. The Division Bench also noted that the initial tender value was estimated as Rs.698 crores for the tender floated in February 2014, and when second tender was floated in July 2014 within the short span of few months, the estimated value of the project had increased to Rs.738 crores. Thus, Division Bench dismissed the appeal holding that re-tendering at later stage would further enhance the estimated value, causing excessive loss to the state exchequer which may not be in the public interest. Being aggrieved, the State of Jharkhand has preferred the present
Rajasthan Housing Board v. G.S. Investments
Uttar Pradesh Avas Evam Vikas Parishad v. Om Prakash Sharma
Tata Cellular v. Union of India
Master Marine Services (P) Ltd. v. Metcalfe & Hodgkinson (P) Ltd.
The main legal point established in the judgment is the binding effect of the settlement between the parties, the waiver of the right to seek re-employment by the workmen, and the entitlement of the ....
A lockout is justified if it is declared in response to an illegal strike or a strike that is in breach of a settlement or award.
The combination of eyewitness testimonies, recovery of the weapon used, and forensic examination results can establish guilt in criminal cases, even based on circumstantial evidence.
The conviction of an accused person under Section 27(3) of the Arms Act is not permissible in law if the accused is also charged with committing murder under Section 302 of the Indian Penal Code.
The court can enhance compensation based on the deceased's income and family dependency, and adjust the multiplier used by the Tribunal if found unjustified.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.