IN THE HIGH COURT OF DELHI AT NEW DELHI
Vibhu Bakhru, J.
Shapoorji Pallonji And Co Pvt Ltd - Appellant
Versus
Rattan India Power Ltd & Anr - Respondent
Arbitration Petition No. 716 of 2019; I.A. No. 7836 of 2020
Decided On : 07-04-2021
ARBITRATION - APPOINTMENT OF ARBITRATOR - NOMINATION OF ARBITRATOR - APPOINTMENT OF ARBITRATOR BY COURT - POWER OF COURT - SECTION 11 OF THE ARBITRATION AND CONCILIATION ACT, 1996 - SCOPE AND APPLICABILITY - APPOINTMENT OF ARBITRATOR BY COURT - WHEN CAN BE MADE - CIRCUMSTANCES - PRINCIPLES - JUDICIAL REVIEW OF ARBITRATION AGREEMENT - SCOPE AND EXTENT - DOCTRINE OF GROUP OF COMPANIES - APPLICATION AND SCOPE - ALTER EGO DOCTRINE - APPLICATION AND SCOPE - ESTOPPEL - APPLICATION AND SCOPE - CONSTRUCTION OF ARBITRATION CLAUSE - PRINCIPLES.
Fact of the Case:
Petitioner, Shapoorji, entered into a contract with Respondent No. 2, Elena, for execution of Civil and Structural Works (BTG Works) at a thermal power plant being developed by Respondent No. 1, Indiabulls. The contract included an arbitration clause. Disputes arose, and Shapoorji issued a notice invoking arbitration. Indiabulls responded, contending that the contracts were separate and independent, and there was no arbitration agreement between Indiabulls and Shapoorji. Elena admitted the existence of an arbitration agreement for disputes under the BTG Contract but disputed the existence of any arbitration agreement for disputes arising from other contracts. Shapoorji filed a petition under Section 11 of the Arbitration and Conciliation Act, 1996 (A&C Act), seeking appointment of an arbitrator to adjudicate disputes relating to the BTG Contract and the BoP Contract (awarded to Shapoorji after termination of the contract with another agency).
Finding of the Court:
1. The court held that an arbitration agreement exists between Indiabulls and Shapoorji in respect of the BTG Contract. 2. The court found that Indiabulls was directly involved in the formation and execution of the BTG Contract, even though it was not a signatory to the contract. 3. The court applied the doctrine of 'Group of Companies' and held that Elena was a necessary and proper party to the arbitration proceedings. 4. The court also applied the 'Alter Ego' doctrine and held that Indiabulls and Elena were one and the same entity, and therefore, Indiabulls was bound by the arbitration agreement. 5. The court further held that Indiabulls was estopped from denying the existence of an arbitration agreement, as it had accepted the benefits of the contract and participated in the arbitration proceedings. 6. The court rejected Shapoorji's claim that disputes relating to the BoP Contract should be considered as additional items under the BTG Contract, as the BoP Contract was a separate contract and did not include an arbitration clause.
Issues: 1. Whether an arbitration agreement exists between Indiabulls and Shapoorji in respect of the BTG Contract. 2. Whether the doctrine of 'Group of Companies' can be applied to compel Indiabulls to arbitrate disputes arising from the BTG Contract. 3. Whether the 'Alter Ego' doctrine can be applied to compel Indiabulls to arbitrate disputes arising from the BTG Contract. 4. Whether Indiabulls is estopped from denying the existence of an arbitration agreement. 5. Whether disputes relating to the BoP Contract should be considered as additional items under the BTG Contract.
Ratio Decidendi: 1. The court held that an arbitration agreement exists between Indiabulls and Shapoorji in respect of the BTG Contract based on the following factors: (i) Indiabulls was directly involved in the formation and execution of the BTG Contract, even though it was not a signatory to the contract; (ii) Indiabulls had accepted the benefits of the contract and participated in the arbitration proceedings; (iii) Indiabulls was estopped from denying the existence of an arbitration agreement. 2. The court applied the doctrine of 'Group of Companies' to compel Indiabulls to arbitrate disputes arising from the BTG Contract, as Elena was a necessary and proper party to the arbitration proceedings. 3. The court applied the 'Alter Ego' doctrine to compel Indiabulls to arbitrate disputes arising from the BTG Contract, as Indiabulls and Elena were one and the same entity. 4. The court rejected Shapoorji's claim that disputes relating to the BoP Contract should be considered as additional items under the BTG Contract, as the BoP Contract was a separate contract and did not include an arbitration clause.
Final Decision: The court allowed the petition and appointed an arbitrator to adjudicate disputes relating to the BTG Contract. The court also directed the parties to nominate the third arbitrator within two weeks, failing which the parties were at liberty to approach the court for appointment of the third arbitrator.
JUDGMENT
Vibhu Bakhru, J. - The petitioner (hereafter referred to as 'Shapoorji'), a company incorporated under the Companies Act, 1956, has filed the present petition under Section 11 of the Arbitration and Conciliation Act, 1996 (hereafter the 'A&C Act'), inter alia, praying as under:-
"Appoint Hon'ble Mr. Justice C. K. Prasad (Retd.) Former Judge, Supreme Court of India, the Nominee Arbitrator already appointed by Respondent No.2 for the BTG contract, or any other person, as this Hon'ble Court may deem fit and proper as the Nominee Arbitrator on behalf of the Respondents for adjudication of the disputes that have arisen between the parties;"
2. Respondent no.1, previously known as Indiabulls Power Limited, (hereafter referred to as 'Indiabulls') was desirous of developing a 5x270 MW thermal power plant at Amravati, Maharashtra (hereafter referred to as the 'Project'). Respondent no. 2 (hereafter 'Elena') is a wholly owned subsidiary of Indiabulls.
3. On 19.05.2008, Indiabulls invited bids for execution of Civil and Structural Works, Boiler Turbine Generator Package (hereafter 'BTG Works'), which was a part of the Project. Shapoorji submitted its bid in response to the said invitation, which was subsequently revised. The revised bid was accepted and a Letter of Award (hereafter 'the LoA') dated 06.02.2010 for the contract of execution of the BTG Works at an estimated price of Rs. 180 Crores, was awarded to Shapoorji. The LoA was signed on behalf of Elena but the letterhead carried the name "Indiabulls".
4. Thereafter, on 26.03.2010 Shapoorji and Elena entered into the 'Contract for BTG Civil and Structural Works' (hereafter 'BTG Contract') for execution of BTG Works. The BTG Contract expressly included the LoA as one of the contract documents. The initial scope of work for the BTG Works was subsequently increased through twenty-one different amendments issued by Elena and the contract price for BTG Contract was changed to Rs. 189,18,87,147.07/- (Rupees One Hundred and Eighty-Nine Crores Eighteen Lakh Eighty-Seven Thousand One Hundred Forty-Seven and Seven Paisa only). The Work Order bearing Amendment No. 21 is dated 31.05.2017. The said Work Order also included an arbitration clause.
5. On 03.01.2012, Work Order for Civil and Structural work for Balance of Plant (BoP Contract) was issued to Shapoorji. Prior to that, on 29.10.2010, the contract for Civil and Structural work for the Balance of Plant (BoP Works) was entered into with Gannon Dunkerley & Co. Ltd. The respondents claim that Gannon Dunkerley & Co. could not complete the BoP Works. Shapoorji agreed to complete it; therefore, the same was offloaded to Shapoorji. Shapoorji claims that the BoP Contract was supplemental to BTG Works and therefore, is covered within the Dispute Resolution Clause under the BTG Contract.
6. On 14.01.2014, a Letter of Intent dated 14.01.2014 was issued by Indiabulls to Shapoorji for civil construction for RCC Bridges.
7. On 18.10.2012, a Work Order bearing No. 332003859 (DG Contract) was awarded to Shapoorji for arrangement of DG Sets.
8. Disputes have arisen in respect of execution of the works and rendering of services under the aforementioned Contract(s). In view of the said disputes, Shapoorji issued a notice invoking arbitration in respect of (i) Letter of Award dated 06.02.2010 (BTG Contract); (ii) Work Order no. 3451000221 dated 03.01.2012 (BoP Contract), awarded to Shapoorji for Balance of Plant Works (BoP Works); (iii) Work Order bearing No. 3382003859 dated 18.10.2012, awarded to Shapoorji for arrangement of DG Sets (DG Contract); and (iv) Letter of Intent dated 14.01.2014 issued by Indiabulls to Shapoorji for civil construction of 4 RCC Bridges (RCC Contract).
9. Shapoorji nominated Justice (Retd.) A.K. Sikri, a former Judge of the Supreme Court as an arbitrator and called upon Indiabulls and Elena to jointly nominate an arbitrator.
10. Indiabulls responded to the said notice by a letter dated 23.10.2019 contending that the Contract(s)/ Wo
Ameet Lalchand Shah vs. Rishabh Enterprises
Cheran Properties Ltd. vs. Kasturi & Sons Ltd
Chloro Controls (India) (P) Ltd. vs. Severn Trent Water Purification Inc.
Dozco vs. Doosan Infracore Co. Ltd
Fuerst Day Lawson Limited vs. Jindal Exports Limited
Mahanagar Telephone Nigam ltd. vs. Canara Bank
SEI Adhavan Power (P) Ltd. vs. Jinneng Clean Energy Technology Ltd.
An arbitration agreement may exist between parties even if one of the parties is not a signatory to the contract, based on factors such as direct involvement in the formation and execution of the con....
The main legal point established in the judgment is the importance of party autonomy in arbitration, the enforceability of the entire arbitration clause, and the conditional acceptance of arbitration....
An application for leave to defend in a summary suit constitutes the 'first statement on the substance of the dispute' under the Arbitration and Conciliation Act. Participating in court proceedings b....
subject matter of suit cannot be bifurcated by leaving one portion of the dispute to be decided in the suit while referring part of a dispute between the parties to the Partnership Deed containing th....
A binding arbitration agreement exists despite challenges to the validity of accompanying contracts, with disputes to be resolved by an appointed arbitrator.
A non-signatory to an arbitration agreement cannot invoke the arbitration clause of the agreement to which it is not a party.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.