IN THE HIGH COURT OF JUDICATURE AT MADRAS
M. SUNDAR, K. GOVINDARAJAN THILAKAVADI, JJ.
N. Jayamurugan – Appellant
Versus
M/s. Saravana Global Holdings Ltd. – Respondent
O.S.A. (CAD) No. 142 of 2023
Decided On : 30-10-2024
JUDGMENT :
K. GOVINDARAJAN THILAKAVADI, J.
1. This is an Appeal under Section 37 of the Arbitration and Conciliation Act, 1996, (hereinafter ‘the Act’) against the order dated 21.07.2023 passed by the learned Single Judge of this Court in O.P. No. 595 of 2019, whereby the application preferred by the respondent herein under Section 34 of the Act for setting aside the award dated 20.02.2019 of the Sole Arbitrator was allowed.
2. The claimant before the Arbitral Tribunal is the appellant and the respondent herein is the counter claimant before the Arbitral Tribunal.
3. The present dispute arises out of a Memorandum of Understanding dated 18.05.2006 entered between the appellant and respondent for purchasing immovable properties measuring about 200 acres at Moosivakkam Village, Kancheepuram. As per the terms of agreement the appellant paid a sum of Rs.50,00,000/- as advance and thereafter, made payments on various dates to the respondent for the said purpose. Since the respondent failed to comply with the terms of agreement, the appellant initiated Arbitral proceeding for the following reliefs:
(B) Award interest at the rate of 24% per annum compounded annually from 01.04.2007 till the date of realization.
(C) Directing the respondent to pay the compensation at Rs.1,00,000/- (Rupees One Lakh only) per acre of shortfall as envisaged under the MOU dated 18.05.2006.
4. The respondent herein resisted the claim as barred by limitation and sought for counter claim in the statement of the defence. The same is extracted as hereunder:
(ii) Direct the claimant to pay a sum of Rs.1,42,89,000/- (Rupees One Crore Forty Two Lakhs Eighty Nine Thousand only) or such other sum as determined by this Hon’ble Tribunal to the respondent along with interest at 24% per annum from the due date till date of payment.
5. The Learned Arbitrator framed 9 issues. The Appellant had examined himself as CW-1 and on behalf of the Respondent, Mr. Padam Challani was examined as R.W.1. On the side of the Appellant, 17 documents were marked as Exhibits C.1 to C.17 and on the side of the Respondent, 21 documents were marked as Exhibits R1 to R21.
6. The Sole Arbitrator after hearing the respective parties pronounced the award dated 20.02.2019 directing the respondent to pay a sum of Rs.6,48,35,500/- with interest at the rate of 9% per annum from 27.04.2012 till the date of award and in the event of the said amount not being paid within a period of two months from the date of award, the respondent was directed to pay interest at the rate of 18% per annum on the sum of Rs.6,48,35,500/- from the date of award till the date of realization.
7. Under the Arbitral award 20.02.2019, the learned Arbitrator has decided the issue of limitation in favour of the appellant on the following premises:
(2) The claim is not barred by limitation and that it would be covered under Section 25(3) of the Indian Contract Act, 1872.
8. Aggrieved against the award dated 20.02.2019 of the learned Sole Arbitrator, the respondent herein preferred an application under Section 34 of the Act before the Commercial Division of this Court, which was registered as O.P. No. 595 of 2019.
9. The proceedings under Section 34 of Arbitration and Conciliation Act of 1996 was initiated assailing the Arbitral award dated 20.02.2019 broadly on two grounds, namely:
2. The learned Arbitral Tribunal has exceeded the scope of its reference as well as the MOU and allowed the claim.
1
Ethirajulu Naidu Vs. Chinnikrishnan Chettiyar
Juggilal Kamlapat V. NV Internationale
K.M. Suresh Babu Vs. Sundaram Finance Limited
Kotak Mahindra Bank Ltd. Vs. Kew Precision Parts Private Limited
Ssangyong Engineering & Construction Co. Ltd. Vs. National Highways Authority of India (NHAI)
The court affirmed that a promise to pay a time-barred debt under Section 25(3) of the Indian Contract Act can revive the claim, and the Arbitrator's findings were not subject to re-evaluation under ....
Claims in arbitration must adhere to statutory limitation periods; failure to comply renders them non-maintainable, emphasizing the strict nature of limitation under arbitration law.
The acknowledgment of liability extends the limitation period for claims, while counterclaims not acknowledged are barred by limitation.
Arbitration awards under Section 34 are upheld unless they contradict fundamental policies of Indian law or evidence patent illegality; acknowledgments of liability in balance sheets extend the limit....
The court reaffirmed the limited scope of judicial review of arbitral awards under Sections 34 and 37 of the Arbitration and Conciliation Act, emphasizing that courts cannot reappraise evidence or in....
The court can set aside an arbitral award under Section 34 if it violates substantive law, contract terms, or public policy, especially when procedural requirements aren't met or if the award is pate....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.