IN THE HIGH OF MADHYA PRADESH
(FULL BENCH)
Sushil Harkauli, Ag. C.J., Alok Aradhe, Mrs. Vimla Jain,
M.A. Siddiqui and T.K. Kaushal, JJ.
Sanjay Dubey v. State of M.P. and another
Civil Revisions No.1343 of 2003, 640 of 2005, 481 of 2006, 178 of 2008 and 179 of 2008 (Jabalpur) : against orders passed by the M.P. Arbitration Tribunal, Bhopal;
Decided on 17.9.2012.
Held : The Tribunal gets the jurisdiction to adjudicate the dispute under the Act, but for the Act, it would have no jurisdiction to adjudicate the dispute in relation to works contract. It is well settled in law that where a Tribunal derives its jurisdiction from the statute that creates it and that statute also defines the conditions under which the Tribunal can function, it goes without saying that before that Tribunal assumes jurisdiction in a matter, it must be satisfied that the conditions requisite for its acquiring seisin of that matter have in fact arisen. Wherever jurisdiction is given to a Court by an Act of Legislature and such jurisdiction is only given upon certain specified terms contained in the Act it is a universal principle that these terms must be complied with, in order to create and raise the jurisdiction for if they be not complied with, the jurisdiction does not arise. AIR 1979 SC 404, (2008)7 SCC 487 and (2011)8 SCC 656 followed. 2006(1) JLJ 322, Civil Revision No.240 of 2012, 2000(3) MPLJ 21 and 2005(4) MPLJ 16 partly overruled. AIR 1953 SC 394 referred to.
ifjlhek vf/kfu;e] 1963 && vuq- 113 && lafonk vf/kfu;e] 1872 && /kkjk 28 && e-iz- ek/;LFke~ vf/kdj.k vf/kfu;e] 1983 && /kkjk 7[k¼1½ rFkk 7[k¼2d½ && vf/kdj.k dh vf/kdkfjrk && ladeZ lafonk ds fuca/kuksa ds v/khu ;Fkk micaf/kr izkf/kdkjh rd igq¡pus ds i’pkr~ gh voyafcr dh tk ldrh gS && ifjlhek vf/kfu;e ds mica/k djkj ds v/khu izkf/kdkfj;ksa ij ykxw ugha D;ksafd os U;k;ky; ugha gSaA vfHkfu/kkZfjr % vf/kdj.k dks vf/kfu;e ds v/khu fookn dk vf/kfu.kZ; djus dh vf/kdkfjrk gS] ijarq vf/kfu;e ds fy,] bls ladeZ lafonk ds laca/k esa fookn dk vf/kfu.kZ; djus dh dksbZ vf/kdkfjrk ugha gksxhA fof/k ds vuqlkj ;g lqLFkkfir gS fd tgk¡ vf/kdj.k ml dkuwu ls viuh vf/kdkfjrk izkIr djrk gS tks mls l`ftr djrk gS rFkk og dkuwu mu ‘krksZa dks Hkh ifjHkkf”kr djrk gS ftuds v/khu vf/kdj.k dk;Z dj ldrk gS] ogk¡ Li”V gS fd ekeys esa ml vf/kdj.k ds vf/kdkfjrk j[kus ds iwoZ bldk lek/kku gksuk pkfg, fd ml ekeys dk dCtk izkIr djus ds fy, vko’;d ‘krsZa okLro esa mRiUu gks pqdh gSaA tgk¡ dgha U;k;ky; dks fo/kkueaMy ds vf/kfu;e }kjk vf/kdkfjrk nh tkrh gS rFkk ;g vf/kdkfjrk ml vf/kfu;e esa varfoZ”V dfri; fofufnZ”V fuca/kuksa ij gh nh tkrh gS] ogk¡ ;g loZO;kih fl)kar gS fd vf/kdkfjrk ds l`tu rFkk mRiUu djus ds fy, bu fuca/kuksa dk vuqikyu gksuk gh pkfg, D;ksafd ;fn budk vuqikyu u fd;k tk, rc vf/kdkfjrk mRiUu ugha gksrh gSA , vkb vkj 1979 ,l lh 404] ¼2008½7 ,l lh lh 487 rFkk ¼2011½8 ,l lh lh 656 vuqlfjrA 2006¼1½ ts ,y ts 322] flfoy iqujh{k.k dz-240 lu~ 2012] 2000¼3½ ,e ih ,y ts 21 rFkk 2005¼4½ ,e ih ,y ts 16 vkaf’kd :i ls myVs x,A , vkb vkj 1953 ,l lh 394 fufnZ”VA
Aradhe, J. -- 1. In this batch of civil revisions the orders passed by the Madhya Pradesh Arbitration Tribunal, Bhopal (hereinafter referred to as the ‘Tribunal’) have been challenged by which the Tribunal has dismissed the reference petitions on the ground that petitions have been presented beyond the period of three years from the date of accrual of cause of action, which is barred by limitation as provided under Article 113 of the Indian Limitation Act, 1963. A Division Bench of this Court vide order 3.8.2007 passed in C.R. No.1343/2003 expressed the doubt with regard to correctness of the view taken by another Division Bench in the case of M/s. Sermen (India) Road Makers Pvt. Ltd. v. State of M.P. and others [2005(3) MPHT 292 (DB)]. The Division Bench thereafter referred five questions for consideration before the Full Bench. The Full Bench vide order dated 27.10.2009 while answering the aforesaid questions, doubted the correctness of the view taken by another Full Bench in the case of State of M.P. and another v. Kamal Kishore Sharma [2006(1) JLJ 322=2006(1) MPHT 565 (DB)], and was of the opinion that decision in Kamal Kishore Sharma (supra), requires consideration by the larger Bench as in the aforesaid case the Full Bench has not taken note of the decision of Supreme Court in the case of State of M.P. and another v. K.K. Shukla and Co. [(2001)10 SCC 194], and has not scanned clause 29 in its entirety. It was further held that Full Bench has not adverted to a case where the agreement does not contain a clause like clause 29. In the aforesaid factual background the matter has come up before this Bench.
2. Learned counsel for the applicants submitted that in the case of Kamal Kishore Sharma (supra), the Full Bench has not considered clause 29 of the Agreement in its entirety as well as the effect of section 28 of the Contract Act, 1872. It was further submitted that the time limit prescribed in clause 29 for approaching the Superintending Engineer as well as Chief Engineer is administrative in nature and cannot be treated as mandatory and even if an aggrieved person does not approach either Superintending Engineer or Chief Engineer, as stipulated in clause 29 of the agreement, he can still approach the Tribunal under section 7 of the Madhya Pradesh Madhyastham Adhikaran Adhiniyam (hereinafter referred to as the ‘Act’). It was also submitted that in view of section 2A of section 7B of the Act, an aggrieved person can approach the Tribunal within a period of three years without approaching the authorities mentioned in the works contract. It was also urged on behalf of the applicants that provisions of Limitation Act, 1963 would apply to the authorities mentioned in clause 29 i.e. Superintending Engineer and Chief Engineer and, therefore, an aggrieved person can approach the Superintending Engineer as well as Chief Engineer within a period of three years as provided under Article 113 of the Limitation Act. Learned counsel for the applicants in support of the aforesaid submissions has placed reliance on the decisions rendered in the cases of National Insurance Co.Ltd. v. Sujir Ganesh Nayak and Co. and another [(1997)4 SCC 366], and P.C. Rajput v. State of M.P. [1993 JLJ 423=1994 MPLJ 387].
3. On the other hand, learned Deputy Advocate General for the State has submitted that under section 7B(2A) of the Act, as amended with effect from 29.8.2005, an aggrieved person has to approach the Tribunal within a period of three years from the date on which the works contract is terminated, foreclosed, abandoned or comes to an end in any other manner or when the dispute arises during the pendency of the works contract.
4. We have considered the respective submissions made by learned counsel for the parties. The precise issue involved in view of the order of reference dated 27.10.2009 passed by the Full Bench is about the period within which a reference can be made by an aggrieved person before the Tribunal constituted under the Act. Th
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.